VEDIC GRAM

UPRERARegistered

VEDIC GRAM is a RERA-registered residential project by ANUSHTHAN BUILDERS AND DEVELOPERS PVT. LTD in HULAS KHEDA, Lucknow (RERA ID UPRERAPRJ437862). Registered with a completion deadline of 9 Oct 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0%Q4'25
47%Q1'26
94.3%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ437862
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAny Other Competent Authority
Proposed start1 Dec 2025
Project duration35 months
AddressVEDIC GRAM KHASRA -506,507,497,505 NEAR KALESWARI DEVI TEMPLE, HULAS KHEDA, Mohanlalganj, Lucknow
TehsilMohanlalganj
Applicant typeCompany
Applicant addressPLOT NO-03, KH NO-576, AURANGABAD JAAGIR, LUCKNOW- 226001 UTTAR PRADESH
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    639/MAP/JILAPANCHAYAT/2025-2026

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered6 Jan 2026
Original completion9 Oct 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,22,000
Sanctioning authorityAny Other Competent Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
RISHI VERMA
License CA/2015/66738
SENANI VIHAR RAEBARELI ROAD LUCKNOW
Engineer
P K SINGH
LDA COLONY KANPUR ROAD LUCKNOW
Contractor
RISHABH SINGH
2/141 MANSAROVER YOJNA KANPUR ROAD LUCKNOW
Sr.Development work declared to RERA
1Demarcation of Plots
The plots available for sale are clearly demarcated on site ensuring transparency in boundary identification and layout . The land is under complete and legal possiession
2Boundary Wall
A 2.1 meter high cemented boundary wall is planned for constraction to ensure enhanced security and well defined para meters for the property.
3Road Work
the developement plan includes the construction, we are incorporating a dedicated green area in the center of the roads along every row.
4Footpaths
N/A
5Water Supply Including Drinking Water Facilities
To ensure areliable and efficient drinking water supply , we will construct an underground water tank (56.025KLD) , complemented by an underground pipline network.
6Sewer System
All sewage wateer will be directed to sewage treatment tank (STT) 50.4225 KLD developed on site any overflow from STT will be connected to the muncipal sweage system ensuring proper waste management.
7Drain
All drainage water will also be directed to the on site Sewage Treatment Tank (STT)50.4225KLD ensuring comprehensive waste and water managemnt within the project .
8Parks
We will develop a park featuring green landscape and multi- purpose spaces wuth various plants and is designed to offer a versitile recreational area for residents to enjoy.
9Tree Planting
We will plany evergreen trees and plants ranging from 1 meter to 4 meter in height along all roads to providing year round greenary.
10Design For Electric Supply Including Street Lighting
We will design and implement the lighting system according to the guidelines provided by the local electricity board.
11Community Buildings
N/A
12Treatment and Disposal System of Sewage and Sullage water
N/A
13Solid Waste Management And Disposal System
N/A
14Water Conservation System
N/A
15Energy Management System Including Use of Renewable Energy
We will install LED light fittings in external areas to ensure efficient and long lasting illumination.
16Fire Protection And Fire Safety System
N/A
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
N/A
19Other Miscellaneous Work
N/A
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 9 Oct 2028.

Sanctioned by Any Other Competent Authority · 23,381 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
639/MAP/JILAPANCHAYAT/2025-202610 Oct 20259 Oct 20288 Oct 20299 Oct 2028
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4974825Khasra
5075260Khasra
5055220Khasra
5069400Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 2018-2024
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 37804
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 29394
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 30129
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7481
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 27668
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18548
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New17 Dec 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New19 Nov 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New19 Nov 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New19 Nov 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New19 Nov 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New19 Nov 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New19 Nov 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New19 Nov 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New19 Nov 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New19 Nov 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New18 Dec 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New19 Nov 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New3 Jan 2026 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New19 Nov 2025 ↗

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q1.

QuarterConstructionCertificates
2025-Q30%CA ↗ · Arch ↗ · Eng ↗
2025-Q447%CA ↗ · Arch ↗ · Eng ↗
2026-Q194.3%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameANUSHTHAN BUILDERS AND DEVELOPERS PVT. LTD
RolePromoter · current
RERA IDUPRERAPRM316770
PANAAZCA9178P
CIN / TANLKNA19618E
Name of chairmanARUN PRATAP SINGH
Registered addressPLOT NO-03, KH NO-576, AURANGABAD JAAGIR, LUCKNOW- 226001 UTTAR PRADESH
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameSOLDIER INFRA DEVELOPERS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
Address4-B/237 VIRINDAVAN YOJNA, RAIBARELI ROAD, B R A University, Lucknow, Lucknow- 226025, Uttar Pradesh
RERA contact
Legal nameJAI PRAKASH SINGH
RoleCo-promoter
Applicant typeIndividual
AddressH. No. 13, Shiv Sagar Nagar, Near Bosco Convent Inter College, Shankar Puri Colony, Kamta, Chinhat, Lucknow, Uttar Pradesh,226028
RERA contact
Legal nameRUPESH KUMAR SINGH
RoleCo-promoter
Applicant typeIndividual
AddressMM 42 SEC-D1 LDA COLONY LUCKNOW
RERA contact
Legal nameSUDHANSHU SINGH
RoleCo-promoter
Applicant typeIndividual
AddressGOPAL KHEDA PURSENI LUCKNOW UP-227305
RERA contact

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
ANUSHTHAN BUILDERS AND DEVELOPERS PVT LTD COLLECTION AC FOR VEDIC GRAMBankICICI BANK LTDBranchNIRALA NAGAR LUCKNOWBranch addressICICI BANK LTD A-29 NIRALA NAGAR LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCICIC0001263Branch emailshatabdi.dhole@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
ANUSHTHAN BUILDERS AND DEVELOPERS PVT LTD SEPARATE AC FOR VEDIC GRAMBankICICI BANK LTDBranchNIRALA NAGAR LUCKNOWBranch addressICICI BANK LTD A-29 NIRALA NAGAR LUCKNOW-226020Branch districtLucknow, Uttar PradeshA/C no.IFSCICIC0001263
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
ANUSHTHAN BUILDERS AND DEVELOPERS PVT LTD RERA TRANSACTION AC FOR VEDIC GRAMBankICICI BANK LTDBranchNIRALA NAGAR LUCKNOWBranch addressICICI BANK LTD A-29 NIRALA NAGAR LUCKNOW -226020Branch districtLucknow, Uttar PradeshA/C no.IFSCICIC0001263
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about VEDIC GRAM

Is VEDIC GRAM RERA registered?

Yes. VEDIC GRAM is registered with UPRERA under registration number UPRERAPRJ437862, registered on 6 Jan 2026. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for VEDIC GRAM?

The completion date filed with UPRERA is 9 Oct 2028. No completion certificate is on record yet.

Who is the builder of VEDIC GRAM?

ANUSHTHAN BUILDERS AND DEVELOPERS PVT. LTD is the promoter entity that filed VEDIC GRAM with UPRERA (promoter RERA ID UPRERAPRM316770). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does VEDIC GRAM have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VEDIC GRAM located?

VEDIC GRAM is registered in HULAS KHEDA, Lucknow, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗