448 E.W.S houses under PMAY at Bhopa road byepass crossingUPRERADelayed 48 mo
Home › Projects › Muzaffarnagar › 448 E.W.S houses under PMAY at Bhopa road byepass crossing

448 E.W.S houses under PMAY at Bhopa road byepass crossing

UPRERADelayed 48 moRegisteredConstruction 100% · 2022 Q4updated 4 Aug 2026

448 E.W.S houses under PMAY at Bhopa road byepass crossing is a RERA-registered real-estate project in Muzaffarnagar (RERA ID UPRERAPRJ142991). Its RERA-registered completion deadline (11 Aug 2022) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
48 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹25
Land area
not reported
Units (from plan)
448
Density (derived)
not reported
Towers
not reported
Config
1 BHK
Carpet
24–24
Registered
5 Jul 2019

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2022 Q4
100%Q1'21
100%Q2'21
100%Q3'21
100%Q4'21
100%Q1'22
100%Q2'22
100%Q3'22
100%Q4'22

Basic details

RERA IDUPRERAPRJ142991
Applicant typeCompetent authority
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start12 Aug 2019
Project duration42
AddressMuzaffarnagar, Muzaffarnagar

Registration & timeline

RERA registered5 Jul 2019
Promised completion11 Aug 2022
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹75,000

Inventory

derived from unit plan
Total units · towers · floors448 · 14 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK44824
Towers as filedTower A · Tower B · Tower C · Tower D · Tower E · Tower F · Tower G · Tower H · Tower I · Tower J · Tower K · Tower L · Tower M · Tower N
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
P.N.N-11011/70/2018-HFA-111-UD(E.FILE9050903)24 Oct 201823 Oct 202111 Aug 2022

Land & documents

1 filing
KhasraAreaType
211M, 212M, 220M, 587M, 59113940Khasra

Quarterly progress reports

12 filed reports
QuarterConstructionCertificatesSource
2020-Q1100%CA · Arch · Engview ↗
2020-Q2100%CA · Arch · Engview ↗
2020-Q3100%CA · Arch · Engview ↗
2020-Q4100%CA · Arch · Engview ↗
2021-Q1100%CA · Arch · Engview ↗
2021-Q2100%CA · Arch · Engview ↗
2021-Q3100%CA · Arch · Engview ↗
2021-Q4100%CA · Arch · Engview ↗
2022-Q1100%CA · Arch · Engview ↗
2022-Q2100%CA · Arch · Engview ↗
2022-Q3100%CA · Arch · Engview ↗
2022-Q4100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2022-Q4.

Nearby projects

Muzaffarnagar

Other projects registered in Muzaffarnagar.

224 E.W.S HOUSES UNDER PANDIT DEENDAYAL UPADHAYAY NAGAR MEERUT ROAD MUZAFFARNAGAR
UPRERA ▲ 57 mo
256 E.W.S houses under PMAY at Begrajpur
UPRERA ▲ 48 mo
256 E.W.S houses under PMAY at Budhana
UPRERA ▲ 48 mo
DWARIKA BALAJI LIG/EWS
UPRERA no delay on record
DWARIKA BALAJI PHASE- 4
UPRERA no delay on record
Dwarika Balaji Phase-5
UPRERA ▲ 4 mo

Common questions about 448 E.W.S houses under PMAY at Bhopa road byepass crossing

Is 448 E.W.S houses under PMAY at Bhopa road byepass crossing RERA registered?

Yes. 448 E.W.S houses under PMAY at Bhopa road byepass crossing is registered with UPRERA under registration number UPRERAPRJ142991, registered on 5 Jul 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Is 448 E.W.S houses under PMAY at Bhopa road byepass crossing delayed?

448 E.W.S houses under PMAY at Bhopa road byepass crossing is 48 months past the completion date filed with UPRERA (11 Aug 2022), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is 448 E.W.S houses under PMAY at Bhopa road byepass crossing located?

448 E.W.S houses under PMAY at Bhopa road byepass crossing is registered in Muzaffarnagar, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 48 mo
QPR filingNo default reported
DistrictMuzaffarnagar
Last updated4 Aug 2026

Location

AddressMuzaffarnagar
View on map ↗

RERA buyer helpline

Coordinator9837047333
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=bDu+qW6XJzQ=&hfFlag=h+WiFBBo3NcfO/CyglQDDg==&NPJ6RAme=bzevXTrq4rE5uBHZJeJKmrFXGWT8ct3PuvgvgBY4gPJYbef8fzPseUqA5thNbcFk+BRFfe4zEwQippQd0VbHvw==&PaURJEMAN4=ZL9MNERkNdYK2gCTeye7dw==&IRSAHEB=D6PY3lyims8=)