ORO Utsav

UPRERARegistered

ORO Utsav is a RERA-registered residential project by ORO REAL INFRA LLP in Lucknow (RERA ID UPRERAPRJ511558). Registered with a completion deadline of 7 Sept 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
50.71%Q3'25
52.12%Q4'25
57.47%Q1'26
58.4%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ511558
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Apr 2023
Project duration54 months
AddressBakshi Ka Talab**, Lucknow
TehsilBakshi Ka Talab**
Applicant typePartnership Firm
Applicant address801, 8th Floor, Eldeco Corporate Tower, Vibhuti Khand, Gomtinagar, Lucknow-226010, Uttar Pradesh
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    LDA/BP/21-22/2633/20082022

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 Oct 2022
Original completion7 Sept 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹14,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors80 · 1 · 8 (units from plan)
  • 1 BHK40 50%
  • 2 BHK40 50%
ConfigurationUnitsCarpet area
1 BHK4030
2 BHK4038
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
ORO UTSAV · 1 BHK, 2 BHK88030-38
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Sanjay Kumar Gupta
License ca/89/12382
108, 1st Floor, Eldeco Corporate Chamber-1, Vibhuti Khand, Gomtinagar, Lucknow
Engineer
Akhilesh Kumar Singh
ATS Structural Consultants, D-27, Indira Nagar, Lucknow-226016
Contractor
Jain Construction Co
P No. 14 A, Eldeco Crossing, Ashraf Vihar Colony, Chinhat, Lucknow
Sr.Development work declared to RERA
1Demarcation of Plots
Single plot of land admeasuring 1809.90 Sq. Mtr. is being demarcated at site as per approved layout plan with fix boundary wall.
2Boundary Wall
7 feet Height fix Boundary wall of entire project shall be constructed
3Road Work
6 Mtr wide Driveway around the building will be constructed with CC or Pavers
4Footpaths
Not Applicable
5Water Supply Including Drinking Water Facilities
Water supply will be provided by Terrace Tank of capacity 15000 Ltr
6Sewer System
Sewer pipes will be laid underground disposal of sewerage shall be done after treatment through STP.
7Drain
Underground storm water pipe will be laid for drainage of water
8Parks
Not applicable
9Tree Planting
There are 23 nos trees proposed of various kinds like Gulmohar, Champa etc.
10Design For Electric Supply Including Street Lighting
Electricity distribution system as per norms of electricity Board with centralized Transformer. HT panel, LT panel, feeder pillar DG backup for common area/services.
11Community Buildings
Not applicable
12Treatment and Disposal System of Sewage and Sullage water
Sewerage disposal will be connected to Ajit ORO County STP
13Solid Waste Management And Disposal System
Nagar Nigam Vendor to collect garbage for Solid waste management.
14Water Conservation System
1 No. Rain water Harvesting pit with capacity of 50000 LPM will be constructed as per requirement of the area.
15Energy Management System Including Use of Renewable Energy
We will provide 12 Nos LED light fittings in external and common areas. In STP all the equipment shall have energy efficient motors.
16Fire Protection And Fire Safety System
Over Head tank of capacity 25000 ltr. will be provided and Fire fighting facility in common area as per norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Minimum 1500mm Fire Staircase will be provided.
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 7 Sept 2027.

Sanctioned by Lucknow Development Authority · 1,810 sqm of land · an approved plan of 1 block and 80 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
LDA/BP/21-22/2633/200820228 Sept 20227 Sept 20277 Sept 20297 Sept 2027
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
EWS/LIG1809.90Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 61
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 146
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New24 Sept 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 Sept 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New28 Sept 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New24 Sept 2022 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New24 Sept 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Sept 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New14 Oct 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New14 Oct 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Sept 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New14 Oct 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New28 Sept 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 Sept 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Sept 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New28 Sept 2022 ↗

Quarterly progress reports

14 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

14 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q1.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q250.71%CA ↗ · Arch ↗ · Eng ↗
2025-Q352.12%CA ↗ · Arch ↗ · Eng ↗
2025-Q457.47%CA ↗ · Arch ↗ · Eng ↗
2026-Q158.4%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameORO REAL INFRA LLP
RolePromoter · current
RERA IDUPRERAPRM152277
PANAAGFO6949L
CIN / TANLKNO06289D
Registered address801, 8th Floor, Eldeco Corporate Tower, Vibhuti Khand, Gomtinagar, Lucknow-226010, Uttar Pradesh
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameAJIT KUMAR MAURYA
RoleCo-promoter
Applicant typeIndividual
AddressB1/5, L Park, Mahanagar S.O, Lucknow, U.P-226006
RERA contact
Legal nameEKTA MAURYA
RoleCo-promoter
Applicant typeIndividual
AddressB1/5, L Park, Mahanagar S.O, Lucknow, Uttar Pradesh-226006
RERA contact
Legal nameRANI MAURYA
RoleCo-promoter
Applicant typeIndividual
AddressB1/5, L Park, Mahanagar S.O, Lucknow. U.P- 226006
RERA contact
Legal nameAISHWARYA MAURYA
RoleCo-promoter
Applicant typeIndividual
AddressB1/5, L Park, Mahanagar S.O, Lucknow U.P-226006
RERA contact

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Ori Collection AC for Oro UtsavBankPunjab National BankBranchVibhuti KhandBranch addressVibhuti, Khand, Gomtinagar, Lucknow-226010Branch districtLucknow, Uttar PradeshA/C no.IFSCPUNB0619300
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Ori Seperate AC for Oro UtsavBankPunjab National BankBranchVibhuti KhandBranch addressVbhuti Khand Gomtinagar, Lucknow-226010Branch districtLucknow, Uttar PradeshA/C no.IFSCPUNB0619300
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Ori Transaction AC for Oro UtsavBankPunjab National BankBranchVibhuti KhandBranch addressVibhuti Khand, Gomtinagar, Lucknow-226010Branch districtLucknow, Uttar PradeshA/C no.IFSCPUNB0619300
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ORO Utsav

Is ORO Utsav RERA registered?

Yes. ORO Utsav is registered with UPRERA under registration number UPRERAPRJ511558, registered on 22 Oct 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ORO Utsav?

The completion date filed with UPRERA is 7 Sept 2027. No completion certificate is on record yet.

Who is the builder of ORO Utsav?

ORO REAL INFRA LLP is the promoter entity that filed ORO Utsav with UPRERA (promoter RERA ID UPRERAPRM152277). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ORO Utsav have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ORO Utsav located?

ORO Utsav is registered in Lucknow, as filed with UPRERA.

What configurations are available in ORO Utsav?

The unit plan filed with UPRERA lists 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in ORO Utsav?

The approved unit plan filed with UPRERA runs from 30 to 38 m² of carpet area (about 325 to 411 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in ORO Utsav?

The approved unit plan describes 1 block and 80 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is ORO Utsav?

About 179 units per acre: 80 planned units across 0.45 acres (1,810 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗