Umesh Park Phase-1

UPRERARegistered

Umesh Park Phase-1 is a RERA-registered residential project by Modi Industries Limited in Sikri Khurd, Ghaziabad (RERA ID UPRERAPRJ821313). Registered with a completion deadline of 23 May 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
0%Q3'25
82%Q4'25
32%Q1'26
38%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ821313
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Jan 2024
Project duration53 months
AddressKhasra No. 375 & 376, Village- Sikri Khurd, Main road, Umesh Park, Modinagar, , Ghaziabad- 201204, Sikri Khurd, Modinagar, Ghaziabad
TehsilModinagar
Applicant typeCompany
Applicant addressKhasra No. 375 and 376, Village Sikri Khurd Main Road, Umesh Park, Modinagar, Ghaziabad- 201204
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/04755/GDA/BP/21-22/0901/11042023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Feb 2024
Original completion23 May 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹43,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors114 · 2 · 10 (units from plan)
  • 2 BHK80 70%
  • 3 BHK34 30%
ConfigurationUnitsCarpet area
3 BHK3487-95
2 BHK8061-64
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · 3 BHK93487-95
2 · 2 BHK108061-64
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Kuldeep Verma
License CA/2000/25588
Koncept Consulting, GF-44, Omaxe Square, Jasola, New Delhi- 110025
Engineer
Er. Mohd. Shahfaiz
B-19, Basement, Dharam Palace, Opposite G.I.C., Near Gurudwara Road, Meerut (U.P) 250002
Contractor
Mr. Navin Tyagi
906, A.R Reflection, Raj nagar Extn. Ghaziabad (U.P)
Sr.Development work declared to RERA
1Demarcation of Plots
Khasra No. 375, 376, Village Sikri Khurd, main Road, Umesh Park, Modinagar, Ghaziabad, U.P. Total Plot Area = 7610.86 square meters.
2Boundary Wall
2.1 m high boundary wall with 1.8m high brick work and 0.60m highmild steel grill between two R.C.C. columns approx. 4.5m center to center. The boundary wall shall be earthquake resistant.
3Road Work
All roads in the complex will be in M25 grade concrete. Roads will be laid over 225 mm water bound macadam.
4Footpaths
All footpaths in the complex will in combination of concrete pavers of difference colors, shape and thickness of 60mm and 90 mm laid over 150 mm water bound macadam surface.
5Water Supply Including Drinking Water Facilities
Potable water supply from GDA shall be collected in underground collection tank and pumped to overhead water tank located at the terrace. The supply of water to individual flats shall be from the said overhead water tanks. Underground and overhead water tank with automatic pumps for 24 hours water supply.
6Sewer System
The sewage will be collected through a soil pipeline arrangement, bends and inspection chambers leading to the sewage water treatment plan (STP) of the project, from where the sewage will be used for irrigation and flushing purpose.
7Drain
Rain water shall be collected in drains having a minimum width of 150 mm connected to the underground cement concrete pipeline. For discharge, water will be collected in manholes to be constructed in periphery of complex, and these manholes shall be finally connected with drain of GDA.
8Parks
Lush green landscaped internal park will be provided and maintained. The landscaped parks will have jogging tracks, Pavilion, children play area and sitting area. The total area in the project will be 1143 sqm. (15 percent of the total plot area)
9Tree Planting
One tree for every 80 sqm of land needs to be planted within construction sites for both residential buildings, ensuring 10 percent green cover for every plot. The trees will be planted at all suitable locations of the project and along the boundary walls. The tree selection, flora and vegetation shall be as per the climatic conditions. Trees will be planted in a manner to ensure that there is no hindrance in the services/ usage in the project.
10Design For Electric Supply Including Street Lighting
Electric supply provided through 33/0.415 KV transformers and by DG set supply for backup. External street lighting shall be through solar power with alternate supply through grid.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
Sewage shall be treated in sewage Treatment plan (STP) and thereafter treated water to be used for flushing and irrigation
13Solid Waste Management And Disposal System
Solid waster to be collected from individual flats and stored in garbage room in the basement. Recyclable shall be processed in the compost machine to make compost. Non recyclable waste shall be disposed of through approved agents of GDA.
14Water Conservation System
Rain water harvesting pits shall be provided for ground water recharging and overflow to be discharges in the municipal drains. Treated sewage shall be used for irrigation and flushing.
15Energy Management System Including Use of Renewable Energy
The main power supply will be through HT power connection, stepped down by transformer and then distributed. DG backup of suitable rating will be provided. The campus lighting will be a combination of solar lights and grid supplied power. The light fittings will be power saving LED fittings.
16Fire Protection And Fire Safety System
Fire fighting system will be provided for all buildings as per the prevailing requirement of National Building Code. Sprinkler shall be provided in all common areas, basement and inside the individual apartments. Smoke detecters, fire doors shall be provided in common areas. Water supply to sprinklers and hydrants shall be from fire pumps located in the basement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Fire staircases shall be provided as per the approved fire drawing for evacuation to open areas.
19Other Miscellaneous Work
Not applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 28 May 2028.

Sanctioned by Ghaziabad Development Authority · 7,611 sqm of land · an approved plan of 2 blocks and 114 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/04755/GDA/BP/21-22/0901/1104202329 May 202328 May 202828 May 203123 May 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
375, 3767611Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1424-1429
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Sale deed · 20273
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 357/359
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New16 Nov 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New16 Nov 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New16 Nov 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New16 Nov 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New10 Jan 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Jan 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New10 Jan 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Dec 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New10 Jan 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Jan 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New16 Nov 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New16 Nov 2023 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New18 Dec 2023 ↗

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q2.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q382%CA ↗ · Arch ↗ · Eng ↗
2025-Q432%CA ↗ · Arch ↗ · Eng ↗
2026-Q138%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameModi Industries Limited
RolePromoter · current
RERA IDUPRERAPRM236423
PANAAACM2063Q
CIN / TANMRTM01008A
Name of chairmanUmesh Kumar Modi
Registered addressKhasra No. 375 and 376, Village Sikri Khurd Main Road, Umesh Park, Modinagar, Ghaziabad- 201204
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Modi Industries Limited- Collection Account For Umesh Park Phase- 1BankAxis BankBranchModinagarBranch addressGround Floor and First Floor, Khasra No. 701, Building No. 79, Srinagar Colony, G.T. Road, modinagar, Ghaziabad- 201204Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0002206Branch emailmodinagar.branchhead@axisbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Modi Industries Limited- Separate Bank Account For Umesh Park Phase- 1BankAxis BankBranchModinagarBranch addressGround and First Floor, Khasra No. 701, Building No. 79, Srinagar Colony, G.T. Road, Modinagar, Ghaziabad, 201204Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0002206
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Modi industries Limited- RERA Transaction Account For Umesh Park Phase- 1BankAxis BankBranchModinagarBranch addressGround and First Floor, Khasra No. 701, Building no. 79, Srinagar Colony, G.T. Road, Modinagar, Ghaziabad, 201204Branch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0002206
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
19 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Umesh Park Phase-1

Is Umesh Park Phase-1 RERA registered?

Yes. Umesh Park Phase-1 is registered with UPRERA under registration number UPRERAPRJ821313, registered on 24 Feb 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Umesh Park Phase-1?

The completion date filed with UPRERA is 23 May 2028. No completion certificate is on record yet.

Who is the builder of Umesh Park Phase-1?

Modi Industries Limited is the promoter entity that filed Umesh Park Phase-1 with UPRERA (promoter RERA ID UPRERAPRM236423). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Umesh Park Phase-1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Umesh Park Phase-1 located?

Umesh Park Phase-1 is registered in Sikri Khurd, Ghaziabad, as filed with UPRERA.

What configurations are available in Umesh Park Phase-1?

The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Umesh Park Phase-1?

The approved unit plan filed with UPRERA runs from 61 to 95 m² of carpet area (about 655 to 1,025 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Umesh Park Phase-1?

The approved unit plan describes 2 blocks and 114 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Umesh Park Phase-1?

About 61 units per acre: 114 planned units across 1.88 acres (7,611 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗