Timeline Bar
Registered16 Oct 2017
Promised22 Jan 2018
Today4 Aug 2026
Timeline
Promised completion22 Jan 2018
Revised completion22 Jan 2018
Actual completion—
Possession delay102 mo delay
Registration & Cost Details
Registration fee (in ₹)₹20,500
Project cost (in ₹ Lakhs)₹450 Lakhs
Project duration61 months
Project categoryResidential
Locality—
Original start date12 Jan 2013
Proposed start date12 Jan 2013
Inventory
Total units120
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 60 | 237.99 |
| 3 BHK | 60 | 306.84 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9999536689
Emaildhanvershabuilders@ymail.com
Coordinator9999536115
Address4/1733, Bhola Nath Nagar,
Shahdara, Delhi – 110032.
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 12517 | 12 May 2012 | 11 May 2017 | 31 Jan 2018 | 11 May 2020 |
| 12517 | 12 May 2012 | 11 May 2017 | 31 Jan 2018 | 11 May 2020 |
| 12517 | 12 May 2012 | 11 May 2017 | 22 Jan 2018 | 11 May 2020 |
| 12517 | 12 May 2012 | 11 May 2017 | 22 Jan 2018 | 11 May 2020 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 548 | 16440 | — |
| 548 | 3100 | Khasra |
Approved Unit Plan
Unit plan rows on file30
Total flats (sum of rows)120
BlocksRIVER HEIGHT - 18
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 9635 | 29 Sept 2011 | — | — |
Frequently Asked Questions
What is the RERA registration number of RIVER HEIGHT TOWER - 18?
The RERA registration number of RIVER HEIGHT TOWER - 18 is UPRERAPRJ6739, as recorded on the UP-RERA portal.
What is the RERA status of RIVER HEIGHT TOWER - 18?
As reported by UP-RERA, the status of RIVER HEIGHT TOWER - 18 is "Registered".
Where is RIVER HEIGHT TOWER - 18 located?
As reported to UP-RERA, RIVER HEIGHT TOWER - 18 is located at Ghaziabad, Ghaziabad, Uttar Pradesh.
When will RIVER HEIGHT TOWER - 18 be completed?
The latest completion date reported to UP-RERA for RIVER HEIGHT TOWER - 18 is 22 Jan 2018.
Is RIVER HEIGHT TOWER - 18 delayed?
Measured against the latest completion date reported to UP-RERA, RIVER HEIGHT TOWER - 18 is 102 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026