Uninav Bliss is a RERA-registered real-estate project in Ghaziabad (RERA ID UPRERAPRJ102648). Its RERA-registered completion deadline (30 Jun 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ102648 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Feb 2020 |
| Project duration | 41 |
| Address | Ghaziabad, Ghaziabad |
| RERA registered | 13 Jul 2020 |
| Promised completion | 30 Jun 2023 |
| Revised completion | — none granted |
| Completion certificate filed | 12 Jan 2023 |
| Registration fee | ₹82,500 |
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 4 | 226–229 |
| SHOP | 3 | 125 |
| 4 BHK | 40 | 152 |
| 3 BHK | 170 | 68–104 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| MAP20190510103648843 | 3 Aug 2019 | 2 Aug 2024 | 30 Jun 2023 |
| Khasra | Area | Type |
|---|---|---|
| 1085 | 6823 | Khasra |
| 1089 | 8287.34 | Khasra |
| 1091 | 189 | Khasra |
| 1091/1 | 117.50 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
Other projects registered in Ghaziabad.
Yes. Uninav Bliss is registered with UPRERA under registration number UPRERAPRJ102648, registered on 13 Jul 2020. Estanzo reproduces that filing; it does not verify the work behind it.
UPRERA still lists Uninav Bliss as Registered, so it is not shown as completed here. A completion certificate dated 12 Jan 2023 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Uninav Bliss is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗