Estanzo

Timeline Bar

Registered15 Aug 2017
Promised1 Mar 2019
Today3 Aug 2026

Timeline

Promised completion1 Mar 2019
Revised completion1 Mar 2019
Actual completion
Possession delay89 mo delay

Registration & Cost Details

Registration fee (in ₹)₹43,000
Project cost (in ₹ Lakhs)₹2,000 Lakhs
Project duration132 months
Project categoryCommercial
Locality
Original start date1 Mar 2014
Proposed start date1 Mar 2014

Inventory

Total units88
Unit TypeUnitsCarpet Area (sqm)
3 BHK5687
SHOP3258

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9044035431
Emailashishinfraestate@gmail.com
Coordinator9044035424
Address501, Gemini Residency, Asuran Chungi Medical Road Shahpur, Gorakhpur ( U.P.), PIN : 273001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
222/1326 Apr 201412 Jan 20191 Mar 201911 Jan 2021
222/2013

Revalidated: 222/2013 (26 Apr 2014)

26 Apr 20141 Mar 2019

Revalidated upto: 17 Feb 2020

1 Mar 201916 Feb 2025

Land Parcels

Khasra No.AreaPlot Type
1830.247
1840.494
2140.437

Approved Unit Plan

Unit plan rows on file9
Total flats (sum of rows)88
Total shops32
Blocks1
Floor types3 BHK, SHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
jild no-1184 prastha no-38 to 40 no-44553 Dec 1965

Frequently Asked Questions

What is the RERA registration number of SILVER HEIGHTS?

The RERA registration number of SILVER HEIGHTS is UPRERAPRJ10024, as recorded on the UP-RERA portal.

What is the RERA status of SILVER HEIGHTS?

As reported by UP-RERA, the status of SILVER HEIGHTS is "Registered".

Where is SILVER HEIGHTS located?

As reported to UP-RERA, SILVER HEIGHTS is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

When will SILVER HEIGHTS be completed?

The latest completion date reported to UP-RERA for SILVER HEIGHTS is 1 Mar 2019.

Is SILVER HEIGHTS delayed?

Measured against the latest completion date reported to UP-RERA, SILVER HEIGHTS is 89 months beyond that date.