Estanzo

Timeline Bar

Registered18 Jun 2021
Completed30 Jan 2025
Promised13 Jul 2025

Timeline

Promised completion13 Jul 2025
Revised completion13 Jul 2025
Actual completion30 Jan 2025
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹38,000
Project cost (in ₹ Lakhs)₹6,000 Lakhs
Project duration51 months
Project categoryResidential
Locality
Original start date
Proposed start date3 May 2021

Inventory

Total units829
Unit TypeUnitsCarpet Area (sqm)
3 BHK79370.4–88.34
PENTHOUSE2183–131.47
SHOP158.46–20.03

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9839236688
Emailprashant.singh@esquarehomes.com
Coordinator9839236688
AddressB-56A, VIBHOOTI KHAND, GOMTI NAGAR, LUCKNOW-226010

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q2100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
MAP-2019052719224077314 Jul 202013 Jul 202513 Jul 202513 Jan 2026

Land Parcels

Khasra No.AreaPlot Type
watersupplyplan0Khasra
ElectricitysupplyPln1Khasra
WasteDisposalPlan2Khasra
Developmentworkplan3Khasra
ProformaofConveyanceDeed4Khasra
Consortiumagreement5Khasra
Allotmentletter6Khasra
2160.405Khasra
2160.253Khasra
Project Land owner ship8Khasra
NEC by Lyer9Khasra
RERAFORM-B10Khasra
RA-1(Updated)11Khasra

Approved Unit Plan

Unit plan rows on file133
Total flats (sum of rows)829
Total shops15
BlocksAspire
Floor types3 BHK, PENTHOUSE, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Aspire?

The RERA registration number of Aspire is UPRERAPRJ450329, as recorded on the UP-RERA portal.

What is the RERA status of Aspire?

As reported by UP-RERA, the status of Aspire is "Registered".

Where is Aspire located?

As reported to UP-RERA, Aspire is located at Lucknow, Lucknow, Uttar Pradesh.

Is Aspire completed?

As reported to UP-RERA, Aspire was completed on 30 Jan 2025.

Is Aspire delayed?

Measured against the latest completion date reported to UP-RERA, Aspire is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026