WMCC-3E is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ3337). Its RERA-registered completion deadline (30 Jun 2020) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ3337 |
| Applicant type | Company |
| Project category | Commercial |
| Project type | other |
| RERA status | Registered |
| Proposed start | 7 Nov 2012 |
| Original start | 7 Nov 2012 |
| Project duration | 98 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 28 Jul 2017 |
| Promised completion | 30 Jun 2020 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹65,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| STUDIO | 825 | 36–47 |
| OTHER | 303 | 6–3,038 |
| SHOP | 39 | 173–312 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| NOIDA/CAP/IV-1371/583 | 7 Nov 2012 | 6 Nov 2017 | 30 Jun 2020 |
| Khasra | Area | Type |
|---|---|---|
| CC-01 | 618952.75 | Plot |
| Registry no. | Date | Type | Area |
|---|---|---|---|
| LD 66229801108-25 | 2 Sept 2011 | — | — |
| LD 66229801108-25 | 2 Sept 2011 | — | — |
| LD 66229801108-25 | 2 Sept 2011 | — | — |
Other projects registered in Gautam Budh Nagar.
Yes. WMCC-3E is registered with UPRERA under registration number UPRERAPRJ3337, registered on 28 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
WMCC-3E is 73 months past the completion date filed with UPRERA (30 Jun 2020), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
WMCC-3E is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗