Timeline Bar

Registered2 Jul 2019
Promised15 Feb 2024
Today4 Aug 2026

Timeline

Promised completion15 Feb 2024
Revised completion15 Feb 2024
Actual completion
Possession delay30 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,60,500
Project cost (in ₹ Lakhs)₹46,123 Lakhs
Project duration63 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jun 2019

Inventory

Total units466
Unit TypeUnitsCarpet Area (sqm)
3 BHK18151.72–164.89
4 BHK318189.56
5 BHK89314–375.16
SHOP4125.13–217.28

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310012345
Emailrera.ivrpdpl@gmail.com
Coordinator9582006011
Address1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
CAP/2015/III-277/110215 Feb 201915 Feb 202415 Feb 202415 Feb 2029

Land Parcels

Khasra No.AreaPlot Type
GH-01, SECTOR 118, NOIDA31019Plot

Approved Unit Plan

Unit plan rows on file238
Total flats (sum of rows)466
Total shops41
BlocksCommercial 05, Commercial 06, N1, N2, N3, N4
Floor types3 BHK, 4 BHK, 5 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6)?

The RERA registration number of AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) is UPRERAPRJ888243, as recorded on the UP-RERA portal.

What is the RERA status of AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6)?

As reported by UP-RERA, the status of AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) is "Registered".

Where is AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) located?

As reported to UP-RERA, AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) be completed?

The latest completion date reported to UP-RERA for AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) is 15 Feb 2024.

Is AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) delayed?

Measured against the latest completion date reported to UP-RERA, AMBROSIA PHASE 04 (TOWER N1,N2,N3,N4,COMMERCIAL 5 & 6) is 30 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026