Estanzo

Timeline Bar

Registered14 Aug 2017
Promised30 Dec 2018
Revised29 Dec 2019
Today4 Aug 2026

Timeline

Promised completion30 Dec 2018
Revised completion29 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹84,500
Project cost (in ₹ Lakhs)₹9,354 Lakhs
Project duration71 months
Project categoryResidential
Locality
Original start date22 Feb 2014
Proposed start date22 Feb 2014

Inventory

Total units570
Unit TypeUnitsCarpet Area (sqm)
2 BHK57057.29–70.05

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310012345
Emailrera.ivrpdpl@gmail.com
Coordinator8588033336
Address1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
III-227/710

Revalidated: WILL BE APPLIED (6 Dec 2023)

15 Feb 20196 Dec 2018

Revalidated upto: 6 Dec 2023

29 Dec 20196 Dec 2023
III-227/710

Revalidated: III-227/710 (6 Dec 2013)

15 Feb 20196 Dec 2018

Revalidated upto: 6 Dec 2023

29 Dec 20196 Dec 2023
CAP/III-277/1102

Revalidated: CAP/III-277/1102 (15 Feb 2019)

15 Feb 201914 Feb 2024

Revalidated upto: 1 Jan 1900

29 Dec 201914 Feb 2029

Land Parcels

Khasra No.AreaPlot Type
GH-01SECTOR 118
GH 01142967Plot

Approved Unit Plan

Unit plan rows on file104
Total flats (sum of rows)570
BlocksA3, A4, B1, B2
Floor types2 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
469624 Oct 2013

Frequently Asked Questions

What is the RERA registration number of THE ROMANO (PHASE-I)?

The RERA registration number of THE ROMANO (PHASE-I) is UPRERAPRJ5748, as recorded on the UP-RERA portal.

What is the RERA status of THE ROMANO (PHASE-I)?

As reported by UP-RERA, the status of THE ROMANO (PHASE-I) is "Registered".

Where is THE ROMANO (PHASE-I) located?

As reported to UP-RERA, THE ROMANO (PHASE-I) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will THE ROMANO (PHASE-I) be completed?

The latest completion date reported to UP-RERA for THE ROMANO (PHASE-I) is 29 Dec 2019.

Is THE ROMANO (PHASE-I) delayed?

Measured against the latest completion date reported to UP-RERA, THE ROMANO (PHASE-I) is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026