Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ6057
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start10 Mar 2013
Original start10 Mar 2013
Project duration91 months
AddressModinagar, Ghaziabad
TehsilModinagar
Applicant typePartnership Firm
Applicant addressKhasra No. 897, Village Noor Nagar, Ghaziabad
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Permit revalidated

    240/MP/ZONE-1/15

  3. 2 building permits sanctioned

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion31 Mar 2019
Revised completion29 Sept 2020
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹50,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors340 · 2 · 19 (units from plan)
Homes · commercial units334 · 6 (shops and offices filed in the same plan)
  • 2 BHK170 50%
  • 3 BHK156 46%
  • PENTHOUSE8 2%
  • SHOP6 2%
ConfigurationUnitsCarpet area
2 BHK17060
3 BHK15677-104
PENTHOUSE8155-189
SHOP680
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · 2 BHK, OTHER, 3 BHK1920260-77
B · 3 BHK, PENTHOUSE, OTHER, SHOP1813877-189
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUJ AGARWAL
License CA/96/19503
A-244, KAUSHAMBI, GHAZIABAD
Engineer
SADANAND OJHA
503, Sachdeva Corporate Tower, Plot No-8, Sector-8, Rohini, Delhi
Contractor
N/A
N/A
Sr.Development work declared to RERA
1Demarcation of Plots
NOT APPLICABLE
2Boundary Wall
COMPLETE
3Road Work
40% COMPLETE
4Footpaths
NOT APPLICABLE
5Water Supply Including Drinking Water Facilities
WORK IN PROGRESS
6Sewer System
WORK IN PROGRESS
7Drain
WORK IN PROGRESS
8Parks
WORK IN PROGRESS
9Tree Planting
WORK IN PROGRESS
10Design For Electric Supply Including Street Lighting
DESIGN IS DONE, WORK IN PROGRESS
11Community Buildings
WORK IN PROGRESS
12Treatment and Disposal System of Sewage and Sullage water
STRUCTURE IS COMPLETE
13Solid Waste Management And Disposal System
NA
14Water Conservation System
RAIN WATER HARVESTING IS IN PROGRESS
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
WORK IN PROGRESS
17Social Infrastructure And Other Public Amenities Including Public Health Services
CLUB HOUSE,
18Emergency Evacuation Services
FIRE STAIR CASE
19Other Miscellaneous Work
WORK IN PROGRESS
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 23 Jul 2020. 1 of them carries a revalidation.

Sanctioned by Ghaziabad Development Authority · 8,905 sqm of land · an approved plan of 2 blocks and 340 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
240/MP/ZONE-1/1524 Jul 201523 Jul 202020 Jun 202130 Mar 2020—
240/MP/ZONE-1/1524 Jul 201523 Jun 202023 Jun 202030 Mar 202024 Jul 2015
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 29 Sept 2020.

#Granted fromExtended uptoNote
131 Mar 201930 Sept 2019—
230 Sept 201930 Mar 2020—
330 Mar 202029 Sept 2020Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

7 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Kh No. 897 Village Noor Nagar, Ghaziabad9578 SQ.MT.—
8979578Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 22 Oct 2012.

Registry no.DateTypeArea
1425222 Oct 2012self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1415-1420
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1415-1420
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New22 Apr 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New22 Apr 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New22 Apr 2021 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old17 Oct 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old17 Oct 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterGROUND WATER
Fire safety (as filed with RERA)AS PER FIRE NOC
Renewable energySOLAR POWER

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

1 filed report

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

1 quarterly progress report is on file with UPRERA, for 2020-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameM.R.DD Developers
RolePromoter · current
RERA IDUPRERAPRM8788
PANAAVFM8795P
Registered addressKhasra No. 897, Village Noor Nagar, Ghaziabad
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
MR DD DEVELOPERSBankUCO BANKBranchRAJ NAGAR EXT.GHAZIABADA/C no.IFSCUCBA0002903
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about PLATINUM 321

Is PLATINUM 321 RERA registered?

Yes. PLATINUM 321 is registered with UPRERA under registration number UPRERAPRJ6057, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for PLATINUM 321?

The completion date filed with UPRERA is 29 Sept 2020. No completion certificate is on record yet.

Who is the builder of PLATINUM 321?

M.R.DD Developers is the promoter entity that filed PLATINUM 321 with UPRERA (promoter RERA ID UPRERAPRM8788). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted PLATINUM 321 more time to complete?

UPRERA's record carries 3 completion extensions for PLATINUM 321, the latest running to 29 Sept 2020. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does PLATINUM 321 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PLATINUM 321 located?

PLATINUM 321 is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in PLATINUM 321?

The unit plan filed with UPRERA lists 2 BHK, OTHER, 3 BHK, PENTHOUSE and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in PLATINUM 321?

The approved unit plan filed with UPRERA runs from 60 to 189 m² of carpet area (about 648 to 2,032 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in PLATINUM 321?

The approved unit plan describes 2 blocks and 340 units of which 334 are homes and 6 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is PLATINUM 321?

About 155 units per acre: 340 planned units across 2.20 acres (8,905 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗