Timeline Bar

Registered4 Oct 2017
Promised13 Mar 2018
Completed18 Jun 2019

Timeline

Promised completion13 Mar 2018
Revised completion13 Mar 2018
Actual completion18 Jun 2019
Possession delay15 mo delay

Registration & Cost Details

Registration fee (in ₹)₹17,000
Project cost (in ₹ Lakhs)₹1,007 Lakhs
Project duration24 months
Project categoryResidential
Locality
Original start date14 Mar 2016
Proposed start date14 Mar 2016

Inventory

Total units48
Unit TypeUnitsCarpet Area (sqm)
2 BHK4852.36

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9628372038
Emailgdagorakhpur@gmail.com
Coordinator9628372026
AddressTaramandal, Deoria Byepass Road, Gorakhpur

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
VASUPH3/1401201614 Jan 201613 Jan 202113 Mar 201813 Jan 2021

Land Parcels

Khasra No.AreaPlot Type
2315
2320.32
2370.62
2380.06
2390.25
2510.60
2540.42
2560.37
2570.40
2580.30
2590.30
2600.40
2610.15
2620.61
2630.03
2650.18
2660.65
2670.54
2740.44
2751.07
1M3236Khasra

Approved Unit Plan

Unit plan rows on file12
Total flats (sum of rows)48
Blocks1, 2, 3
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
569/VI.BHU.A.A/GORAKHPUR28 May 1987

Frequently Asked Questions

What is the RERA registration number of Vasundhara Enclave - III?

The RERA registration number of Vasundhara Enclave - III is UPRERAPRJ8653, as recorded on the UP-RERA portal.

What is the RERA status of Vasundhara Enclave - III?

As reported by UP-RERA, the status of Vasundhara Enclave - III is "Registered".

Where is Vasundhara Enclave - III located?

As reported to UP-RERA, Vasundhara Enclave - III is located at Gorakhpur, Gorakhpur, Uttar Pradesh.

Is Vasundhara Enclave - III completed?

As reported to UP-RERA, Vasundhara Enclave - III was completed on 18 Jun 2019.

Is Vasundhara Enclave - III delayed?

Measured against the latest completion date reported to UP-RERA, Vasundhara Enclave - III is 15 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026