Estanzo

Timeline Bar

Registered1 Oct 2020
Completed11 May 2023
Promised19 May 2023

Timeline

Promised completion19 May 2023
Revised completion19 May 2023
Actual completion11 May 2023
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,13,500
Project cost (in ₹ Lakhs)₹3,528 Lakhs
Project duration36 months
Project categoryResidential
Locality
Original start date
Proposed start date20 May 2020

Inventory

Total units240
Unit TypeUnitsCarpet Area (sqm)
2 BHK24054.45

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9628372038
Emailgdagorakhpur@gmail.com
Coordinator9628372038
AddressTaramandal, Deoria Byepass Road, Gorakhpur

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
2/NIYOJAN/27-04-202027 Apr 202026 Apr 202519 May 202326 Apr 2028

Land Parcels

Khasra No.AreaPlot Type
584,585MI,836MI,837,838MI,844MI,845MI,851MI,852MI,856MI,857,85821657.65Khasra

Approved Unit Plan

Unit plan rows on file60
Total flats (sum of rows)240
Blocks1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15
Floor types2 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME?

The RERA registration number of PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME is UPRERAPRJ478126, as recorded on the UP-RERA portal.

What is the RERA status of PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME?

As reported by UP-RERA, the status of PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME is "Registered".

Where is PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME located?

As reported to UP-RERA, PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

Is PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME completed?

As reported to UP-RERA, PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME was completed on 11 May 2023.

Is PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME delayed?

Measured against the latest completion date reported to UP-RERA, PATRAKARPURAM VISTAR 4 STORY AFFORDABLE (G+3) SEMI FINISHED HOUSING SCHEME is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026