RICHMOND HOMEZUPRERADelayed 84 mo
Home › Projects › Meerut › RICHMOND HOMEZ

RICHMOND HOMEZ

UPRERADelayed 84 moRegisteredupdated 4 Aug 2026

RICHMOND HOMEZ is a RERA-registered real-estate project in Meerut (RERA ID UPRERAPRJ4513). Its RERA-registered completion deadline (25 Jul 2019) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
84 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹20
Land area
not reported
Units (from plan)
35
Density (derived)
not reported
Towers
not reported
Config
3 BHK/OTHER
Carpet
1,156–1,281
Registered
8 Aug 2017

Basic details

RERA IDUPRERAPRJ4513
Applicant typePartnership Firm
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start24 Apr 2013
Project duration76
AddressMeerut, Meerut

Registration & timeline

RERA registered8 Aug 2017
Promised completion25 Jul 2019
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹20,000

Inventory

derived from unit plan
Total units · towers · floors35 · 1 · 6 (units from plan)
ConfigurationUnitsCarpet area
3 BHK351,156–1,281
Towers as filed1
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

3 permits
Permit no.DateValid uptoRevised end
1410/1230 Jan 201329 Jan 201825 Jul 2019
1410/1230 Jan 201329 Jan 201825 Jul 2019
1410/1230 Jan 201329 Jan 201825 Jul 2019

Nearby projects

Meerut

Other projects registered in Meerut.

"Ornate"
UPRERA ▲ 76 mo
131/144 Type Duplex and 69/142 Type Residential Houses in Sector-3, Scheme No. 11, Jagriti Vihar (Ext.), Meerut
UPRERA ▲ 15 mo
528 FLATS IN AIRPORT ENCLAVE, SECTOR-10, SHATABDI NAGAR, MEERUT
UPRERA ▲ 67 mo
A2Z COLONY
UPRERA no delay on record
Aashiyana Green Wood
UPRERA ▲ 16 mo
Abdullah Residency and Shoping Plaza
UPRERA no delay on record

Common questions about RICHMOND HOMEZ

Is RICHMOND HOMEZ RERA registered?

Yes. RICHMOND HOMEZ is registered with UPRERA under registration number UPRERAPRJ4513, registered on 8 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Is RICHMOND HOMEZ delayed?

RICHMOND HOMEZ is 84 months past the completion date filed with UPRERA (25 Jul 2019), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is RICHMOND HOMEZ located?

RICHMOND HOMEZ is registered in Meerut, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 84 mo
QPR filingNo default reported
DistrictMeerut
Last updated4 Aug 2026

Location

AddressMeerut
View on map ↗

RERA buyer helpline

Coordinator9690509404
official grievance contact, as published by RERA