Registered25 Jan 2025
Today3 Aug 2026
Promised31 Dec 2026

Timeline

Promised completion31 Dec 2026
Revised completion31 Dec 2026
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,02,000
Project cost (in ₹ Lakhs)₹7,412 Lakhs
Project duration24 months
Project categoryCommercial
LocalitySECTOR-5
Original start date
Proposed start date1 Jan 2025

Inventory

Total units57
Unit TypeUnitsCarpet Area (sqm)
SHOP3026.48–52.29
OTHER2757.49–151.83

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006403
Helpline9568006429
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q4
2025-Q1
2025-Q244.4%
2025-Q392.2%
2025-Q492.8%
2026-Q192.9%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
B.D.A./RGN SEC-5 COMMERCIAL COMPLEX (BLOCK-A)28 Oct 202427 Oct 202931 Dec 202627 Oct 2032

Land Parcels

Khasra No.AreaPlot Type
19, 20, 22, 23, 24, 25, 26, 27, 309200.35Khasra

Approved Unit Plan

Unit plan rows on file47
Total flats (sum of rows)57
Total shops30
BlocksBLOCK-A
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY?

The RERA registration number of COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY is UPRERAPRJ293273, as recorded on the UP-RERA portal.

What is the RERA status of COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY?

As reported by UP-RERA, the status of COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY is "Registered".

Where is COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY located?

As reported to UP-RERA, COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY is located at RAMGANGA NAGAR SCHEME SECTOR-5, SECTOR-5, Bareilly, Bareilly, Uttar Pradesh.

When will COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY be completed?

The latest completion date reported to UP-RERA for COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY is 31 Dec 2026.

Is COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY delayed?

Measured against the latest completion date reported to UP-RERA, COMMERCIAL COMPLEX (BLOCK-A) AT SECTER-5 RAMGANGA NAGAR SCHEME, BAREILLY is on time.