Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
67%Q3'24
73%Q4'24
84%Q1'25
88%Q2'25
93%Q3'25
100%Q4'25
105%Q1'26
107%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7477
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Aug 2016
Original start1 Aug 2016
Project duration125 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressA-133, Sector-63, Noida, Gautam Buddh Nagar (Uttar Pradesh)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Permit revalidated (2)

  3. 3 building permits sanctioned

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

  9. Completion certificate filed

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Aug 2017
Original completion31 Jul 2021
Revised completion20 Dec 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary22 Dec 2025
Registration fee₹1,06,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors972 · 6 · 24 (units from plan)
Homes · commercial units939 · 33 (shops and offices filed in the same plan)
  • 2 BHK638 66%
  • 3 BHK262 27%
  • PENTHOUSE39 4%
  • SHOP33 3%
ConfigurationUnitsCarpet area
2 BHK63855-67
3 BHK26280
PENTHOUSE3987-119
SHOP334-31
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CASCADE · 2 BHK, PENTHOUSE, 3 BHK2217155-117
COMMERCIAL · SHOP2334-31
FONTANE · 2 BHK, PENTHOUSE, 3 BHK2419255-117
LAGOON · 2 BHK, PENTHOUSE, 3 BHK2419255-117
NLV · 2 BHK, 3 BHK, PENTHOUSE2419255-119
SLV · 2 BHK, 3 BHK, PENTHOUSE2419255-119
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
M/s Confluence (Mr. Vishal Sharma)
License CA/1998/23261
B-21, New Friends Colony, New Delhi
Engineer
M/S Mehro Consultants
A-1/36, Safdarjung Enclave, New Delhi
Contractor
M/s Progressive Buildcon Pvt. Ltd.
H-20, Sector 63, Noida
Sr.Development work declared to RERA
1Demarcation of Plots
Not Applicable
2Boundary Wall
RCC and Brick Work with wire fencing.
3Road Work
6 M Wide Roads with Paved Surface and Paved
4Footpaths
Landscapeed /paved Pathways
5Water Supply Including Drinking Water Facilities
Potable water supplied by Municipal Authority stored in underground and overhead tanks provided on top of each tower
6Sewer System
Sewage system provided with adequate capacity of STP for treatment of effluents
7Drain
Surface Drainage system provided with provision of harvesting rainwater from building terrace
8Parks
adequate no. of Parks provided in central landscapped area with shading trees, pathways & Kids play area along with water bodies
9Tree Planting
Native tree plantation as per gold rated green building standards by IGBC provided in central area as well as periphery of the plot
10Design For Electric Supply Including Street Lighting
HT & LT Electric supply as per load demand of the complex provided with meter room, Transformers, HT Panel, LT Panel along with adequate DG Sets for power backup
11Community Buildings
Cetral Club/ Community building provided wth facility for indoor games , Gymnasium and swimming pool etc
12Treatment and Disposal System of Sewage and Sullage water
Sewage Treatment plant of adequate capacity provided in basement area for effluents. Water discharged from Plant used for landscaping/horticuture
13Solid Waste Management And Disposal System
Door to door collection of Solid waste planned along with engagement of specialized agency for disposal of all collected solid waste
14Water Conservation System
Water conservation measures as per Gold rated Green Building standards proposed such as installation of Irrigation system, Low flow fixtures etc
15Energy Management System Including Use of Renewable Energy
Renewable energy usage proposed in common area as per Gold rated Green building standards with Solar PV generation or Solar water Heating syatems.
16Fire Protection And Fire Safety System
Fire Hose Reels, Fire alarm system, Sprinklers, fire Extinguishers provided in each building satisfying all fire norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
Commercil area along with central club provided as social amenties
18Emergency Evacuation Services
Emergency exits, fire exits provided in each tower at ground floor with adequate signages.
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1PROPCASA CONSULTANCY PVT. LTD.UPRERAAGT10038
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 21 Dec 2021. 2 of them carry a revalidation, the latest valid to 21 Dec 2026.

Sanctioned by Greater Noida Authority · 20,121 sqm of land · an approved plan of 6 blocks and 972 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Letter No. PLG(BP) 3608/69 Dated 22-12-201622 Dec 201621 Dec 202121 Dec 202631 Jul 2021—
PLG(BP) 3608/6922 Dec 201621 Dec 202121 Dec 202629 Oct 202322 Dec 2016
valid to 21 Dec 2026
NIYO/2024/BP-3608/153422 Dec 201621 Dec 202121 Dec 202629 Oct 202322 Dec 2016
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 20 Dec 2026.

#Granted fromExtended uptoNote
131 Jul 202130 Jan 2022Six months extension in view of force majeure caused by covid-19 pandemic
230 Jan 202229 Oct 2023—
329 Oct 202320 Dec 2026—

Land & documents

23 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-05A, Sector 16B, Greater Noida20120.63—
GH-05A, Sector 16B, Greater Noida20121Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 21 Mar 2016.

Registry no.DateTypeArea
586421 Mar 2016self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 5864
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New29 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New30 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Aug 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old31 Jul 2017 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old31 Jul 2017 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
Old31 Jul 2017 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old31 Jul 2017 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old31 Jul 2017 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old31 Jul 2017 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old31 Jul 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old31 Jul 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAs per NBC Norms
Fire safety (as filed with RERA)As per NBC Norms
Health serviceAs per NBC Norms
Renewable energyAs per Sanctioned Plan
Other facilitiesAs per Sanctioned Plan

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q454%CA ↗ · Arch ↗ · Eng ↗
2024-Q161%CA ↗ · Arch ↗ · Eng ↗
2024-Q267%CA ↗ · Arch ↗ · Eng ↗
2024-Q373%CA ↗ · Arch ↗ · Eng ↗
2024-Q484%CA ↗ · Arch ↗ · Eng ↗
2025-Q188%CA ↗ · Arch ↗ · Eng ↗
2025-Q293%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4105%CA ↗ · Arch ↗ · Eng ↗
2026-Q1107%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameDecent Buildwell Pvt. Ltd.
RolePromoter · current
RERA IDUPRERAPRM14449
PANAAECD4761A
CIN / TANU70102UP2012PTC053213
Name of chairmanSuresh Chand Kaushik
Registered addressA-133, Sector-63, Noida, Gautam Buddh Nagar (Uttar Pradesh)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Decent Buildwell Pvt. Ltd.BankICICI BankBranchSector 63, NoidaA/C no.IFSCICIC0000816
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

5 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q1 — engineer certificate
- → https://www.up-rera.in/ViewDocument?Param=PRJ747724092026120550026EC.pdf
changed in Estanzo’s record
25 Sept 2026
Quarterly progress report
2026-Q1 — architect certificate
- → https://www.up-rera.in/ViewDocument?Param=PRJ747724092026120406872AC.pdf
changed in Estanzo’s record
25 Sept 2026
Quarterly progress report
2025-Q4 — engineer certificate
- → https://www.up-rera.in/ViewDocument?Param=PRJ747724092026120139385EC.pdf
changed in Estanzo’s record
25 Sept 2026
Quarterly progress report
2025-Q4 — architect certificate
- → https://www.up-rera.in/ViewDocument?Param=PRJ747724092026120051160AC.pdf
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)131 (Under Registration - 0 ) → 132 (Under Registration - 0 )
changed in Estanzo’s record
1 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 1 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Shri Radha Aqua Gardens

Is Shri Radha Aqua Gardens RERA registered?

Yes. Shri Radha Aqua Gardens is registered with UPRERA under registration number UPRERAPRJ7477, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has Shri Radha Aqua Gardens been completed?

UPRERA still lists Shri Radha Aqua Gardens as Registered, so it is not shown as completed here. A completion certificate dated 22 Dec 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Shri Radha Aqua Gardens?

Decent Buildwell Pvt. Ltd. is the promoter entity that filed Shri Radha Aqua Gardens with UPRERA (promoter RERA ID UPRERAPRM14449). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Shri Radha Aqua Gardens more time to complete?

UPRERA's record carries 3 completion extensions for Shri Radha Aqua Gardens, the latest running to 20 Dec 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Shri Radha Aqua Gardens have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Shri Radha Aqua Gardens located?

Shri Radha Aqua Gardens is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Shri Radha Aqua Gardens?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, PENTHOUSE and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Shri Radha Aqua Gardens?

The approved unit plan filed with UPRERA runs from 4 to 119 m² of carpet area (about 42 to 1,283 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Shri Radha Aqua Gardens?

The approved unit plan describes 6 blocks and 972 units of which 939 are homes and 33 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Shri Radha Aqua Gardens?

About 195 units per acre: 972 planned units across 4.97 acres (20,121 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗