Registered31 Jul 2017
Completed26 Sept 2019
Promised25 Feb 2022

Timeline

Promised completion25 Feb 2022
Revised completion25 Feb 2022
Actual completion26 Sept 2019
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹5,870
Project cost (in ₹ Lakhs)₹1,900 Lakhs
Project duration95 months
Project categoryResidential
Locality
Original start date25 Aug 2014
Proposed start date29 Sept 2014

Inventory

Total units114
Unit TypeUnitsCarpet Area (sqm)
2 BHK8061.032–74.784
3 BHK3486.511

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9953283333
Emailinfo@mccdevelopers.in
Coordinator9953283333
AddressMr. Nirmal Jain - Flat no. 3, 2nd Floor, W-130, Greater Kailash - II, New Delhi - 110048 Mr. Manish

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
89/GH/ZONE-1/15-166 May 20175 May 202225 Feb 20225 May 2022

Land Parcels

Khasra No.AreaPlot Type
9762150Khasra
977806.84Khasra
98111222.1342Khasra

Approved Unit Plan

Unit plan rows on file57
Total flats (sum of rows)114
BlocksT4
Floor types2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of MCC Signature Heights - Phase II?

The RERA registration number of MCC Signature Heights - Phase II is UPRERAPRJ4158, as recorded on the UP-RERA portal.

What is the RERA status of MCC Signature Heights - Phase II?

As reported by UP-RERA, the status of MCC Signature Heights - Phase II is "Registered".

Where is MCC Signature Heights - Phase II located?

As reported to UP-RERA, MCC Signature Heights - Phase II is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is MCC Signature Heights - Phase II completed?

As reported to UP-RERA, MCC Signature Heights - Phase II was completed on 26 Sept 2019.

Is MCC Signature Heights - Phase II delayed?

Measured against the latest completion date reported to UP-RERA, MCC Signature Heights - Phase II is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026