STELLAR ONE PHASE II is a RERA-registered residential project by Stellar Spring Projects Private Limited in SECTOR-01, Gautam Budh Nagar (RERA ID UPRERAPRJ923780). Registered with a completion deadline of 15 Nov 2028.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ923780 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Greater Noida Authority |
| Proposed start | 1 Nov 2023 |
| Project duration | 61 months |
| Address | PLOT NO -GH-09, SECTOR-01, Dadri, Gautam Budh Nagar |
| Tehsil | Dadri |
| Applicant type | Company |
| Applicant address | Registered Office - B-29, Sheikh Sarai, Phase -1, New Delhi-110017 Corporate Office - C 56/9, Sector 62, Noida, U.P.-201309 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
PLG/(BP)3475/947
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 30 Dec 2023 |
| Original completion | 15 Nov 2028 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,14,500 |
| Sanctioning authority | Greater Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK432 81%
- 4 BHK76 14%
- 2 BHK24 5%
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 432 | 96-108 |
| 4 BHK | 76 | 145 |
| 2 BHK | 24 | 70 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| L · 2 BHK, 3 BHK | 19 | 152 | 70-108 |
| M · 2 BHK, 3 BHK | 19 | 152 | 70-108 |
| N · 3 BHK, 2 BHK | 19 | 152 | 70-108 |
| P · 4 BHK | 19 | 76 | 145 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots North East side 24m wide road, South West side Plot no. GH-10, South East side Stellar One Phase I, North West side 60m wide road. Temporary barricading between each phase boundary.
Plot Area of Stellar One Phase II is 21,887.952 Sq. m. and is part of the Total Plot Area 64,803 Sq. m. at GH-09, Sector-1, Greater Noida (West) U. P. allotted by Greater Noida Authority. The Demarcation of total plot area and and Stellar One Phase II plot is attached with layout plan. |
| 2 | Boundary Wall 2100 mm high boundary wall with a combination of RCC (1000 mm) and MS grill (1100 mm). Temporary barricading between each phase boundary. |
| 3 | Road Work All internal road work in concrete paver blocks/VDF. |
| 4 | Footpaths Footpath/Pathway provided as per landscape details. |
| 5 | Water Supply Including Drinking Water Facilities GNIDA Water supply shall be collected in the Underground tank of adequate capacity for Whole Project site already built in Stellar One Phase I as per NBCC 2016. Overhead Domestic tank for each tower shall be filled with pumps to give supply to the units/flats. Water Treatment Plant is provided. |
| 6 | Sewer System PVC pipe of adequate size with manhole, chambers shall be provided. The sewer lines shall be laid in desired slopes as per available invert level. |
| 7 | Drain PVC pipe/R.C.C. Saucer drain with manhole, chambers with Rain Water Harvesting Shall be provided. The number of catch basin shall be provided as per design requirement based on run off. |
| 8 | Parks Landscape with civil work with masonry and stone, horticulture work and various types of plantation, shrubs shall be provided. Native Plants shall be planted. |
| 9 | Tree Planting A variety of trees as per authority and Green Building norms. |
| 10 | Design For Electric Supply Including Street Lighting Pole light will be provided. Design for electric supply has been uploaded. |
| 11 | Community Buildings Community building will be a common facility for all phase of Stellar One project as per approved building plan. Community facility as per approved plan. |
| 12 | Treatment and Disposal System of Sewage and Sullage water 800 KLD S.T.P. shall be provided. It will be provided with collection tank. The Treated water shall be used for irrigation and flushing purposes. |
| 13 | Solid Waste Management And Disposal System Organic Waste convertor and Garbage collection/segregation area is already provided as per authority norms for complete project in Stellar One Phase I. |
| 14 | Water Conservation System Rain water harvesting pits are to provided as per norms of EIA/Authority. |
| 15 | Energy Management System Including Use of Renewable Energy Mix of LED lights shall be used to conserve the energy. |
| 16 | Fire Protection And Fire Safety System As per approved fire drawing smoke detector fire alarm systems etc. Shall be installed. Fire tender path shall be constructed as per fire norms. Fire fighting system with fire pumps of adequate capacity and water storage tanks shall be provided. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Community facility inside project and public amenities in the vicinity. |
| 18 | Emergency Evacuation Services As per approved layout. Staircases shall be provided in basement/towards to exit in case of emergency/fire and/or any natural calamity. |
| 19 | Other Miscellaneous Work As per architects design. |
Registered agents
12 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | Beniwal Associates C/O Ravi Beniwal | UPRERAAGT17023 |
| 3 | BLUECRUMBS INFRA PRIVATE LIMITED | UPRERAAGT16897 |
| 4 | DHEERENDER PANDEY | UPRERAAGT19904 |
| 5 | GOLD BUCKS INFRATECH PRIVATE LIMITED | UPRERAAGT16636 |
| 6 | JOINT BRICKS PROPMART | UPRERAAGT11518 |
| 7 | KAVI KANT | UPRERAAGT24223 |
| 8 | Kishankant Sharma | UPRERAAGT21798 |
| 9 | PROPFIN SOLUTIONS PVT LTD | UPRERAAGT14948 |
| 10 | RAJAT ROHATGI | UPRERAAGT21456 |
| 11 | REAL BRICKS INFRATECH | UPRERAAGT13418 |
| 12 | REDMAPLE BUILDIKO PRIVATE LIMITED | UPRERAAGT14395 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 26 Oct 2028.
Sanctioned by Greater Noida Authority · 21,888 sqm of land · an approved plan of 4 blocks and 532 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| PLG/(BP)3475/947 | 27 Oct 2023 | 26 Oct 2028 | 2 Nov 2033 | 15 Nov 2028 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
18 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| GH-09, Sector-1 | 21887.96 | Plot |
| Lease deed · 26868 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Allotment letter from the authority · PROP/BRS-02/2010/1512 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 29 Nov 2023 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 30 Oct 2023 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 30 Oct 2023 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 30 Oct 2023 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 1 Nov 2023 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 1 Nov 2023 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 1 Nov 2023 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 29 Nov 2023 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 29 Nov 2023 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 29 Nov 2023 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 29 Nov 2023 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 29 Nov 2023 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 2 Dec 2023 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 29 Nov 2023 ↗ |
Quarterly progress reports
11 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
11 quarterly progress reports are on file with UPRERA, covering 2023-Q3 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 54.66% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 65% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 74.66% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 85.86% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Stellar Spring Projects Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM8082 |
| PAN | AAOCS2530C |
| CIN / TAN | U70102DL2010PTC202540 |
| Name of chairman | Mr. Ravi Mohan Sethi |
| Registered address | Registered Office - B-29, Sheikh Sarai, Phase -1, New Delhi-110017 Corporate Office - C 56/9, Sector 62, Noida, U.P.-201309 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | STELLAR SPPL STELLAR ONE PH II COLL A/CBankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | STELLAR SPPL STELLAR ONE PH II SEP A/CBankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | STELLAR SPPL STELLAR ONE PH II TRAN A/C.BankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about STELLAR ONE PHASE II
Is STELLAR ONE PHASE II RERA registered?
Yes. STELLAR ONE PHASE II is registered with UPRERA under registration number UPRERAPRJ923780, registered on 30 Dec 2023. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for STELLAR ONE PHASE II?
The completion date filed with UPRERA is 15 Nov 2028. No completion certificate is on record yet.
Who is the builder of STELLAR ONE PHASE II?
Stellar Spring Projects Private Limited is the promoter entity that filed STELLAR ONE PHASE II with UPRERA (promoter RERA ID UPRERAPRM8082). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does STELLAR ONE PHASE II have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is STELLAR ONE PHASE II located?
STELLAR ONE PHASE II is registered in SECTOR-01, Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in STELLAR ONE PHASE II?
The unit plan filed with UPRERA lists 3 BHK, 4 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in STELLAR ONE PHASE II?
The approved unit plan filed with UPRERA runs from 70 to 145 m² of carpet area (about 755 to 1,559 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in STELLAR ONE PHASE II?
The approved unit plan describes 4 blocks and 532 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is STELLAR ONE PHASE II?
About 98 units per acre: 532 planned units across 5.41 acres (21,888 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗