PALM RESORT

UPRERARegistered

PALM RESORT is a RERA-registered residential project by MRJV Construction Company in Ghaziabad (RERA ID UPRERAPRJ7354). Registered with a completion deadline of 31 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
91.45%Q4'24
92%Q1'25
92.84%Q2'25
92%Q3'25
90.08%Q4'25
92.67%Q1'26
93.47%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7354
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start16 Nov 2013
Original start16 Nov 2013
Project duration158 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typePartnership Firm
Applicant addressKhasra No. 1042, 1045, 1046, 1047, 1067 & 1068, Palm Resort Raj Nagar Extn. Ghaziabad
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. to

    Extension granted

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  7. to

    Extension granted

  8. to

    Extension granted

  9. to

    Extension granted

  10. valid to

    Permit revalidated

    GDA/BP/21-22/1502

  11. Permit revalidated (3)

  12. 4 building permits sanctioned

  13. to

    Extension granted

  14. 3 completion certificates filed

  15. to

    Extension granted

  16. valid to

    Permit revalidated

    GDA/BP/21-22/1502

  17. Completion certificate filed

  18. Completion certificate filed

  19. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion31 Dec 2019
Revised completion31 Dec 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary11 Jul 2024
Registration fee₹1,48,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors935 · 20 · 19 (units from plan)
Homes · commercial units913 · 22 (shops and offices filed in the same plan)
  • 2 BHK611 65%
  • 1 BHK180 19%
  • 3 BHK122 13%
  • SHOP22 2%
ConfigurationUnitsCarpet area
2 BHK61153-71
3 BHK12280-117
1 BHK18040-48
SHOP2213-16
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block-1 Tower A2 (Type 1) · 2 BHK1510453
Block-1 Tower A2 (Type 2) · 2 BHK154553-62
Block-1 Tower D2 · 2 BHK1510453
Block-1 Tower G1 (Type 1) · 2 BHK1513353
Block-1 Tower G1 (Type 2) · 2 BHK151562
Block-1 Tower G1 (Type 3) · 2 BHK141471
Block-2 Tower C · 3 BHK155880
Block-2 Tower E1 (Type 1) · 2 BHK101953
Block-2 Tower E1 (Type 2) · 2 BHK111971
Block-2 Tower E1 (Type 3) · 2 BHK111959-69
Block-2 Tower E1 (Type 4) · 3 BHK112291
Block-2 Tower E1 (Type 5) · 3 BHK1142117-117
Block-2 Tower F (Type 1) · 2 BHK1411153
Block-2 Tower F (Type 2) · 2 BHK141462
Block-2 Tower F (Type 3) · 2 BHK141471
E.W.S. · 1 BHK189040
L.I.G. · 1 BHK189048
Shop (Type 1) · SHOP1513
Shop (Type 2) · SHOP1414
Shop (Type 3) · SHOP11316
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Vishal Mittal
License CA/98/23185
B 34 Sector 67 Noida U.P.
Engineer
V D SHARMA
B 24 sector 67 Noida U.P.
Contractor
N/A
N/A
Sr.Development work declared to RERA
1Demarcation of Plots
Total plot area 37048.12. Sq. m. located at Khasra No. 1037,1042,1043,1044,1045,1046,1047,1051,1067 & 1068 Village Noornagar, Ghaziabad, U.P.
2Boundary Wall
2100 mm high, along entire periphery.
3Road Work
Interlocking Tremix
4Footpaths
Interlocking Pavers
5Water Supply Including Drinking Water Facilities
UGT Of domestic tank capacity 275 K.L.
6Sewer System
Underground system using UPVC/RCC Sewer pipes.
7Drain
Underground system using UPVC/RCC Sewer pipes.
8Parks
Parks having total area of 4,943.24 sq. m. shall be provided.
9Tree Planting
151 nos. trees are to be planted out of that 50% will be evergreen tree.
10Design For Electric Supply Including Street Lighting
Electricity Transformers 02 nos. of 1600 KVA capacity each & 01 no. of 2000 KVA shall be used along with necessary switch-gear for distributing electricity at LT voltage.
11Community Buildings
Applicable.
12Treatment and Disposal System of Sewage and Sullage water
STP of capacity 300 KLD shall be provided. Treated water shall be used for flushing, irrigation, pathways cleaning and excess sewage shall be discharged in the municipal sewer.
13Solid Waste Management And Disposal System
Manual collection and organic waste converter shall be provided.
14Water Conservation System
10 No. sets of recharge Pits (2 x 1.75 x 1m effective depth) and desilting tank (5 x 1.75 x 2 m effective depth) shall be provided.
15Energy Management System Including Use of Renewable Energy
Solar panels shall be provided on terrace for renewable energy. Single point metering will be there for energy purchased from the grid/ power supply company.
16Fire Protection And Fire Safety System
Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and UGT of Fire tank capacity 200 K.L. (common) and OHT of Fire tanks (at each block terrace) shall be provided as per NBC & NOC from fire depp.
17Social Infrastructure And Other Public Amenities Including Public Health Services
STP, organic waste converter shall be provided.
18Emergency Evacuation Services
Staircases shall be provided In Basement & all the Towers for fire/ emergency exit as per NBC.
19Other Miscellaneous Work
-
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1NIKHIL JAINUPRERAAGT12804
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

6 permits

An approval and the date it runs to - not proof the work matching it was done.

6 sanctioning permits are on record with UPRERA, the latest valid to 19 Jul 2028. 5 of them carry a revalidation, the latest valid to 19 Jul 2028.

Sanctioned by Ghaziabad Development Authority · 28,567 sqm of land · an approved plan of 20 blocks and 935 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
711/Zone-I/14-1510 Feb 20179 Feb 20229 Feb 202227 Mar 2022—
711/Zone-I/14-1510 Feb 20179 Feb 20221 Jan 202527 Mar 202222 May 2023
valid to 1 Jan 2025
as GDA/BP/21-22/1502
Group housing/04073/GDA/BP/21-22/1502/211120221 Jun 202317 Jun 20251 Jan 202527 Mar 20221 Jun 2023
valid to 1 Jan 2025
GDA/BP/21-22/15021 Jun 20231 Jun 202317 Jun 202523 May 202419 Mar 2025
valid to 19 Jul 2028
GDA/BP/21-22/15021 Jun 202319 Jul 202817 Jun 202531 Dec 20241 Jun 2023
GDA/BP/21-22/15021 Jun 202319 Jul 202817 Jun 202531 Dec 20241 Jun 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 7 completion extensions for this project, the latest running to 31 Dec 2026.

#Granted fromExtended uptoNote
131 Dec 201930 Dec 2020—
230 Dec 202029 Jun 2021Six months extension in view of force majeure caused by covid-19 pandemic
329 Jun 202128 Dec 2021—
428 Dec 202127 Mar 2022—
527 Mar 202223 May 2024—
623 May 202431 Dec 2024—
731 Dec 202431 Dec 2026—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1042, 1045, 1046, 1047, 1067, 106837048.12Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1415-1420
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1415-1420
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · GDA/BP/21-22/1502
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Sale deed · APPROVED MAP
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 Aug 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New25 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New25 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New25 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New21 Jan 2022 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old17 Oct 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterGROUND WATER
Fire safety (as filed with RERA)AS PER FIRE NOC
Renewable energyAS PER SANCTION MAP
Other facilitiesN.A

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q391.45%CA ↗ · Arch ↗ · Eng ↗
2024-Q492%CA ↗ · Arch ↗ · Eng ↗
2025-Q192.84%CA ↗ · Arch ↗ · Eng ↗
2025-Q292%CA ↗ · Arch ↗ · Eng ↗
2025-Q390.08%CA ↗ · Arch ↗ · Eng ↗
2025-Q492.67%CA ↗ · Arch ↗ · Eng ↗
2026-Q193.47%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMRJV Construction Company
RolePromoter · current
RERA IDUPRERAPRM8449
PANAAUFM1463D
Registered addressKhasra No. 1042, 1045, 1046, 1047, 1067 & 1068, Palm Resort Raj Nagar Extn. Ghaziabad
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
MRJV CONSTRUCTION COMPANYBankPUNJAB NATIONAL BANKBranchLCB BRANCH, SECTOR-63, NOIDAA/C no.IFSCPUNB0093110
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Latest completion certificate filed on2026-07-08 → 2026-09-16
changed in Estanzo’s record
19 Sept 2026
When these facts last moved
Latest completion certificate filed onchanged in Estanzo’s record · 19 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about PALM RESORT

Is PALM RESORT RERA registered?

Yes. PALM RESORT is registered with UPRERA under registration number UPRERAPRJ7354, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has PALM RESORT been completed?

UPRERA still lists PALM RESORT as Registered, so it is not shown as completed here. A completion certificate dated 11 Jul 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of PALM RESORT?

MRJV Construction Company is the promoter entity that filed PALM RESORT with UPRERA (promoter RERA ID UPRERAPRM8449). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted PALM RESORT more time to complete?

UPRERA's record carries 7 completion extensions for PALM RESORT, the latest running to 31 Dec 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does PALM RESORT have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PALM RESORT located?

PALM RESORT is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in PALM RESORT?

The unit plan filed with UPRERA lists 2 BHK, 3 BHK, 1 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in PALM RESORT?

The approved unit plan filed with UPRERA runs from 13 to 117 m² of carpet area (about 140 to 1,264 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in PALM RESORT?

The approved unit plan describes 20 blocks and 935 units of which 913 are homes and 22 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is PALM RESORT?

About 132 units per acre: 935 planned units across 7.06 acres (28,567 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗