Timeline Bar

Registered5 Aug 2017
Promised30 May 2021
Today3 Aug 2026

Timeline

Promised completion30 May 2021
Revised completion30 May 2021
Actual completion
Possession delay62 mo delay

Registration & Cost Details

Registration fee (in ₹)₹5,86,000
Project cost (in ₹ Lakhs)₹46,500 Lakhs
Project duration54 months
Project categoryResidential
Locality
Original start date1 Jun 2017
Proposed start date1 Jun 2017

Inventory

Total units1172
Unit TypeUnitsCarpet Area (sqm)
2 BHK25857.89–66.91
3 BHK85666.91–98.72
4 BHK58104.31

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810643744
Emailceo@apexindia.in
Coordinator9810643744
AddressCharanjeet Singh

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
98112 Apr 201711 Apr 202230 May 2021
981

Revalidated: 981 (12 Apr 2017)

12 Apr 201711 Apr 2022

Revalidated upto: 1 Jan 1900

30 May 202111 Apr 2024

Land Parcels

Khasra No.AreaPlot Type
20126000
4/BS2-326000Plot

Approved Unit Plan

Unit plan rows on file15
Total flats (sum of rows)1172
BlocksA, B, C, D, E, F, G
Floor types2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
795728 Dec 2012

Frequently Asked Questions

What is the RERA registration number of APEX THE KREMLIN?

The RERA registration number of APEX THE KREMLIN is UPRERAPRJ7601, as recorded on the UP-RERA portal.

What is the RERA status of APEX THE KREMLIN?

As reported by UP-RERA, the status of APEX THE KREMLIN is "Registered".

Where is APEX THE KREMLIN located?

As reported to UP-RERA, APEX THE KREMLIN is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will APEX THE KREMLIN be completed?

The latest completion date reported to UP-RERA for APEX THE KREMLIN is 30 May 2021.

Is APEX THE KREMLIN delayed?

Measured against the latest completion date reported to UP-RERA, APEX THE KREMLIN is 62 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026