Timeline Bar
Registered7 Jun 2018
Promised26 May 2024
Completed22 May 2026
Timeline
Promised completion26 May 2024
Revised completion26 May 2024
Actual completion22 May 2026
Possession delay24 mo delay
Registration & Cost Details
Registration fee (in ₹)₹1,05,500
Project cost (in ₹ Lakhs)₹3,300 Lakhs
Project duration75 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Sept 2018
Inventory
Total units1102
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 378 | 48.72–54.34 |
| 3 BHK | 576 | 59.84–70.36 |
| 4 BHK | 112 | 91.6 |
| SHOP | 36 | 11.64–25.04 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8860021835
Emailrite2rajan28@gmail.com
Coordinator9999557711
AddressThe Corenthum
134, Tower-A , 3rd Floor, SEC-62
NOIDA
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| bp/4336/letter no 3439 | 28 May 2018 | 27 May 2024 | 26 May 2024 | — |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| GH01B(3) ITA II G noida | 20073.9 | Plot |
Approved Unit Plan
Unit plan rows on file326
Total flats (sum of rows)1102
Total shops36
BlocksASTER, Local Shopping complex, Zinnia, orchid, tulip
Floor types2 BHK, 3 BHK, 4 BHK, SHOP, OTHER
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of SKA metro Ville?
The RERA registration number of SKA metro Ville is UPRERAPRJ16460, as recorded on the UP-RERA portal.
What is the RERA status of SKA metro Ville?
As reported by UP-RERA, the status of SKA metro Ville is "Registered".
Where is SKA metro Ville located?
As reported to UP-RERA, SKA metro Ville is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
Is SKA metro Ville completed?
As reported to UP-RERA, SKA metro Ville was completed on 22 May 2026.
Is SKA metro Ville delayed?
Measured against the latest completion date reported to UP-RERA, SKA metro Ville is 24 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026