Registered14 Aug 2017
Promised23 Jun 2018
Completed27 Jun 2023

Timeline

Promised completion23 Jun 2018
Revised completion23 Jun 2018
Actual completion27 Jun 2023
Possession delay60 mo delay

Registration & Cost Details

Registration fee (in ₹)₹55,000
Project cost (in ₹ Lakhs)₹13,369.5 Lakhs
Project duration36 months
Project categoryResidential
Locality
Original start date29 Jan 2014
Proposed start date24 Jun 2015

Inventory

Total units381
Unit TypeUnitsCarpet Area (sqm)
1 BHK28536.01
3 BHK96102.53

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9811005579
Emailceo@gnida.in
Coordinator9871090092
AddressPLOT NO-01, KNOWLEDGE PARK-04, GREATER NOIDA, G.B. NAGAR UP

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP) 3708/513010 Aug 20179 Aug 202223 Jun 20189 Aug 2022

Land Parcels

Khasra No.AreaPlot Type
457875
45855
459190
460190
4611310
4622310
4632250
464320
4672500
457875Khasra
45855Khasra
459190Khasra
460190Khasra
4611310Khasra
4622310Khasra
4632250Khasra
464320Khasra
4672500Khasra

Approved Unit Plan

Unit plan rows on file27
Total flats (sum of rows)381
BlocksA, B
Floor types1 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
NA1 Aug 2017

Frequently Asked Questions

What is the RERA registration number of BHS-17 LOHIYA ENCLAVE SECTOR-12?

The RERA registration number of BHS-17 LOHIYA ENCLAVE SECTOR-12 is UPRERAPRJ9565, as recorded on the UP-RERA portal.

What is the RERA status of BHS-17 LOHIYA ENCLAVE SECTOR-12?

As reported by UP-RERA, the status of BHS-17 LOHIYA ENCLAVE SECTOR-12 is "Registered".

Where is BHS-17 LOHIYA ENCLAVE SECTOR-12 located?

As reported to UP-RERA, BHS-17 LOHIYA ENCLAVE SECTOR-12 is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

Is BHS-17 LOHIYA ENCLAVE SECTOR-12 completed?

As reported to UP-RERA, BHS-17 LOHIYA ENCLAVE SECTOR-12 was completed on 27 Jun 2023.

Is BHS-17 LOHIYA ENCLAVE SECTOR-12 delayed?

Measured against the latest completion date reported to UP-RERA, BHS-17 LOHIYA ENCLAVE SECTOR-12 is 60 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026