PURVANCHAL SKYLINE VISTA

UPRERARegistered

PURVANCHAL SKYLINE VISTA is a RERA-registered commercial project by PURVANCHAL PROJECTS PRIVATE LIMITED in SECTOR 94, NOIDA, Gautam Budh Nagar (RERA ID UPRERAPRJ770757). Registered with a completion deadline of 20 Oct 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
24.55%Q3'25
28.91%Q4'25
18.13%Q1'26
19.72%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ770757
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start18 Dec 2023
Project duration59 months
AddressPLOT NO. 01 A, SECTOR 94, NOIDA, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressLSC, A-7, 2nd FLOOR, PURVANCHAL PLAZA, MAYUR VIHAR, PHASE-II, DELHI-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Feb 2024
Original completion20 Oct 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,11,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors512 · 1 · 38 (units from plan)
Homes · commercial units274 · 238 (shops and offices filed in the same plan)
  • OTHER274 54%
  • SHOP238 46%
ConfigurationUnitsCarpet area
OTHER27436-125
SHOP2386-246
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · OTHER, SHOP385126-1,076
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 329.25 m² for a OTHER, 329.15 m² for a OTHER, 332.59 m² for a OTHER and 8 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ARUN PATWAL
License CA/88/11752
DEVELOPMENTS CONSULTANT, 209 -C, MASJID MOTH ( OPP R BLOCK SOUTH EXTENSION PART -2, NEW DELHI 110049
Engineer
DR. MAQSUD E NAZAR
NNC DESIGN INTERNATIONAL, G70 2 FLOOR, JASWANT PLAZA, SHAHEEN BAGH, OKHLA , NEW DELHI - 110025
Contractor
PURVANCHAL PROJECTS PRIVATE LIMITED
PURVANCHAL BUSINESS WORLD, A 103, SECTOR 136, NOIDA 201305 (U.P)
Sr.Development work declared to RERA
1Demarcation of Plots
Two sides open plot with 24 meter wide road on One side and 45 meter wide sector road on other side. Proper demarcation of plot is completed as per approved layout of the competant authority.
2Boundary Wall
Boundary wall of the said plot will be constructed with the combination of RCC columns and brick wall in between. It will be finished with red sand stone annd MS grill.
3Road Work
7.5 and 9 Meter drive way will be provided in trimix concrete road. On top of this, a layer finish of cement concrete pavement tiles / stamped concreting will be done.
4Footpaths
Footpaths inside the complex will be constructed with a mix of colored cement concrete and a combination of checkered tiles and granite.
5Water Supply Including Drinking Water Facilities
The water supply of desired quality and purity will be provided through over head tanks up to each unit through treated water, supplied by central water supply from development authority.
6Sewer System
The Proper provision of sever line has been provided as per norms and bye laws of development authority. Sewage treament plant of suitable capacity will be established.
7Drain
The proper provision of drainge has been provided as per norms and bye laws of development authority. A well designed drainage system connected to the sewage treatment plant of suitable capacity will be estabilished.
8Parks
NA
9Tree Planting
Trees will be planted inside the complex in accordance with the approved drawings from the development authority.
10Design For Electric Supply Including Street Lighting
Designer electric poles, LE lights to be provided. All electrical related workings will be according to the bureau of Indian standards, Indian electricity rules etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
The proper provision for treatment and disposal of sewage and sullage water will be provied in accordance with the norms and bye-laws of development authority. The sewage treatment plant of suitable capicity will be estabilised for the treatment and disposal of sewage and sullage water, provision are provided for recycled water to be used in flusing and irrigation works.
13Solid Waste Management And Disposal System
The proper provision for solid waste management and disposal system will be provided in accordance with the norms and bye-laws of development authority.
14Water Conservation System
All guidelines and bye-laws of competent authority will be followed for the conservation of natural water. Rainwater harvesting system will be provided in accordance with the approved maps and layouts from the development authority.
15Energy Management System Including Use of Renewable Energy
Partial solar energy will be utilized as per the bye-laws of competent authority and as per approved building plans.
16Fire Protection And Fire Safety System
All rules annd regulations of NBC is being followed. Water sprinklers system with automatic upright / pendent side wall sprinklers on each floor as per the national building code - 2016. Intelligent fire detection and alarm system in the entire building will be provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
Fire staircase has been provided on each floor for emergency evacuation. Intelligent fire detection and alarm system with emergency voice evacuation system will be installed.
19Other Miscellaneous Work
Provision for mechanical car parking system in all three basements will be installed as per the approved drawings from competent authority.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

13 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2BRICKLAND CONSULTING PVT LTDUPRERAAGT21208
3CAPITALBOON CONSULTINGUPRERAAGT18663
4ORANGE DOOR INFRA PRIVATE LIMITEDUPRERAAGT15693
5PC MANTRA INFOSYSTEM PVT. LTD.UPRERAAGT10580
6Propertypistol Realty Pvt LtdUPRERAAGT12730
7REALTY ASSISTANT PRIVATE LIMITED (Formerly REALTY ASSISTANTS HUB PVT LTD)UPRERAAGT18286
8Sapphire EstateUPRERAAGT12673
9SMC Real Estate Advisors Private LimitedUPRERAAGT10113
10SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
11star estateUPRERAAGT10202
12vardhanam Infratech pvt ltdUPRERAAGT15161
13WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 20 Oct 2028. 2 of them carry a revalidation, the latest valid to 1 Jun 2031.

Sanctioned by Noida Authority · 10,031 sqm of land · an approved plan of 1 block and 512 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
2023/08/19/943721 Oct 202320 Oct 202815 Feb 203020 Oct 2028—
2023/08/19/943721 Oct 202320 Oct 20281 Jun 203320 Oct 202821 Oct 2023
valid to 1 Jun 2031
2023/08/19/943721 Oct 202320 Oct 20281 Jun 203320 Oct 202821 Oct 2023
valid to 1 Jun 2031
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
01/A, SECTOR 94, NOIDA10031Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 974
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New4 Jan 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New20 Dec 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New4 Jan 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New20 Dec 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New4 Jan 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New20 Dec 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New20 Dec 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New20 Dec 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 Dec 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New20 Dec 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New20 Dec 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 Dec 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New20 Dec 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New5 Jan 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New20 Dec 2023 ↗

Quarterly progress reports

12 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

12 quarterly progress reports are on file with UPRERA, covering 2023-Q3 to 2026-Q2.

QuarterConstructionCertificates
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q224.55%CA ↗ · Arch ↗ · Eng ↗
2025-Q328.91%CA ↗ · Arch ↗ · Eng ↗
2025-Q418.13%CA ↗ · Arch ↗ · Eng ↗
2026-Q119.72%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePURVANCHAL PROJECTS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM73757
PANAAFCP4046B
CIN / TANU70102DL2010PTC200716
Name of chairmanSHAH ALAM
Registered addressLSC, A-7, 2nd FLOOR, PURVANCHAL PLAZA, MAYUR VIHAR, PHASE-II, DELHI-110092
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PPPL COLLECTION AC FOR SKYLINE VISTABankHDFC BANKBranchSECTOR 18 NOIDABranch addressANSALS FORTUNE ARCADE K BLOCK SECTOR 18 NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088Branch emailneelam.bisht@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PPPL SEPARATE BANK AC FOR SKYLINE VISTABankHDFC BANKBranchSECTOR 18 NOIDABranch addressANSALS FORTUNE ARCADE , K BLOCK SECTOR 18 NOIDA UP 201305Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PPPL RERA TRANSCTION AC FOR SKYLINE VISTABankHDFC BANKBranchNOIDA SECTOR 18Branch addressK BLOCK SECTOR 18 NOIDA UP 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
21 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about PURVANCHAL SKYLINE VISTA

Is PURVANCHAL SKYLINE VISTA RERA registered?

Yes. PURVANCHAL SKYLINE VISTA is registered with UPRERA under registration number UPRERAPRJ770757, registered on 24 Feb 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for PURVANCHAL SKYLINE VISTA?

The completion date filed with UPRERA is 20 Oct 2028. No completion certificate is on record yet.

Who is the builder of PURVANCHAL SKYLINE VISTA?

PURVANCHAL PROJECTS PRIVATE LIMITED is the promoter entity that filed PURVANCHAL SKYLINE VISTA with UPRERA (promoter RERA ID UPRERAPRM73757). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does PURVANCHAL SKYLINE VISTA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is PURVANCHAL SKYLINE VISTA located?

PURVANCHAL SKYLINE VISTA is registered in SECTOR 94, NOIDA, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in PURVANCHAL SKYLINE VISTA?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in PURVANCHAL SKYLINE VISTA?

The approved unit plan filed with UPRERA runs from 6 to 246 m² of carpet area (about 60 to 2,646 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in PURVANCHAL SKYLINE VISTA?

The approved unit plan describes 1 block and 512 units of which 274 are homes and 238 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is PURVANCHAL SKYLINE VISTA?

About 207 units per acre: 512 planned units across 2.48 acres (10,031 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗