Estanzo

Timeline Bar

Registered13 Aug 2017
Promised30 Dec 2019
Today4 Aug 2026

Timeline

Promised completion30 Dec 2019
Revised completion30 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,03,500
Project cost (in ₹ Lakhs)₹28,120 Lakhs
Project duration83 months
Project categoryResidential
Locality
Original start date22 Feb 2014
Proposed start date22 Feb 2014

Inventory

Total units1241
Unit TypeUnitsCarpet Area (sqm)
2 BHK60046.7–140.07
3 BHK51370.09–219.28
4 BHK12870.01–219.28

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310012345
Emailrera.ivrpdpl@gmail.com
Coordinator8588033336
Address1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
III-227/710

Revalidated: WILL BE APPLIED (6 Dec 2023)

6 Dec 20136 Dec 2018

Revalidated upto: 6 Dec 2023

30 Dec 20196 Dec 2023
CAP/III-277/1102

Revalidated: CAP/III-277/1102 (15 Feb 2019)

15 Feb 201914 Feb 2024

Revalidated upto: 1 Jan 1900

30 Dec 201924 Feb 2024

Land Parcels

Khasra No.AreaPlot Type
GH-01sec-118
GH 01142967Plot

Approved Unit Plan

Unit plan rows on file311
Total flats (sum of rows)1241
BlocksA1, A2, B3, B4, B7, C1, C2, C3, E1, F1
Floor types2 BHK, 3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
469624 Oct 2013

Frequently Asked Questions

What is the RERA registration number of THE ROMANO (PHASE-II)?

The RERA registration number of THE ROMANO (PHASE-II) is UPRERAPRJ5705, as recorded on the UP-RERA portal.

What is the RERA status of THE ROMANO (PHASE-II)?

As reported by UP-RERA, the status of THE ROMANO (PHASE-II) is "Registered".

Where is THE ROMANO (PHASE-II) located?

As reported to UP-RERA, THE ROMANO (PHASE-II) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will THE ROMANO (PHASE-II) be completed?

The latest completion date reported to UP-RERA for THE ROMANO (PHASE-II) is 30 Dec 2019.

Is THE ROMANO (PHASE-II) delayed?

Measured against the latest completion date reported to UP-RERA, THE ROMANO (PHASE-II) is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026