Registered2 Apr 2019
Promised25 Feb 2022
Revised24 Aug 2022
Completed4 Aug 2023

Timeline

Promised completion25 Feb 2022
Revised completion24 Aug 2022
Actual completion4 Aug 2023
Possession delay11 mo delay

Registration & Cost Details

Registration fee (in ₹)₹9,920
Project cost (in ₹ Lakhs)₹3,340 Lakhs
Project duration79 months
Project categoryResidential
Locality
Original start date
Proposed start date31 Jan 2017

Inventory

Total units165
Unit TypeUnitsCarpet Area (sqm)
2 BHK9561.032–74.784
3 BHK5474.784–106.618
4 BHK16121.725

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9953283333
Emailinfo@mccdevelopers.in
Coordinator9953283333
AddressMr. Nirmal Jain - Flat no. 3, 2nd Floor, W-130, Greater Kailash - II, New Delhi - 110048 Mr. Manish

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
89/GH/Zone-1/15-166 May 20175 May 202225 Feb 20225 May 2022
89/GH/Zone-1/15-16

Revalidated: 89/GH/Zone-1/15-16 (6 May 2017)

6 May 20175 May 2022

Revalidated upto: 8 Sept 2023

24 Aug 20227 Sept 2025

Land Parcels

Khasra No.AreaPlot Type
9762150Khasra
97780.84Khasra
98111222.1342Khasra

Approved Unit Plan

Unit plan rows on file108
Total flats (sum of rows)165
BlocksT5, T6
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of MCC Signature Heights - Phase III?

The RERA registration number of MCC Signature Heights - Phase III is UPRERAPRJ250301, as recorded on the UP-RERA portal.

What is the RERA status of MCC Signature Heights - Phase III?

As reported by UP-RERA, the status of MCC Signature Heights - Phase III is "Registered".

Where is MCC Signature Heights - Phase III located?

As reported to UP-RERA, MCC Signature Heights - Phase III is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is MCC Signature Heights - Phase III completed?

As reported to UP-RERA, MCC Signature Heights - Phase III was completed on 4 Aug 2023.

Is MCC Signature Heights - Phase III delayed?

Measured against the latest completion date reported to UP-RERA, MCC Signature Heights - Phase III is 11 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026