Vastu Vihar Phase-2 is a RERA-registered real-estate project in Gorakhpur (RERA ID UPRERAPRJ12487). Its RERA-registered completion deadline (21 Dec 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ12487 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 25 Jul 2017 |
| Original start | 21 Dec 2015 |
| Project duration | 83 |
| Address | Gorakhpur, Gorakhpur |
| RERA registered | 31 Oct 2017 |
| Promised completion | 21 Dec 2023 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹29,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 29,742 | 44–44 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 296/2015 | 21 Dec 2015 | 21 Dec 2020 | 21 Dec 2023 |
| Khasra | Area | Type |
|---|---|---|
| 379 | 117 DISMIL | — |
| 379 | 4743.21 | Khasra |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 4154 | 27 Apr 2016 | — | — |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
Yes. Vastu Vihar Phase-2 is registered with UPRERA under registration number UPRERAPRJ12487, registered on 31 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Vastu Vihar Phase-2 is 32 months past the completion date filed with UPRERA (21 Dec 2023), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Vastu Vihar Phase-2 is registered in Gorakhpur, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗