NIRALA DIADEM

UPRERARegistered

NIRALA DIADEM is a RERA-registered commercial project by Parth Builtech Private Limited in SECTOR-10, Gautam Budh Nagar (RERA ID UPRERAPRJ825497). Registered with a completion deadline of 12 Oct 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
1%Q4'25
1%Q1'26
1%Q2'26
—Q3'26

Construction stayed at 1% across 3 consecutive filed quarters (Oct–Dec 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ825497
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start14 Oct 2025
Project duration60 months
AddressPLOT NO C-6, SECTOR-10, GREATER NOIDA, SECTOR-10, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressG-83/207, Vijay Chowk, Laxmi Nagar, Delhi-110092 and Corporate office Address as Office No.21, Logix Infotech Park, Ground Floor, D-5, Sector-59, Noida-201301, Uttar Pradesh.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP-SM-10-FEB-2025-23783

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered17 Nov 2025
Original completion12 Oct 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,16,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 23 (from plan)
ConfigurationUnitsCarpet area
SHOP—14-374
OTHER—3-788
STUDIO—23-37
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Commercial · SHOP, OTHER, STUDIO23—3-788
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.The plan also files 238.32 m² for a STUDIO, 221.6 m² for a STUDIO, 238.32 m² for a STUDIO and 27 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
GIAN PRAKASH MATHUR
License CA/1980/05769
C-55, EAST OF KAILASH, NEW DELHI-110065
Engineer
NAVEEN
C-55, EAST OF KAILASH, NEW DELHI-110065
Contractor
Inhouse by Parth Builtech Private Limited
Inhouse by Parth Builtech Private Limited
Sr.Development work declared to RERA
1Demarcation of Plots
Not a Plotted development and demarcation will be as per the approved plan.
2Boundary Wall
382.07 m, 1.2 m MS railing above brickwork.
3Road Work
363 m, 6.0 m wide road, 1 lane
4Footpaths
NA
5Water Supply Including Drinking Water Facilities
Minimum 2 Nos. Connection, Fire Tank 400 KL, Raw Water 100KL, Garden hydrants will be provided, Domestic 100 KL, Soft Sater 100 KL, Source of water Municipal (GNIDA)
6Sewer System
Length 276 Mtr., 200 dia pipe size, Gravity Flow, uPVC pipe, Yes Network Design.
7Drain
Length 325 mtr., 200 dia pipe size, Gravity Flow, RCC pipe for storm water system, excess overflow rain water will connect to municipal drain.
8Parks
It is a commercial project with 1732.61 sq. mtr. green area, at different place.
9Tree Planting
65 Trees
10Design For Electric Supply Including Street Lighting
Nos. of Pole - 25 and Pole Light - 25 Nos., Transformer - 2 Nos. 2500 KVA Oil Type, 33 KV/433V, LED Type Light, Some solar Light.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
STP 310 KLD, Treatment unit of Screening chamber, Oil and Grease Trap, Equalization tank, Anoxic, FAB, settling tank, sludge holding tank, treated water tank, filter feed tank, pressure sand filter, activated carbon filter, chlorination, filter press. STP Treated water use for flushing, irrigation Soft water as per CPCP, SPCB, MOEF and CC, and NBC 2016 guildelines.
13Solid Waste Management And Disposal System
The Solid Waste generated from the project site will be 1.55 TPD. Solid wastes generated will be segregated into 0.73 TPD biodegradable and 0.82 TPD non-biodegradable components and collected in separate bins. The biodegradable wastes will be composted in an onsite composting unit and the manure will be used for landscaping. The non-biodegradable/recyclable wastes will be disposed at GNIDA designated site through authorized vendors.
14Water Conservation System
3 No. Harvasting pit of 3 Mtr. Dia and 2.3 Mtr. Effective Water depth, water-efficient fixtures, Groundwater Recharge through recharge pit WC 4.5/3 LPF, Urinal 1.5 LPF, Health Faucet upto 6 LPM, Kitchen Sink less than 4 LPM, 4 bar Shower Head upto 6 LPM.
15Energy Management System Including Use of Renewable Energy
Solar Capacity-102.8 KW, Nos of Solar Panel-191 Nos. Renewable Energy used-grid integration
16Fire Protection And Fire Safety System
3 Nos. Hydrants at each Floor, Fire exit proposed, sprinklers proposed, fire suppression system proposed automatic, fire suppression system proposed as per NBC 2016, Fire Safety Training will provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
(07 Male, 07 Female and 07 handicapped toilet) upto 4th floor and 01 nos of toilet for each studio unit (total 555 studios)
18Emergency Evacuation Services
03 nos. of gates for site evacuation, 01 on 130 m wide road, 01 on 24 m side road and 01 on paved road. Provision of UGT Storage tanks, firefighting pumps, FHC, wet riser system, sprinklers and OHT.
19Other Miscellaneous Work
Approx. 80 nos. CCTV units, 20 benches, landscape for beautification and signage for directions and tectonic tiles and ramps for handicapped.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 13 Oct 2030.

Sanctioned by Greater Noida Authority · 10,600 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP-SM-10-FEB-2025-2378314 Oct 202513 Oct 203013 Oct 203512 Oct 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Plot No. C-6, Sector-10, Greater Noida, U.P.10600Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · Document No. 922, Book No. 1, Volume No. 30012, Page No. 181 to 230.
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New17 Oct 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New17 Oct 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New17 Oct 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New17 Oct 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New17 Oct 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New17 Oct 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New17 Oct 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New17 Oct 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Oct 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Nov 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Nov 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New17 Oct 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New17 Oct 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New17 Oct 2025 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q2.

QuarterConstructionCertificates
2025-Q31%CA ↗ · Arch ↗ · Eng ↗
2025-Q41%CA ↗ · Arch ↗ · Eng ↗
2026-Q11%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameParth Builtech Private Limited
RolePromoter · current
RERA IDUPRERAPRM348231
PANAAFCP2755F
CIN / TANU45400DL2008PTC184278
Name of chairmanSuresh Kumar Garg
Registered addressG-83/207, Vijay Chowk, Laxmi Nagar, Delhi-110092 and Corporate office Address as Office No.21, Logix Infotech Park, Ground Floor, D-5, Sector-59, Noida-201301, Uttar Pradesh.
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PBPL COLL ACC FOR NIRALA DIADEMBankYES BANK LIMITEDBranchSECTOR 63, NOIDABranch addressBASEMENT, GROUND AND FIRST FLOOR, PLOT NO 38, BLOCK H 1 A, SEC 63, NOIDA-201301, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCYESB0000014Branch emailDLTEAMBSDSECTOR63-NOIDA@YESBANK.IN
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PBPL SEPARATE BANK ACCOUNT FOR NIRALA DIADEMBankYES BANK LIMITEDBranchSECTOR 63, NOIDABranch addressBASEMENT, GROUND AND FIRST FLOOR, PLOT NO 38, BLOCK H 1 A , SECTOR 63, NOIDA-201301, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCYESB0000014
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PBPL RERA TRANSACTION ACCOUNT FOR NIRALA DIADEMBankYES BANK LIMITEDBranchSECTOR-63, NOIDABranch addressBASEMENT, GROUND AND FIRST FLOOR, PLOT NO 38, BLOCK H 1 A, SECTOR 63, NOIDA-201301, U.P.Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCYESB0000014
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about NIRALA DIADEM

Is NIRALA DIADEM RERA registered?

Yes. NIRALA DIADEM is registered with UPRERA under registration number UPRERAPRJ825497, registered on 17 Nov 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for NIRALA DIADEM?

The completion date filed with UPRERA is 12 Oct 2030. No completion certificate is on record yet.

Who is the builder of NIRALA DIADEM?

Parth Builtech Private Limited is the promoter entity that filed NIRALA DIADEM with UPRERA (promoter RERA ID UPRERAPRM348231). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does NIRALA DIADEM have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is NIRALA DIADEM located?

NIRALA DIADEM is registered in SECTOR-10, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in NIRALA DIADEM?

The unit plan filed with UPRERA lists SHOP, OTHER and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in NIRALA DIADEM?

The approved unit plan filed with UPRERA runs from 3 to 788 m² of carpet area (about 34 to 8,486 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗