Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ17962
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start11 Nov 2018
Project duration66 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressPLOT NO. 2, FLAT NO. 118, F/F, NETAJI SUBHASH MARG, DARYA GANJ, DELHI, 110002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    172 Manchitra No. - 658 / Zone-1 / 14-15

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered5 Nov 2018
Original completion21 Oct 2023
Revised completion20 Apr 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary1 Dec 2025
Registration fee₹75,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors97 · 1 · 9 (units from plan)
Homes · commercial units17 · 80 (shops and offices filed in the same plan)
  • SHOP80 82%
  • OTHER17 18%
ConfigurationUnitsCarpet area
OTHER1733-183
SHOP8021-370
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · OTHER, SHOP99721-689
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 469.98 m² for a OTHER, 478 m² for a OTHER, 496.37 m² for a OTHER and 2 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VASTU SRIJAN
License CA/85/9138
WB-64, Shakarpur, Delhi - 110092
Engineer
CE CON Engg
HS-25, 2nd Floor Kailash Colony Market, N. Delhi- 110048
Contractor
NA
NA
Sr.Development work declared to RERA
1Demarcation of Plots
Total Plot Area of 6426.73 Sq. Mtrs. Located in Khasra 1069 situated in Village Noor Nagar, Pargana Loni, District Ghaziabad, U.P.
2Boundary Wall
Designer Wall on Front Road Side and 2100mm high along balance entire periphery.
3Road Work
Interlocking Pavers
4Footpaths
Interlocking Pavers
5Water Supply Including Drinking Water Facilities
Two Underground Tanks of 300 KL capacity each.
6Sewer System
Underground system using uPVC (SN-4) pipes.
7Drain
Underground system using uPVC (SN-4) sewerpipes.
8Parks
Green Area having total area of 321.95 Sq. Mtrs. shall be provided.
9Tree Planting
37 trees are to be planted @ 1 Tree per 100 Sq. Mtrs. All will be evergreen tree.
10Design For Electric Supply Including Street Lighting
Two Electricity Transformers of 1250 KVA capacity each shall be used along with necessary switch-gear for distributing electricity at LT voltage.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
STP of capacity 120KLD shall be provided. Treated water shall be used for flushing, irrigation, carwash, HVAC and pathways cleaning.
13Solid Waste Management And Disposal System
Manual collection and organic waste converter shall be provided in the project.
14Water Conservation System
Rain water harvesting facilities shall be provided with 2 RWH pits.
15Energy Management System Including Use of Renewable Energy
Solar panels shall be provided on terrace for renewable energy. Single point metering will be there for energy purchased from the grid/power supply company.
16Fire Protection And Fire Safety System
Fire tender path shall be provided as per NBC. Fire fighting systems along with pumps and water storage tanks shall be provided as per NBC & NOC from fire department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
STP, organic waste converter shall be provided.
18Emergency Evacuation Services
Staircases shall be provided in Basement & all floors of the building for fire/emergency exit as per norms.
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 22 Oct 2023.

Sanctioned by Ghaziabad Development Authority · 6,427 sqm of land · an approved plan of 1 block and 97 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
172 Manchitra No. - 658 / Zone-1 / 14-1523 Oct 201822 Oct 202321 Oct 202621 Oct 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 20 Apr 2024.

#Granted fromExtended uptoNote
121 Oct 202320 Apr 2024Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

13 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
10696426.73Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · Sale Deed No - Bahi No. 1 Jild No. 8712 Page No. 197 to 222 Serial No. 10044 dated 11/08/2014 & Tran
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New5 Nov 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Nov 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Nov 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Nov 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Nov 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Nov 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Nov 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New5 Nov 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Nov 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Nov 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Nov 2018 ↗

Quarterly progress reports

17 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

17 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2024-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSPOTLITE PROJECTS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM65412
PANAADCJ8493L
CIN / TANU70109DL2016PTC309147
Name of chairmanRAJEEV KUMAR JAIN
Registered addressPLOT NO. 2, FLAT NO. 118, F/F, NETAJI SUBHASH MARG, DARYA GANJ, DELHI, 110002
RERA contact
Registered since2018
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
SPOTLITE PROJECTS PRIVATE LIMITED COLLECTION A/CBankPunjab National BankBranchKaushambiA/C no.IFSCPUNB0300000
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about SPOTLITE

Is SPOTLITE RERA registered?

Yes. SPOTLITE is registered with UPRERA under registration number UPRERAPRJ17962, registered on 5 Nov 2018. Estanzo reproduces that filing; it does not verify the work behind it.

Has SPOTLITE been completed?

UPRERA still lists SPOTLITE as Registered, so it is not shown as completed here. A completion certificate dated 1 Dec 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of SPOTLITE?

SPOTLITE PROJECTS PRIVATE LIMITED is the promoter entity that filed SPOTLITE with UPRERA (promoter RERA ID UPRERAPRM65412). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted SPOTLITE more time to complete?

UPRERA's record carries 1 completion extension for SPOTLITE, the latest running to 20 Apr 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does SPOTLITE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SPOTLITE located?

SPOTLITE is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in SPOTLITE?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SPOTLITE?

The approved unit plan filed with UPRERA runs from 21 to 370 m² of carpet area (about 221 to 3,980 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SPOTLITE?

The approved unit plan describes 1 block and 97 units of which 17 are homes and 80 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SPOTLITE?

About 61 units per acre: 97 planned units across 1.59 acres (6,427 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗