TOWER 4 is a RERA-registered commercial project by Wegmans Industries Pvt Ltd in Gautam Budh Nagar (RERA ID UPRERAPRJ563533). Registered with a completion deadline of 15 Dec 2030.
RERA status as reported: Registered.Construction progress
Construction stayed at 0% across 4 consecutive filed quarters (Jul–Sep 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ563533 |
| Project category | Commercial |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Greater Noida Authority |
| Proposed start | 1 May 2023 |
| Project duration | 92 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | F-7, First Floor, East of Kailash, New Delhi- 110065 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
PLG/BP SM-28-Oct-2021 12523
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 18 Apr 2023 |
| Original completion | 15 Dec 2030 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹69,000 |
| Sanctioning authority | Greater Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- SHOP4 57%
- OTHER3 43%
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 4 | 727-1,387 |
| OTHER | 3 | 506-581 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| TOWER 4 · SHOP, OTHER | 5 | 7 | 506-1,387 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Total Plot area= 40554 Sq. Mtr.
Current Project Plot area= 5826 Sq. Mtr.
Plot No.- 03, Sector Knowledge Park-3, Greater Noida UP- Allotted by Greater Noida Industrial Development Authority. |
| 2 | Boundary Wall 2.1 meter high boundary wall with 450 mm high brick and plaster wall. |
| 3 | Road Work All roads in the complex will be in combination with concrete pavers. Roads will be laid over 225 mm water-bound macadam. |
| 4 | Footpaths All footpaths in the complex will be a combination of concrete pavers of different colors, shape and thickness of 65 mm and 80 mm laid over 150 mm water bound macadam surface. |
| 5 | Water Supply Including Drinking Water Facilities Potable water supply from GNIDA shall be collected in underground collection tank and pumped to overhead water tank (2 numbers) located at the top floor terrace of total capacity of 20KL. |
| 6 | Sewer System The sewage will be collected through a soil pipeline arrangement, bends and inspection chambers leading to the sewage water treatment plant (STP) of the project, from where the sewage will be used for irrigation and flushing purpose. |
| 7 | Drain Rain water will be collected in drains having a minimum width of 150 mm connected to the underground cement concrete pipeline. For discharge, water will be collected in man holes to be constructed in the periphery of complex and these man holes shall be finally connected with drain of Greater Noida Authority. |
| 8 | Parks Not Applicable |
| 9 | Tree Planting The trees will be planted at all suitable locations of the project and along the boundary walls. The tree selection, flora and vegetation shall be as per the climatic conditions. Trees will be planted in a manner to ensure that there is no hindrance in the services/ usage in the project. |
| 10 | Design For Electric Supply Including Street Lighting Electric supply provided through 11/0.415 KV transformers and by DG set supply for backup. External street lighting shall be through solar power with alternate supply through grid. |
| 11 | Community Buildings Not Applicable |
| 12 | Treatment and Disposal System of Sewage and Sullage water Sewage shall be treated in Sewage Treatment Plant (STP) and thereafter treated water to be used for flushing and irrigation. |
| 13 | Solid Waste Management And Disposal System Solid waste to be collected and stored in garbage room. Recyclable shall be processed in the compost machine to make compost. Non recyclable water shall be disposed of through approved agents of Greater Noida Authority. |
| 14 | Water Conservation System Rain water harvesting pit shall be provided for ground water recharging and overflow to be discharged in the municipal drains. Treated sewage shall be used for irrigation and flushing. |
| 15 | Energy Management System Including Use of Renewable Energy Solar panel shall be provided on terrace for renewable energy. Single point metering will be therefore energy purchased from the grid/ power supply company. |
| 16 | Fire Protection And Fire Safety System Fire fighting system shall be provided for building as per the prevailing requirements of National Building Code. Sprinkler shall be provided in all common areas, basement and inside the individual apartments. Smoke dtectors, fire doors shall be provided in common areas. Water supply to sprinklers and hydrants shall be from fire pumps located in the basement. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Not Applicable |
| 18 | Emergency Evacuation Services Fire staircases shall be provided as per the approved fire drawing for evacuation to open areas. |
| 19 | Other Miscellaneous Work Not Applicable |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 14 Jan 2028.
Sanctioned by Greater Noida Authority · 5,826 sqm of land · an approved plan of 1 block and 7 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| PLG/BP SM-28-Oct-2021 12523 | 15 Jan 2023 | 14 Jan 2028 | 14 Jan 2031 | 15 Dec 2030 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
15 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 03, Sector Knowledge Park-III, Greater Noida | 40554 | Plot |
| Lease deed · 887 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 2 Mar 2023 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 2 Mar 2023 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 2 Mar 2023 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 2 Mar 2023 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 2 Mar 2023 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 2 Mar 2023 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 2 Mar 2023 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 2 Mar 2023 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 2 Mar 2023 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 2 Mar 2023 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 2 Mar 2023 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 2 Mar 2023 ↗ |
Quarterly progress reports
13 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
13 quarterly progress reports are on file with UPRERA, covering 2023-Q1 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Wegmans Industries Pvt Ltd |
| Role | Promoter · current |
| RERA ID | UPRERAPRM12469 |
| PAN | AAACW0175F |
| CIN / TAN | U25206DL1992PTC047288 |
| Name of chairman | Surendra Kumar Gupta |
| Registered address | F-7, First Floor, East of Kailash, New Delhi- 110065 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | WEGMANS INDUSTRIES PVT LTD- COLLECTION ACCOUNT FOR TOWER-4BankHDFC BankBranchGaur City-1, Greater Noida West BranchBranch addressShop No- 4-9, Gaur City-1, AIG Park Greater Noida West, Uttar Pradesh- 201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | WEGMANS INDUSTRIES PVT LTD- SEPARATE BANK ACCOUNT FOR TOWER-4BankHDFC BankBranchGaur City-1, Greater Noida West BranchBranch addressShop Np. 4-9, Gaur City-1, AIG Park Greater Noida West, Uttar Pradesh- 201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | WEGMANS INDUSTRIES PVT LTD- RERA TRANSACTION ACCOUNT FOR TOWER-4BankHDFC BankBranchGaur City-1, Greater Noida West BranchBranch addressShop No. 4-9, Gaur City-1, AIG Park Greater Noida West, Uttar Pradesh- 201009Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0005212 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about TOWER 4
Is TOWER 4 RERA registered?
Yes. TOWER 4 is registered with UPRERA under registration number UPRERAPRJ563533, registered on 18 Apr 2023. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for TOWER 4?
The completion date filed with UPRERA is 15 Dec 2030. No completion certificate is on record yet.
Who is the builder of TOWER 4?
Wegmans Industries Pvt Ltd is the promoter entity that filed TOWER 4 with UPRERA (promoter RERA ID UPRERAPRM12469). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does TOWER 4 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is TOWER 4 located?
TOWER 4 is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in TOWER 4?
The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in TOWER 4?
The approved unit plan filed with UPRERA runs from 506 to 1,387 m² of carpet area (about 5,445 to 14,929 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in TOWER 4?
The approved unit plan describes 1 block and 7 units of which 3 are homes and 4 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is TOWER 4?
About 5 units per acre: 7 planned units across 1.44 acres (5,826 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗