Registered31 Jul 2017
Promised31 Dec 2019
Today4 Aug 2026

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion
Possession delay79 mo delay

Registration & Cost Details

Registration fee (in ₹)₹87,500
Project cost (in ₹ Lakhs)₹32,300 Lakhs
Project duration100 months
Project categoryResidential
Locality
Original start date6 Dec 2013
Proposed start date6 Dec 2013

Inventory

Total units854
Unit TypeUnitsCarpet Area (sqm)
1 BHK344.97–53.81
2 BHK71144.97–82.55
3 BHK14082.47–82.55

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310012345
Emailrera.ivrpdpl@gmail.com
Coordinator9582006011
Address1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/CAP/2015/III-277/7106 Dec 20136 Dec 201831 Dec 20196 Dec 2023

Land Parcels

Khasra No.AreaPlot Type
GH-01, SECTOR 118, NOIDA142967Plot

Approved Unit Plan

Unit plan rows on file479
Total flats (sum of rows)854
BlocksTOWER A, TOWER B, TOWER C, TOWER D, TOWER E
Floor types1 BHK, 2 BHK, 3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
230119 Apr 2012

Frequently Asked Questions

What is the RERA registration number of AMBROSIA (Phase-1: Tower A B C D & E)?

The RERA registration number of AMBROSIA (Phase-1: Tower A B C D & E) is UPRERAPRJ5814, as recorded on the UP-RERA portal.

What is the RERA status of AMBROSIA (Phase-1: Tower A B C D & E)?

As reported by UP-RERA, the status of AMBROSIA (Phase-1: Tower A B C D & E) is "Registered".

Where is AMBROSIA (Phase-1: Tower A B C D & E) located?

As reported to UP-RERA, AMBROSIA (Phase-1: Tower A B C D & E) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will AMBROSIA (Phase-1: Tower A B C D & E) be completed?

The latest completion date reported to UP-RERA for AMBROSIA (Phase-1: Tower A B C D & E) is 31 Dec 2019.

Is AMBROSIA (Phase-1: Tower A B C D & E) delayed?

Measured against the latest completion date reported to UP-RERA, AMBROSIA (Phase-1: Tower A B C D & E) is 79 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.