T HOMES PHASE-1 is a RERA-registered real-estate project in Ghaziabad (RERA ID UPRERAPRJ17268). Its RERA-registered completion deadline (30 Apr 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ17268 |
| Applicant type | Company |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 20 Sept 2018 |
| Project duration | 74 |
| Address | Ghaziabad, Ghaziabad |
| RERA registered | 4 Aug 2018 |
| Promised completion | 30 Apr 2024 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹47,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 184 | 11–111 |
| 3 BHK | 321 | 54–96 |
| SHOP | 25 | 16–50 |
| 5 BHK | 52 | 186 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 1871/NIPRA-52/2017/VANI-5 | 30 Jun 2017 | 29 Jun 2022 | 30 Apr 2024 |
| Khasra | Area | Type |
|---|---|---|
| 3/SP-03 Sector 3, Siddharth Vihar, Ghaziabad-20100 | 8375 | Plot |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
Other projects registered in Ghaziabad.
Yes. T HOMES PHASE-1 is registered with UPRERA under registration number UPRERAPRJ17268, registered on 4 Aug 2018. Estanzo reproduces that filing; it does not verify the work behind it.
T HOMES PHASE-1 is 27 months past the completion date filed with UPRERA (30 Apr 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
T HOMES PHASE-1 is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗