VILASAA

UPRERACompleted

VILASAA is a RERA-registered residential project by VAIKUNTAM BUILDCON PRIVATE LIMITED in Ghaziabad (RERA ID UPRERAPRJ700245). RERA status: Completed on 6 Jan 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Completed.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
90.61%Q3'25
100%Q4'25
100%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ700245
Project categoryResidential
Registration typeNew
RERA statusCompleted
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start26 Jun 2021
Project duration68 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressB-128,First Floor,Sector-2,Noida,Gautam Buddha Nagar, Noida, Uttar Pradesh, India,201301
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. valid to

    Permit revalidated

    PLOTTED RESI DEVELOPMENT/PLOTTED HOUSING/01127/GDA/LD/20-21/0970/03042021

  3. 2 building permits sanctioned

  4. Registered with RERA

  5. Completion certificate filed

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Completed.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Mar 2022
Original completion3 Feb 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary6 Jan 2026
Registration fee₹39,000
Sanctioning authorityGhaziabad Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
DUSHYANT KUMAR
License CA/2014/63100
D-201, BLUEMOON RESIDENCY, RAJ NAGAR EXTENSION
Engineer
AKHILESH SINGH
POCKET-8, PLOT NO. 245, SECTOR-23, ROHINI, NEW DELHI-110085
Contractor
KATYAYANI INFRA INDIA
C-70, FIRST FLOOR, SECTOR-8, NOIDA
Sr.Development work declared to RERA
1Demarcation of Plots
As per approved drawings, Demarcation of plots was done by Total Station Machine
2Boundary Wall
(i) RCC Cum brick wall having thickness of 230 mm. (ii) Height of the boundary wall will be 6 feet from 0-0 level.
3Road Work
Two 9 m Roads having length of 70 m each and one 7.5 m road having length of 75 m will be constructed. The road will be constructed in several steps- (i) 3 times backfilling of soil. (ii) After each step of soil feeling, compaction and curing will be done. (iii) 2 times GSB layering having thickness of 150 mm each one 6 m of width on 9 m road and 4.5 m of width on 7.5 m of road, then compaction and curing will be done. (iv) WBM Bituminous layer of thickness 150 mm.
4Footpaths
On the remaining 3 m compacted soil (1.5m on each side), we will lay interlocking tiles on the footpath.
5Water Supply Including Drinking Water Facilities
For every individual Villa, drinking water connection through 90 degree dia PVC line.
6Sewer System
Sewer System will be constructed in following steps- (i) Excavation as per level of sewer in approved drawings (ii) PCC. (iii) NP3 pipes having 300 degree dia of slope in ration of 1/200 will be used in the sewer system. (iv) Backfilling of soil and plaster. (v) Waste water will discharge into sewer pipes, then sewer water will discharge into STP.
7Drain
(i) Excavation as per level of draining line in approved drawings. (ii) PCC (iii) NP3 pipes having 300 degree dia of slope in ratio of 1/200 will be used in the drainage system. (iv) Backfilling of soil and plaster (v) Drainage water will be discharged into the RWH pit by NP3 pipes.
8Parks
(i) 10 percentage of the total plot area which is 678.15 sq.m (ii) The level of the green area will be 75 mm down from road level.
9Tree Planting
(i) 35 trees will be plated in the green area. (ii) Different types of trees and flowers will be planted.
10Design For Electric Supply Including Street Lighting
(i) 25 KVA transformer will be placed. (ii) 3 m distance between two street lights. (iii) 9 feet height 0-0 level.
11Community Buildings
(i) Sector shopping provided having an area of 181.09 sq.m. (ii) Convenient shops provided having an area of 157.07 sq.m. (iii) Club house having an area of 73 sq.m.
12Treatment and Disposal System of Sewage and Sullage water
STP of 70 KLD will be provided having an area of 70 sq.m.
13Solid Waste Management And Disposal System
Garbage area provided having an area of 33.19 sq. m.
14Water Conservation System
RWH (Rain water harvesting) having an area of 10 sq.m. will be provided (i) 250mm 230mm dia bore filled with pea gravels. (ii) 160 degree PVC slotted pipe. (iii) 50-150 mm size boulders (iv) Mesh (v) Gravel 5-10 mm (vi) Coarse sand (1.5 to 2 mm) (vii) Geotextile (160 GSM) (viii) 600 x 600 x 100 mm RCC Deflector or stone slab
15Energy Management System Including Use of Renewable Energy
(i) Electrical panel room and 100 percent power backup. (ii) Two 125 KVA D.G will be provided.
16Fire Protection And Fire Safety System
(i) Ring line having 150mm thickness. (ii) Extinguisher in each villa (iii) Fire tank of RCC. (Capacity as per drawings)
17Social Infrastructure And Other Public Amenities Including Public Health Services
(i) Gym (ii) Swimming pool (iii) Banquet hall
18Emergency Evacuation Services
(i) Fire Alarm system in panel room. (ii) NT smokers in all villas
19Other Miscellaneous Work
As per requirement
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 4 Feb 2027. 1 of them carries a revalidation, valid to 3 Mar 2027.

Sanctioned by Ghaziabad Development Authority · 6,778 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
Plotted Resi development/ Plotted Housing/ 10127/ GDA/ LD/ 20-21/ 0970/ 030420215 Feb 20224 Feb 20274 Feb 20273 Feb 2027—
PLOTTED RESI DEVELOPMENT/PLOTTED HOUSING/01127/GDA/LD/20-21/0970/030420215 Feb 20223 Feb 202728 Apr 20273 Feb 20275 Feb 2022
valid to 3 Mar 2027
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

26 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
13135600Khasra
13123470Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Water supply plan
How the project proposed to supply water, as filed at registration.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New10 Mar 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New10 Mar 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New10 Mar 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New10 Mar 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New10 Mar 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Mar 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Feb 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Feb 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New10 Mar 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Mar 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New10 Mar 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New10 Mar 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New10 Mar 2022 ↗

Quarterly progress reports

20 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

20 quarterly progress reports are on file with UPRERA, covering 2021-Q1 to 2025-Q4.

QuarterConstructionCertificates
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q290.61%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameVAIKUNTAM BUILDCON PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM164745
PANAAHCV6701B
CIN / TANU45309UP2020PTC136370
Name of chairmanVISHAL TYAGI
Registered addressB-128,First Floor,Sector-2,Noida,Gautam Buddha Nagar, Noida, Uttar Pradesh, India,201301
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Vaikuntam Buildcon Private Limited- Collection Account for VILASAABankAxis BankBranchVVIP Mall Rajnagar Extension Ghaziabad.Branch addressVVIP Mall Rajnagar Extension GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0004428
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Vaikuntam Buildcon Private limited- Separate Bank Account for VilasaaBankAxis BankBranchVVIP Mall Rajnagar Extension GhaziabadBranch addressVVIP Mall Rajnagar Extension GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0004428
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Vaikunatam Buildcon Private Limited- Rera Transaction Account for VilasaaBankAxis BankBranchVVIP Mall Rajnagar Extension GhaziabadBranch addressVVIP Mall Rajnagar Extension GhaziabadBranch districtGhaziabad, Uttar PradeshA/C no.IFSCUTIB0004428
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about VILASAA

Is VILASAA RERA registered?

Yes. VILASAA is registered with UPRERA under registration number UPRERAPRJ700245, registered on 30 Mar 2022. Estanzo reproduces that filing; it does not verify the work behind it.

Has VILASAA been completed?

UPRERA lists VILASAA as completed, with a completion certificate dated 6 Jan 2026, against a filed deadline of 3 Feb 2027.

Who is the builder of VILASAA?

VAIKUNTAM BUILDCON PRIVATE LIMITED is the promoter entity that filed VILASAA with UPRERA (promoter RERA ID UPRERAPRM164745). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does VILASAA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VILASAA located?

VILASAA is registered in Ghaziabad, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗