Estanzo

Timeline Bar

Registered31 Jul 2017
Promised31 Dec 2020
Today4 Aug 2026

Timeline

Promised completion31 Dec 2020
Revised completion31 Dec 2020
Actual completion
Possession delay67 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,06,000
Project cost (in ₹ Lakhs)₹26,500 Lakhs
Project duration103 months
Project categoryResidential
Locality
Original start date6 Dec 2013
Proposed start date6 Dec 2013

Inventory

Total units753
Unit TypeUnitsCarpet Area (sqm)
1 BHK253.81–54.2
2 BHK33068.14–68.85
3 BHK42183.49–108.71

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310012345
Emailrera.ivrpdpl@gmail.com
Coordinator9582006011
Address1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/2015/III-277/7106 Dec 20136 Dec 201831 Dec 20206 Dec 2023

Land Parcels

Khasra No.AreaPlot Type
GH-01, SECTOR 118, NOIDA142967Plot

Approved Unit Plan

Unit plan rows on file361
Total flats (sum of rows)753
BlocksTOWER F, TOWER G, TOWER K, TOWER-H, TOWER-J
Floor types1 BHK, 2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of AMBROSIA (Phase-2: Tower F G H J & K)?

The RERA registration number of AMBROSIA (Phase-2: Tower F G H J & K) is UPRERAPRJ5823, as recorded on the UP-RERA portal.

What is the RERA status of AMBROSIA (Phase-2: Tower F G H J & K)?

As reported by UP-RERA, the status of AMBROSIA (Phase-2: Tower F G H J & K) is "Registered".

Where is AMBROSIA (Phase-2: Tower F G H J & K) located?

As reported to UP-RERA, AMBROSIA (Phase-2: Tower F G H J & K) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will AMBROSIA (Phase-2: Tower F G H J & K) be completed?

The latest completion date reported to UP-RERA for AMBROSIA (Phase-2: Tower F G H J & K) is 31 Dec 2020.

Is AMBROSIA (Phase-2: Tower F G H J & K) delayed?

Measured against the latest completion date reported to UP-RERA, AMBROSIA (Phase-2: Tower F G H J & K) is 67 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026