SPEEDWAY AVENUE is a RERA-registered residential project by PYRAMID TOWNSHIPS PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ12128). Registered with a completion deadline of 21 Feb 2019.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ12128 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Yamuna Expressway Authority |
| Proposed start | 1 May 2016 |
| Original start | 1 May 2016 |
| Project duration | 34 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | PYRAMID TOWNSHIPS PRIVATE LIMITED. A-14, KAILASH COLONY , NEW DELHI-110048 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated (2)
3 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 18 Oct 2017 |
| Original completion | 21 Feb 2019 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹54,000 |
| Sanctioning authority | Yamuna Expressway Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK125 46%
- 3 BHK110 40%
- OTHER22 8%
- 4 BHK16 6%
| Configuration | Units | Carpet area |
|---|---|---|
| 2 BHK | 125 | 53-73 |
| 3 BHK | 110 | 70-110 |
| OTHER | 22 | 103-218 |
| 4 BHK | 16 | 135 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| 1B · 2 BHK, 3 BHK, OTHER | 18 | 83 | 63-149 |
| 2B · 2 BHK, 3 BHK, OTHER | 18 | 102 | 53-137 |
| 3B · 3 BHK, 2 BHK, 4 BHK, OTHER | 18 | 88 | 58-218 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots work not start till date |
| 2 | Boundary Wall work not start till date |
| 3 | Road Work work not start till date |
| 4 | Footpaths work not start till date |
| 5 | Water Supply Including Drinking Water Facilities work not start till date |
| 6 | Sewer System work not start till date |
| 7 | Drain work not start till date |
| 8 | Parks work not start till date |
| 9 | Tree Planting work not start till date |
| 10 | Design For Electric Supply Including Street Lighting work not start till date |
| 11 | Community Buildings work not start till date |
| 12 | Treatment and Disposal System of Sewage and Sullage water work not start till date |
| 13 | Solid Waste Management And Disposal System work not start till date |
| 14 | Water Conservation System work not start till date |
| 15 | Energy Management System Including Use of Renewable Energy work not start till date |
| 16 | Fire Protection And Fire Safety System work not start till date |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services work not start till date |
| 18 | Emergency Evacuation Services work not start till date |
| 19 | Other Miscellaneous Work work not start till date |
Registered agents
3 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | ABHAY PRATAP SINGH | UPRERAAGT10207 |
| 3 | ADVENTURES ENTERPRISES PVT LTD | UPRERAAGT11208 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 21 Feb 2019. 2 of them carry a revalidation, the latest valid to 2 Nov 2022.
Sanctioned by Yamuna Expressway Authority · 9,715 sqm of land · an approved plan of 3 blocks and 273 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| BB 49/1092 | 26 Nov 2014 | 21 Feb 2019 | 21 Feb 2019 | 21 Feb 2019 | — | |
| BB 49/1092 | 26 Nov 2014 | 21 Feb 2019 | 2 Nov 2022 | 1 Nov 2022 | 26 Nov 2014 valid to 2 Nov 2022 | |
| BB 49/1092 | 26 Nov 2014 | 21 Feb 2019 | 2 Nov 2022 | 1 Nov 2022 | 26 Nov 2014 valid to 2 Nov 2022 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
Land & documents
17 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| GH-A3 ,SEC-25 | 9715 | — |
| GH A3 | 9714 | Plot |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 9 Apr 2014.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 12045 | 9 Apr 2014 | self | — |
| Registry document · 12045 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Lease deed · 12045 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 31 Jul 2018 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 31 Jul 2018 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 31 Jul 2018 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 31 Jul 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 31 Jul 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 31 Jul 2018 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 31 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 31 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 31 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 31 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 31 Jul 2018 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 21 Aug 2017 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 21 Aug 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AS PER LAYOUT PLAN |
| Fire safety (as filed with RERA) | AS PER FIRE APPROVAL |
| Health service | AS PER LAYOUT PLAN |
| Renewable energy | AS PER LAYOUT PLAN |
| Other facilities | CLUB FACILITY |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | PYRAMID TOWNSHIPS PRIVATE LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM15869 |
| PAN | AAHCP0395F |
| CIN / TAN | U45204DL2012PTC241978 |
| Name of chairman | ANIL KUMAR VASWANI |
| Registered address | PYRAMID TOWNSHIPS PRIVATE LIMITED. A-14, KAILASH COLONY , NEW DELHI-110048 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | PYRAMID TOWNSHIP PRIVATE LIMITEDBankPUNJAB NATIONAL BANKBranchSARITA VIHARA/C no.IFSCPUNB0397600 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
Common questions about SPEEDWAY AVENUE
Is SPEEDWAY AVENUE RERA registered?
Yes. SPEEDWAY AVENUE is registered with UPRERA under registration number UPRERAPRJ12128, registered on 18 Oct 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for SPEEDWAY AVENUE?
The completion date filed with UPRERA is 21 Feb 2019. No completion certificate is on record yet.
Who is the builder of SPEEDWAY AVENUE?
PYRAMID TOWNSHIPS PRIVATE LIMITED is the promoter entity that filed SPEEDWAY AVENUE with UPRERA (promoter RERA ID UPRERAPRM15869). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does SPEEDWAY AVENUE have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is SPEEDWAY AVENUE located?
SPEEDWAY AVENUE is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in SPEEDWAY AVENUE?
The unit plan filed with UPRERA lists 2 BHK, 3 BHK, OTHER and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in SPEEDWAY AVENUE?
The approved unit plan filed with UPRERA runs from 53 to 218 m² of carpet area (about 570 to 2,347 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in SPEEDWAY AVENUE?
The approved unit plan describes 3 blocks and 273 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is SPEEDWAY AVENUE?
About 114 units per acre: 273 planned units across 2.40 acres (9,715 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗