RUDRAKSH APARTMENTS is a RERA-registered residential project by Real Image Developers Pvt. Ltd. in Bareilly (RERA ID UPRERAPRJ13686). Registered with a completion deadline of 2 Sept 2021. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ13686 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Bareily Development Authority |
| Proposed start | 4 Mar 2013 |
| Original start | 20 Feb 2013 |
| Project duration | 102 months |
| Address | Bareilly, Bareilly |
| Tehsil | Bareilly |
| Applicant type | Company |
| Applicant address | 1, TULSI NAGAR, PILIBHIT BYPASS ROAD, BAREILLY |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
2 building permits sanctioned
Registered with RERA
- valid to
Permit revalidated
180/01/GH/12
- valid to
Permit revalidated
180/01/GH/12
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 18 Oct 2017 |
| Original completion | 3 Mar 2021 |
| Revised completion | 2 Sept 2021 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹28,000 |
| Sanctioning authority | Bareily Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK64 67%
- 2 BHK32 33%
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 64 | 111 |
| 2 BHK | 32 | 93 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| A · 3 BHK | 8 | 32 | 111 |
| B · 2 BHK, 3 BHK | 8 | 32 | 93-111 |
| C · 2 BHK, 3 BHK | 8 | 32 | 93-111 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Not applicable being multi storey apartments |
| 2 | Boundary Wall Boundary wall 7 ft. tall |
| 3 | Road Work Well connected with Roads |
| 4 | Footpaths Sufficient walking tracks available as per approved plan |
| 5 | Water Supply Including Drinking Water Facilities Drinking water facility supplied through overhead tanks. |
| 6 | Sewer System Sewage treatment plant available at site as per approved plan |
| 7 | Drain Proper drainage system available as per approved plan |
| 8 | Parks Available as per approved plan |
| 9 | Tree Planting Sufficient |
| 10 | Design For Electric Supply Including Street Lighting Sufficient |
| 11 | Community Buildings Club house facility available |
| 12 | Treatment and Disposal System of Sewage and Sullage water Sewage treatment plant installed at site as per approved plan |
| 13 | Solid Waste Management And Disposal System Solid waste collection facility available |
| 14 | Water Conservation System Rain Water harvesting pits built for conservation as per approved plan |
| 15 | Energy Management System Including Use of Renewable Energy Not Available |
| 16 | Fire Protection And Fire Safety System Hose reel, fire extinguishers, fire alarm system, fire hydrants available |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Not available at site but available nearby within 1 km radius |
| 18 | Emergency Evacuation Services Balcony, Multiple staircases etc. are available as per approved plan |
| 19 | Other Miscellaneous Work Swimming pool, Power backup, Gym etc, available |
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 26 Nov 2018. All 2 carry a revalidation, the latest valid to 3 Mar 2021.
Sanctioned by Bareily Development Authority · 4,572 sqm of land · an approved plan of 3 blocks and 96 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 180/01/GH/12 | 26 Nov 2013 | 26 Nov 2018 | 3 Mar 2021 | 3 Mar 2021 | 26 Nov 2019 valid to 3 Mar 2021 | |
| 180/01/GH/12 | 26 Nov 2013 | 26 Nov 2018 | 3 Mar 2021 | 3 Mar 2021 | 26 Nov 2018 valid to 3 Mar 2021 |
| Document | File |
|---|---|
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 2 Sept 2021.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 3 Mar 2021 | 2 Sept 2021 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
9 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 250,251,252 | 4572 | — |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 6 Sept 2012.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 5180 | 6 Sept 2012 | self | — |
| Registry document · 10187 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 10188 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 18 Oct 2017 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | Old | 18 Oct 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 18 Oct 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AVAILABLE |
| Fire safety (as filed with RERA) | FIRE WATER CAPACITY - 75KL |
| Health service | NOT INCLUDED IN PROJECT, HOWEVER AVAILABLE NEARBY |
| Renewable energy | NOT AVAILABLE |
| Other facilities | SWIMMING POOL |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Real Image Developers Pvt. Ltd. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM25799 |
| PAN | AAECR3724M |
| CIN / TAN | U45400UP2009PTC037546 |
| Name of chairman | MR. RAKESH KUMAR |
| Registered address | 1, TULSI NAGAR, PILIBHIT BYPASS ROAD, BAREILLY |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Bareilly
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | REAL IMAGE DEVELOPERS PVT. LTD.BankHDFC BANKBranchPILIBHIT BYPASS, BAREILLYA/C no.IFSCHDFC0004463 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
Common questions about RUDRAKSH APARTMENTS
Is RUDRAKSH APARTMENTS RERA registered?
Yes. RUDRAKSH APARTMENTS is registered with UPRERA under registration number UPRERAPRJ13686, registered on 18 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for RUDRAKSH APARTMENTS?
The completion date filed with UPRERA is 2 Sept 2021. No completion certificate is on record yet.
Who is the builder of RUDRAKSH APARTMENTS?
Real Image Developers Pvt. Ltd. is the promoter entity that filed RUDRAKSH APARTMENTS with UPRERA (promoter RERA ID UPRERAPRM25799). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Why does RUDRAKSH APARTMENTS show "default on QPR"?
UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.
Has UPRERA granted RUDRAKSH APARTMENTS more time to complete?
UPRERA's record carries 1 completion extension for RUDRAKSH APARTMENTS, the latest running to 2 Sept 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does RUDRAKSH APARTMENTS have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is RUDRAKSH APARTMENTS located?
RUDRAKSH APARTMENTS is registered in Bareilly, as filed with UPRERA.
What configurations are available in RUDRAKSH APARTMENTS?
The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in RUDRAKSH APARTMENTS?
The approved unit plan filed with UPRERA runs from 93 to 111 m² of carpet area (about 1,001 to 1,195 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in RUDRAKSH APARTMENTS?
The approved unit plan describes 3 blocks and 96 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is RUDRAKSH APARTMENTS?
About 85 units per acre: 96 planned units across 1.13 acres (4,572 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗