SKA ARCADIA is a RERA-registered commercial project by KAMROOP PROMOTERS LLP in Ghaziabad (RERA ID UPRERAPRJ228610). Registered with a completion deadline of 30 Oct 2027.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ228610 |
| Project category | Commercial |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Ghaziabad Development Authority |
| Proposed start | 30 Nov 2022 |
| Project duration | 60 months |
| Address | Ghaziabad, Ghaziabad |
| Tehsil | Ghaziabad |
| Applicant type | Partnership Firm |
| Applicant address | 12th floor, Anthurium Tower, Plot 03, sector 73 Noida Gautam Buddha Nagar Uttar Pradesh 201301 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
GDA/BP/22-23/0828
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion certificate filed
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 20 Dec 2022 |
| Original completion | 30 Oct 2027 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 24 Sept 2025 |
| Registration fee | ₹89,000 |
| Sanctioning authority | Ghaziabad Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 722 | 6-44 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| SKA ARCADIA · OTHER, SHOP | 6 | 722 | 6-44 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots will be done by total station |
| 2 | Boundary Wall Boundary wall of 1800 mm height will be constructed with RCC columns , brickwork etc. |
| 3 | Road Work Internal road will be constructed with RCC trimix , Pavers and Stone |
| 4 | Footpaths Foot path will be constructed with pavers and stone. |
| 5 | Water Supply Including Drinking Water Facilities Water Supply up to the boundary of Plot is provided by Wave city . Internal distribution will be done by us with PVC / UPVC / GI pipes.Drawing enclosed. |
| 6 | Sewer System Sewer System up to boundry of plot is provided by Wave city. Internal sewer system will be constructed by us and connected to this system . The Sewer will be constructed by RCC/ PVC pipes . Drawing enclosed |
| 7 | Drain Strom water drains will be constructed with RCC/ brickwork/ PVC pipes as per drawing enclosed. The external drain system is provided by Wave city . |
| 8 | Parks NA as it is a small commercial plot. |
| 9 | Tree Planting total 79 local trees will be planted |
| 10 | Design For Electric Supply Including Street Lighting The design of Electrical supply will be done as per norms |
| 11 | Community Buildings NA as it is a commercial building. |
| 12 | Treatment and Disposal System of Sewage and Sullage water A STP based on MBR of 150KLD will be installed for treatment of sewer and treated water will be used for flushing and AC purpose. |
| 13 | Solid Waste Management And Disposal System Biodegradable solid waste will be composted in OWC and used as manure. Other solid waste will be disposed as per Municipal solid waste management by CPHEEO |
| 14 | Water Conservation System Rain water will be diverted to RWH for water table recharging in two RWH pits.
STP treated water will be used in flushing and AC purpose. |
| 15 | Energy Management System Including Use of Renewable Energy 50 percent of common area lighting of basement will be done through solar power panel ( Renewable energy). Energy saving will be done by LED lighting, 3star rated pump and electric motors |
| 16 | Fire Protection And Fire Safety System Fire Protection and safety work will be done as per FIRE NOC and rules |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA as it is a small commercial project.However public rest room , Lift and Escalator will be provided |
| 18 | Emergency Evacuation Services As per Fire NOC and rules |
| 19 | Other Miscellaneous Work The construction will be done as per specification of project |
Registered agents
3 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | Black Opal Consultants Limited(formerly known as Black Opal Consultant Private Limited) | UPRERAAGT20706 |
| 2 | GOLDHOMZ DEVELOPERS PVT LTD | UPRERAAGT23371 |
| 3 | PROPSHOP | UPRERAAGT10129 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 30 Oct 2027.
Sanctioned by Ghaziabad Development Authority · 7,861 sqm of land · an approved plan of 1 block and 722 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| GDA/BP/22-23/0828 | 31 Oct 2022 | 30 Oct 2027 | 30 Oct 2029 | 30 Oct 2027 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
18 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| Commercial Plot 1D | 7860.61 | Plot |
| Sale deed · 7872 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 6 Dec 2022 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 6 Dec 2022 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 6 Dec 2022 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 4 Nov 2022 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 4 Nov 2022 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 3 Nov 2022 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 3 Nov 2022 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 3 Nov 2022 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 3 Nov 2022 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 22 Nov 2022 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 22 Nov 2022 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 4 Nov 2022 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 22 Nov 2022 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 3 Nov 2022 ↗ |
Quarterly progress reports
16 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
16 quarterly progress reports are on file with UPRERA, covering 2022-Q3 to 2026-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 78.61% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 80% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 95% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 100% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | KAMROOP PROMOTERS LLP |
| Role | Promoter · current |
| RERA ID | UPRERAPRM203619 |
| PAN | AAYFK8543J |
| CIN / TAN | MRTK06092C |
| Registered address | 12th floor, Anthurium Tower, Plot 03, sector 73 Noida Gautam Buddha Nagar Uttar Pradesh 201301 |
| RERA contact | |
| Registered since | 2022 |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | KAMROOP PROMOTERS LLP COLLECTION ACCOUNT FOR SKA ARCADIABankHDFC BANK LTDBranchLOHIA NAGARBranch addressC-9, Lohiya Nagar, GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0004833 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | KAMROOP PROMOTERS LLP SEPARATE ACCOUNT FOR SKA ARCADIABankHDFC BANK LTDBranchLOHIA NAGARBranch addressC-9, LOHIA NAGARBranch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0004833 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | KAMROOP PROMOTERS LLP TRANSACTION ACCOUNT FOR SKA ARCADIABankHDFC BANK LTDBranchLOHIA NAGARBranch addressC-9,Lohia Nagar, GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCHDFC0004833 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Quarterly progress report 2026-Q2 | QPR 2026-Q2 newly filed with RERA | 18 Oct 2026 |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about SKA ARCADIA
Is SKA ARCADIA RERA registered?
Yes. SKA ARCADIA is registered with UPRERA under registration number UPRERAPRJ228610, registered on 20 Dec 2022. Estanzo reproduces that filing; it does not verify the work behind it.
Has SKA ARCADIA been completed?
UPRERA still lists SKA ARCADIA as Registered, so it is not shown as completed here. A completion certificate dated 24 Sept 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of SKA ARCADIA?
KAMROOP PROMOTERS LLP is the promoter entity that filed SKA ARCADIA with UPRERA (promoter RERA ID UPRERAPRM203619). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does SKA ARCADIA have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is SKA ARCADIA located?
SKA ARCADIA is registered in Ghaziabad, as filed with UPRERA.
What configurations are available in SKA ARCADIA?
The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in SKA ARCADIA?
The approved unit plan filed with UPRERA runs from 6 to 44 m² of carpet area (about 65 to 470 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in SKA ARCADIA?
The approved unit plan describes 1 block and 722 units of which 0 are homes and 722 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is SKA ARCADIA?
About 372 units per acre: 722 planned units across 1.94 acres (7,861 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗