Registered28 Jul 2017
Promised31 Dec 2022
NCLT25 Feb 2025

Timeline

Promised completion31 Dec 2022
Revised completion31 Dec 2022
Actual completion
Possession delay43 mo delay

Registration & Cost Details

Registration fee (in ₹)₹44,500
Project cost (in ₹ Lakhs)₹8,323 Lakhs
Project duration66 months
Project categoryResidential
Locality
Original start date2 Sept 2015
Proposed start date1 Jan 2018

Inventory

Total units240
Unit TypeUnitsCarpet Area (sqm)
2 BHK24060.3–66.25

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile6389022190
Emailreraansalapi@gmail.com
Coordinator6389022193
Address115, ANSAL BHAWAN, 16, KG MARG, NEW DELHI-110001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
3929821 Dec 201520 Dec 202031 Dec 202220 Dec 2023

Land Parcels

Khasra No.AreaPlot Type
222, 272, 2737896.74 Sq. Meter
2231790Khasra
2726070Khasra
2737480Khasra

Approved Unit Plan

Unit plan rows on file160
Total flats (sum of rows)240
BlocksC - 1, C - 2
Floor types2 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
685212 Apr 2016
178817 Dec 2011
1474631 Jul 2013
188926 Feb 2007
1289 May 2007

Frequently Asked Questions

What is the RERA registration number of ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH?

The RERA registration number of ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH is UPRERAPRJ3545, as recorded on the UP-RERA portal.

What is the RERA status of ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH?

As reported by UP-RERA, the status of ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH is "NCLT".

Where is ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH located?

As reported to UP-RERA, ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH is located at Lucknow, Lucknow, Uttar Pradesh.

When will ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH be completed?

The latest completion date reported to UP-RERA for ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH is 31 Dec 2022.

Is ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH delayed?

Measured against the latest completion date reported to UP-RERA, ANSAL API-GREEN FIELD RESIDENTIA TOWER C1 & C2, GH is 43 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.