Registered10 Jul 2024
Completed21 May 2026
Promised9 Jan 2028

Timeline

Promised completion9 Jan 2028
Revised completion9 Jan 2028
Actual completion21 May 2026
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,06,500
Project cost (in ₹ Lakhs)₹2,534 Lakhs
Project duration45 months
Project categoryResidential
LocalityManoharpur
Original start date
Proposed start date1 May 2024

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeIndividual
Mobile9897890212
Emailrehmanafeefur20@gmail.com
Coordinator9821128428
AddressS/O Mehboob Ur Rehman, MEBA Brass, Pandat Nagla Bypass, Sambhal road, Moradabad 244001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q1
2024-Q280.0%
2024-Q380.0%
2024-Q480.0%
2025-Q180.0%
2025-Q280.0%
2025-Q392.0%
2025-Q4100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
MBDA/LD/21-22/056610 Jan 20239 Jan 20289 Jan 20289 Jan 2028

Land Parcels

Khasra No.AreaPlot Type
59, 60, 63, 64, 65, 66, 6720213.74Khasra

Frequently Asked Questions

What is the RERA registration number of Regency Green?

The RERA registration number of Regency Green is UPRERAPRJ342605, as recorded on the UP-RERA portal.

What is the RERA status of Regency Green?

As reported by UP-RERA, the status of Regency Green is "Registered".

Where is Regency Green located?

As reported to UP-RERA, Regency Green is located at Village- Manoharpur, Delhi road, Tehsil and DIstrict- Moradabad - 244001, Khasara No- 59, 60, 63, 64, 65, 66, 67, Manoharpur, Moradabad, Moradabad, Uttar Pradesh.

Is Regency Green completed?

As reported to UP-RERA, Regency Green was completed on 21 May 2026.

Is Regency Green delayed?

Measured against the latest completion date reported to UP-RERA, Regency Green is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026