STELLAR ONE PHASE II

UPRERARegistered

STELLAR ONE PHASE II is a RERA-registered residential project by Stellar Spring Projects Private Limited in SECTOR-01, Gautam Budh Nagar (RERA ID UPRERAPRJ923780). Registered with a completion deadline of 15 Nov 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
54.66%Q3'25
65%Q4'25
74.66%Q1'26
85.86%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ923780
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Nov 2023
Project duration61 months
AddressPLOT NO -GH-09, SECTOR-01, Dadri, Gautam Budh Nagar
TehsilDadri
Applicant typeCompany
Applicant addressRegistered Office - B-29, Sheikh Sarai, Phase -1, New Delhi-110017 Corporate Office - C 56/9, Sector 62, Noida, U.P.-201309
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/(BP)3475/947

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Dec 2023
Original completion15 Nov 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,14,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors532 · 4 · 19 (units from plan)
  • 3 BHK432 81%
  • 4 BHK76 14%
  • 2 BHK24 5%
ConfigurationUnitsCarpet area
3 BHK43296-108
4 BHK76145
2 BHK2470
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
L · 2 BHK, 3 BHK1915270-108
M · 2 BHK, 3 BHK1915270-108
N · 3 BHK, 2 BHK1915270-108
P · 4 BHK1976145
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
SAMEER BALGOTRA
License CA/2018/91953
C-56/9, SECTOR-62, NOIDA,U.P.
Engineer
SANJEEV SHARMA OF MELIOR STRUCTURAL SOLUTIONS PVT LTD
2174, SECTOR-38C, CHANDIGARD,-160014
Contractor
KEYSTONE DEVELOPERS PVT LTD
C-56/9, SECTOR-62, NOIDA, U.P.
Sr.Development work declared to RERA
1Demarcation of Plots
North East side 24m wide road, South West side Plot no. GH-10, South East side Stellar One Phase I, North West side 60m wide road. Temporary barricading between each phase boundary. Plot Area of Stellar One Phase II is 21,887.952 Sq. m. and is part of the Total Plot Area 64,803 Sq. m. at GH-09, Sector-1, Greater Noida (West) U. P. allotted by Greater Noida Authority. The Demarcation of total plot area and and Stellar One Phase II plot is attached with layout plan.
2Boundary Wall
2100 mm high boundary wall with a combination of RCC (1000 mm) and MS grill (1100 mm). Temporary barricading between each phase boundary.
3Road Work
All internal road work in concrete paver blocks/VDF.
4Footpaths
Footpath/Pathway provided as per landscape details.
5Water Supply Including Drinking Water Facilities
GNIDA Water supply shall be collected in the Underground tank of adequate capacity for Whole Project site already built in Stellar One Phase I as per NBCC 2016. Overhead Domestic tank for each tower shall be filled with pumps to give supply to the units/flats. Water Treatment Plant is provided.
6Sewer System
PVC pipe of adequate size with manhole, chambers shall be provided. The sewer lines shall be laid in desired slopes as per available invert level.
7Drain
PVC pipe/R.C.C. Saucer drain with manhole, chambers with Rain Water Harvesting Shall be provided. The number of catch basin shall be provided as per design requirement based on run off.
8Parks
Landscape with civil work with masonry and stone, horticulture work and various types of plantation, shrubs shall be provided. Native Plants shall be planted.
9Tree Planting
A variety of trees as per authority and Green Building norms.
10Design For Electric Supply Including Street Lighting
Pole light will be provided. Design for electric supply has been uploaded.
11Community Buildings
Community building will be a common facility for all phase of Stellar One project as per approved building plan. Community facility as per approved plan.
12Treatment and Disposal System of Sewage and Sullage water
800 KLD S.T.P. shall be provided. It will be provided with collection tank. The Treated water shall be used for irrigation and flushing purposes.
13Solid Waste Management And Disposal System
Organic Waste convertor and Garbage collection/segregation area is already provided as per authority norms for complete project in Stellar One Phase I.
14Water Conservation System
Rain water harvesting pits are to provided as per norms of EIA/Authority.
15Energy Management System Including Use of Renewable Energy
Mix of LED lights shall be used to conserve the energy.
16Fire Protection And Fire Safety System
As per approved fire drawing smoke detector fire alarm systems etc. Shall be installed. Fire tender path shall be constructed as per fire norms. Fire fighting system with fire pumps of adequate capacity and water storage tanks shall be provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Community facility inside project and public amenities in the vicinity.
18Emergency Evacuation Services
As per approved layout. Staircases shall be provided in basement/towards to exit in case of emergency/fire and/or any natural calamity.
19Other Miscellaneous Work
As per architects design.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

12 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2Beniwal Associates C/O Ravi BeniwalUPRERAAGT17023
3BLUECRUMBS INFRA PRIVATE LIMITEDUPRERAAGT16897
4DHEERENDER PANDEYUPRERAAGT19904
5GOLD BUCKS INFRATECH PRIVATE LIMITEDUPRERAAGT16636
6JOINT BRICKS PROPMARTUPRERAAGT11518
7KAVI KANTUPRERAAGT24223
8Kishankant SharmaUPRERAAGT21798
9PROPFIN SOLUTIONS PVT LTDUPRERAAGT14948
10RAJAT ROHATGIUPRERAAGT21456
11REAL BRICKS INFRATECHUPRERAAGT13418
12REDMAPLE BUILDIKO PRIVATE LIMITEDUPRERAAGT14395
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 26 Oct 2028.

Sanctioned by Greater Noida Authority · 21,888 sqm of land · an approved plan of 4 blocks and 532 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/(BP)3475/94727 Oct 202326 Oct 20282 Nov 203315 Nov 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH-09, Sector-121887.96Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 26868
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · PROP/BRS-02/2010/1512
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New29 Nov 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New30 Oct 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New30 Oct 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New30 Oct 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New1 Nov 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New1 Nov 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New1 Nov 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New29 Nov 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New29 Nov 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New29 Nov 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Nov 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Nov 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New2 Dec 2023 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New29 Nov 2023 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q3 to 2026-Q1.

QuarterConstructionCertificates
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q254.66%CA ↗ · Arch ↗ · Eng ↗
2025-Q365%CA ↗ · Arch ↗ · Eng ↗
2025-Q474.66%CA ↗ · Arch ↗ · Eng ↗
2026-Q185.86%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameStellar Spring Projects Private Limited
RolePromoter · current
RERA IDUPRERAPRM8082
PANAAOCS2530C
CIN / TANU70102DL2010PTC202540
Name of chairmanMr. Ravi Mohan Sethi
Registered addressRegistered Office - B-29, Sheikh Sarai, Phase -1, New Delhi-110017 Corporate Office - C 56/9, Sector 62, Noida, U.P.-201309
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
STELLAR SPPL STELLAR ONE PH II COLL A/CBankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
STELLAR SPPL STELLAR ONE PH II SEP A/CBankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
STELLAR SPPL STELLAR ONE PH II TRAN A/C.BankHDFC BANK LTD.BranchSECTOR-62, NOIDABranch addressSTELLAR IT PARK, C-25, SECTOR-62, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about STELLAR ONE PHASE II

Is STELLAR ONE PHASE II RERA registered?

Yes. STELLAR ONE PHASE II is registered with UPRERA under registration number UPRERAPRJ923780, registered on 30 Dec 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for STELLAR ONE PHASE II?

The completion date filed with UPRERA is 15 Nov 2028. No completion certificate is on record yet.

Who is the builder of STELLAR ONE PHASE II?

Stellar Spring Projects Private Limited is the promoter entity that filed STELLAR ONE PHASE II with UPRERA (promoter RERA ID UPRERAPRM8082). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does STELLAR ONE PHASE II have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is STELLAR ONE PHASE II located?

STELLAR ONE PHASE II is registered in SECTOR-01, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in STELLAR ONE PHASE II?

The unit plan filed with UPRERA lists 3 BHK, 4 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in STELLAR ONE PHASE II?

The approved unit plan filed with UPRERA runs from 70 to 145 m² of carpet area (about 755 to 1,559 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in STELLAR ONE PHASE II?

The approved unit plan describes 4 blocks and 532 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is STELLAR ONE PHASE II?

About 98 units per acre: 532 planned units across 5.41 acres (21,888 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.