Timeline Bar

Registered26 Dec 2019
Promised1 Jun 2022
Completed19 Mar 2025

Timeline

Promised completion1 Jun 2022
Revised completion1 Jun 2022
Actual completion19 Mar 2025
Possession delay34 mo delay

Registration & Cost Details

Registration fee (in ₹)₹80,000
Project cost (in ₹ Lakhs)₹10,830 Lakhs
Project duration97 months
Project categoryResidential
Locality
Original start date1 May 2016
Proposed start date1 May 2016

Inventory

Total units308
Unit TypeUnitsCarpet Area (sqm)
2 BHK14051.15–83.45
3 BHK11261.16–134.46
4 BHK5688.19–133.85

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile7705008258
Emailadmin@als.net.in
Coordinator9793481851
AddressSaraf Sadan, Gandhi Nagar, Golghar, Gorakhpur - 273001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
938/151 Apr 201631 Mar 20211 Jun 202231 Mar 2024

Land Parcels

Khasra No.AreaPlot Type
11333930Khasra
1134mi280Khasra
1135mi1400Khasra
1135mi20Khasra
1135mi20Khasra
1135ka2720Khasra
1135ka2720Khasra
11372390Khasra
11372390Khasra
1139850Khasra
1139850Khasra
11401740Khasra
1141mi260Khasra
1142mi100Khasra
1142mi100Khasra
1143mi610Khasra
1141mi1680Khasra
1141mi1680Khasra
1141ka810Khasra
1142ka300Khasra
1142ka300Khasra
1143/1320Khasra
1143/2ka1460Khasra
1143/2ka1460Khasra
1144930Khasra
1145/2810Khasra
1145/2810Khasra
1145/11740Khasra
11461660Khasra
11471050Khasra
10201210Khasra
1046/11660Khasra
1148/2890Khasra
1149/2280Khasra
11653080Khasra
1148/1890Khasra
1149/1360Khasra
1150/1810Khasra
1151890Khasra
1148/3810Khasra
1149/3810Khasra
1150/2770Khasra
1154/1610Khasra
1154/2400Khasra
1155890Khasra
11561860Khasra
11572270Khasra
1158490Khasra
1196ka810Khasra
1159650Khasra
11601540Khasra
11611500Khasra
1162mi240Khasra
10243880Khasra
10251010Khasra
11623240Khasra
1163360Khasra
11665470Khasra
11674500Khasra
11741210Khasra
1175240Khasra
11971130Khasra
12021660Khasra
1203850Khasra
10191340Khasra
1021/1970Khasra
1022mi890Khasra
1021/1970Khasra
1022/1ka850Khasra
1022/1ka850Khasra
1021/21940Khasra
1022/21740Khasra
10232750Khasra
10265630Khasra
10271010Khasra
10282100Khasra
10336840Khasra
10347690Khasra
10372270Khasra
10381580Khasra
10381580Khasra
10391010Khasra
10401500Khasra
10411170Khasra
10421420Khasra
10451980Khasra
10451980Khasra
10431210Khasra
10441580Khasra
1046/21620Khasra
10474580Khasra
1193/12390Khasra
1194/12180Khasra
1195/1650Khasra
1193/2890Khasra
1194/2200Khasra
1195/21420Khasra
1198/22790Khasra
11982830Khasra
12013590Khasra
12042750Khasra

Approved Unit Plan

Unit plan rows on file294
Total flats (sum of rows)308
BlocksA, G, H, T-1
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Paalm Paradise Phase II?

The RERA registration number of Paalm Paradise Phase II is UPRERAPRJ119189, as recorded on the UP-RERA portal.

What is the RERA status of Paalm Paradise Phase II?

As reported by UP-RERA, the status of Paalm Paradise Phase II is "Registered".

Where is Paalm Paradise Phase II located?

As reported to UP-RERA, Paalm Paradise Phase II is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

Is Paalm Paradise Phase II completed?

As reported to UP-RERA, Paalm Paradise Phase II was completed on 19 Mar 2025.

Is Paalm Paradise Phase II delayed?

Measured against the latest completion date reported to UP-RERA, Paalm Paradise Phase II is 34 months beyond that date.