WMCC-2B is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ5489). Its RERA-registered completion deadline (31 Jul 2019) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ5489 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 26 Dec 2012 |
| Original start | 26 Dec 2012 |
| Project duration | 80 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 31 Jul 2017 |
| Promised completion | 31 Jul 2019 |
| Revised completion | — none granted |
| Completion certificate filed | 5 Mar 2021 |
| Registration fee | ₹52,500 |
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 38 | 34–791 |
| 4 BHK | 86 | 173–177 |
| 3 BHK | 226 | 119–131 |
| 2 BHK | 112 | 87 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| NOIDA/CAP/2014/IV-1372/751 | 10 Sept 2014 | 9 Sept 2019 | 31 Jul 2019 |
| NOIDA/CAP/2014/IV-1372/751 | 10 Sept 2014 | 9 Sept 2019 | 31 Jul 2019 |
| Khasra | Area | Type |
|---|---|---|
| CC-01 | 618952.75 | Plot |
Other projects registered in Gautam Budh Nagar.
Yes. WMCC-2B is registered with UPRERA under registration number UPRERAPRJ5489, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
UPRERA still lists WMCC-2B as Registered, so it is not shown as completed here. A completion certificate dated 5 Mar 2021 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
WMCC-2B is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗