Krishna Greens

UPRERARegistered

Krishna Greens is a RERA-registered residential project by Krishna Greens Developers in Mauza Kota, Mathura (RERA ID UPRERAPRJ637082). Registered with a completion deadline of 28 Oct 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
6%Q3'25
20%Q4'25
44%Q1'26
57%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ637082
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMathura-Vrindavan Development Authority
Proposed start23 Sept 2024
Project duration62 months
AddressKhasra No. 104, 105, 106, 109, 115, 116 & 117, Mauza Kota, Mathura, Mathura
TehsilMathura
Applicant typePartnership Firm
Applicant addressKrishna Orchid Goverdhan Road Mathura
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MVDA/LD/23-24/1602

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered7 Mar 2025
Original completion28 Oct 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹81,000
Sanctioning authorityMathura-Vrindavan Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
KANCHANA AGRAWAL
License CA/2016/78675
BBC COMPANY, OPP. BSA COLLAGE, MATHURA
Engineer
MUKUL SHARMA
SPACE DESIGNERS AND ARCHITECTS, 104-F, PUNEET VRINDAVAN, SANJAY PLACE, AGRA
Contractor
V. D. CONSTRUCTIONS
54, GANESHRA SPORTS STADIUM, GOVERDHAN MARG, MATHURA UP 281004
Sr.Development work declared to RERA
1Demarcation of Plots
NA
2Boundary Wall
230 mm Wall in brick massonary with FPS bricks of class designation 75 in ratio of 1:6 cement mortar or RCC footing and colum structure.
3Road Work
Laying of roads with Proper longitudinal and Cross-sectional road slopes in Cobble Stoneover well compacted subgrade with 75 mm and 50 mm layers of send.
4Footpaths
Laying of designing Tiles of 40 mm over well compacted subgrade with GSB layers.
5Water Supply Including Drinking Water Facilities
Laying of 50, 65, 80 (OD) UPVC Fresh Water Supply Line from Underground Tank to individual plots with Proper Air Valve, Sluice Valve in Chambers, Scour Valve and Fire Brigade Outlet Connection at Underground Tank, as per MEP drawings.
6Sewer System
Laying of SN-4 Pipes DWC pipes and making of circular manholes and retangular manhole of size 900 x 800 mm with 600x600 MM Manhole cover for main line with proper finished for formulation level, Invert level of menhole and Connection to individual plots, as per Mep drawings.
7Drain
Laying of DWC/RCC NP-3 pipes for storm water drainage throughout the project with circular Manholes and retangular catch basins of size 700 X 700 on main line, rectangular catch basin of size 450 X 450 X 450 for individual plots (In plot owner schope), de-silting chamber of dia 1.5 M and recharge Well Size 1.2 Dia. in coordination with finished formation Levels, invert level of manhole and flow rate, as per MEP drawings.
8Parks
Landscaping of the parks with plantation including trees, shrubs and ground covers and recreational areas with benches, sports facilities such as badminton court, mini-basketball court and walkway.
9Tree Planting
Tree Plantation of Turmal Elia, ficus Panda and palm trees throughout the project in the park and on roadside to provide shade, as per landscaping drawings.
10Design For Electric Supply Including Street Lighting
Laying of overhead HT and LT cables from Main electricity board connection to Transformers and upto plots for individual connections which shall we be directly obtained by the plot owners from the electricity board along with fixing of 30 w and 50 w street light on the 9 m and 11 m Steel tubular poles with provision of required capacity Transformers as per UPPCL guidelines
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Contruction of STP collection tank along with modular treatment system and laying of dwc pipe from STP to individual plots and green areas for flushing and ingration as per mep drawings and overflow discharge connection to the government dain
13Solid Waste Management And Disposal System
NA
14Water Conservation System
Installation of Rain Water Harvesting pits for percolation of rainwater to maintain the local ground water levels as per approve layout from MVDA and laying of severage treated water supply line to plots and green areas for flushing and irrigation as per mep .
15Energy Management System Including Use of Renewable Energy
Electrification as per approved drawing by the UPPCl.
16Fire Protection And Fire Safety System
NA
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
NA
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 28 Oct 2029.

Sanctioned by Mathura-Vrindavan Development Authority · 15,176 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MVDA/LD/23-24/160223 Sept 202428 Oct 202927 Oct 203228 Oct 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1041505.64Khasra
105900Khasra
106,1081800Khasra
1092700Khasra
115640.74Khasra
1163350Khasra
1174280Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 1234
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7956
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 23164
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9253
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 5407
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 12202
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 12202
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 12242
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New3 Feb 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New3 Feb 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Feb 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New3 Feb 2025 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New3 Feb 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New3 Feb 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New3 Feb 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New3 Feb 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New4 Feb 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New4 Feb 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New20 Feb 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New3 Feb 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New3 Feb 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New4 Feb 2025 ↗

Quarterly progress reports

9 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

9 quarterly progress reports are on file with UPRERA, covering 2024-Q2 to 2026-Q2.

QuarterConstructionCertificates
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q26%CA ↗ · Arch ↗ · Eng ↗
2025-Q320%CA ↗ · Arch ↗ · Eng ↗
2025-Q444%CA ↗ · Arch ↗ · Eng ↗
2026-Q157%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameKrishna Greens Developers
RolePromoter · current
RERA IDUPRERAPRM224298
PANAAYFK5831H
CIN / TANAGRK12606G
Registered addressKrishna Orchid Goverdhan Road Mathura
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Mathura

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
KRISHNA GREENS DEVELOPERS COLLECTION ACCOUNT FOR KRISHNA GREENSBankCANARA BANKBranchMATHURA MAIN BRANCHBranch address1018/B, CHOKI BAG BAHADUR ROAD MATHURA HO. UP 281001Branch districtMathuraA/C no.IFSCCNRB0000198Branch emailcb0198@canarabank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
KRISHNA GREENS DEVELOPERS SEPARATE BANK AC FOR KRISHNA GREENSBankCANARA BANKBranchMATHURA MAIN BRANCHBranch address1018/B CHOUKI BAG BAHADUR ROAD MATHURA H. O. UP 281001Branch districtMathura, Uttar PradeshA/C no.IFSCCNRB0000198
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
KRISHNA GREENS DEVELOPERS RERA TRANSACTION AC FOR KRISHNA GREENSBankCANARA BANKBranchMATHURA MAIN BRANCHBranch address1018/B, CHOUKI BAG BAHADUR ROAD MATHURA H.O. UP 281001Branch districtMathura, Uttar PradeshA/C no.IFSCCNRB0000198
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Krishna Greens

Is Krishna Greens RERA registered?

Yes. Krishna Greens is registered with UPRERA under registration number UPRERAPRJ637082, registered on 7 Mar 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Krishna Greens?

The completion date filed with UPRERA is 28 Oct 2029. No completion certificate is on record yet.

Who is the builder of Krishna Greens?

Krishna Greens Developers is the promoter entity that filed Krishna Greens with UPRERA (promoter RERA ID UPRERAPRM224298). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Krishna Greens have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Krishna Greens located?

Krishna Greens is registered in Mauza Kota, Mathura, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗