SUPERTECH CAPETOWN (PHASE-V) is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ17551). RERA status: NCLT (since 13 Oct 2023). Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: NCLT.| RERA ID | UPRERAPRJ17551 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | NCLT |
| Proposed start | 1 Oct 2018 |
| Project duration | 78 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 19 Sept 2018 |
| Promised completion | 30 Sept 2024 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹58,000 |
| NCLT order date | 13 Oct 2023 |
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 2 | 51 |
| 3 BHK | 388 | 75–85 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 2014/III-227/757 | 30 Sept 2014 | 30 Sept 2019 | 30 Sept 2024 |
| Khasra | Area | Type |
|---|---|---|
| GH-01 A | 209271.47 | Plot |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | Arch · Eng | view ↗ |
Other projects registered in Gautam Budh Nagar.
Yes. SUPERTECH CAPETOWN (PHASE-V) is registered with UPRERA under registration number UPRERAPRJ17551, registered on 19 Sept 2018. Estanzo reproduces that filing; it does not verify the work behind it.
SUPERTECH CAPETOWN (PHASE-V) is 22 months past the completion date filed with UPRERA (30 Sept 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
SUPERTECH CAPETOWN (PHASE-V) is registered in Gautam Budh Nagar, as filed with UPRERA.