ACE ACREVILLEUPRERADelayed 4 mo
Home › Projects › Gautam Budh Nagar › ACE ACREVILLE

ACE ACREVILLE

UPRERADelayed 4 moRegisteredConstruction 57% · 2025 Q3updated 4 Aug 2026

ACE ACREVILLE is a RERA-registered real-estate project in SECTOR- 22A, Gautam Budh Nagar (RERA ID UPRERAPRJ248777). Its RERA-registered completion deadline (31 Mar 2026) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
4 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹595
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
7 Mar 2025

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2025 Q3
—Q3'24
—Q4'24
—Q1'25
37%Q2'25
57%Q3'25

Basic details

RERA IDUPRERAPRJ248777
Applicant typeCompany
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start20 Nov 2024
Project duration17
AddressTS-01, Sector-22A, Yamuna Expressway, SECTOR- 22A, Gautam Buddha Nagar, Gautam Budh Nagar

Registration & timeline

RERA registered7 Mar 2025
Promised completion31 Mar 2026
Revised completion— none granted
Completion certificate filed19 Feb 2026
Registration fee₹20,29,500

Permits & extensions

2 permits
Permit no.DateValid uptoRevised end
YEA/PLANNING/699/20241 Oct 202430 Sept 202931 Mar 2026
YEA/PLANNING/699/20241 Oct 202430 Sept 202931 Mar 2026

Land & documents

1 filing
KhasraAreaType
TS-01, SECTOR-22A, YAMUNA EXPRESSWAY404860.60Plot

Quarterly progress reports

5 filed reports
QuarterConstructionCertificatesSource
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q237%CA · Arch · Engview ↗
2025-Q357%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3.

Nearby projects

Gautam Budh Nagar

Other projects registered in Gautam Budh Nagar.

"1st - A Park View" - Gaur Yamuna City
UPRERA ▲ 10 mo
"1st - B Park View" - Gaur Yamuna City
UPRERA ▲ 10 mo
14th Avenue (Group Housing) - Gaur City
UPRERA ▲ 46 mo
168Xaviers - Cambridge and Crystal
UPRERA ▲ 91 mo
168Xaviers - MARIOTT TOWER
UPRERA ▲ 88 mo
16th Parkview - Gaur Yamuna City
UPRERA ▲ 39 mo

Common questions about ACE ACREVILLE

Is ACE ACREVILLE RERA registered?

Yes. ACE ACREVILLE is registered with UPRERA under registration number UPRERAPRJ248777, registered on 7 Mar 2025. Estanzo reproduces that filing; it does not verify the work behind it.

Has ACE ACREVILLE been completed?

UPRERA still lists ACE ACREVILLE as Registered, so it is not shown as completed here. A completion certificate dated 19 Feb 2026 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Where is ACE ACREVILLE located?

ACE ACREVILLE is registered in SECTOR- 22A, Gautam Budh Nagar, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 4 mo
QPR filingNo default reported
DistrictGautam Budh Nagar
LocalitySECTOR- 22A
Last updated4 Aug 2026

Location

AddressTS-01, Sector-22A, Yamuna Expressway
View on map ↗

RERA buyer helpline

Coordinator9599680647
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=x2LL4vhz5k8=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=fBBL+1aYBzJO3Cyay39Qsg==&PaURJEMAN4=ZL9MNERkNdYUFKaRmvd3j4ysR8Wa1xbW&IRSAHEB=D6PY3lyims8=)