Valencia County East GH-18 is a RERA-registered residential project by M/s Shalimar Lakecity Private Limited (Formerly M/s ANS Developers Private Limited) in Lucknow (RERA ID UPRERAPRJ707640). Registered with a completion deadline of 20 Feb 2027.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ707640 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 20 Oct 2022 |
| Project duration | 53 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Company |
| Applicant address | 11th floor, Shalimar Titanium Vibhuti Khand Gomti Nagar Lucknow-226010 UP India |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
Group Housing/05115/LDA/BP/21-22/1761/20052022
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 3 Dec 2022 |
| Original completion | 20 Oct 2026 |
| Revised completion | 20 Feb 2027 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹2,29,500 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
| Configuration | Units | Carpet area |
|---|---|---|
| VILLA | 51 | 126-264 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| 1 · VILLA | 4 | 1 | 264 |
| 2 · VILLA | 4 | 1 | 264 |
| 3 · VILLA | 4 | 1 | 264 |
| 4 · VILLA | 4 | 1 | 264 |
| 5 · VILLA | 4 | 1 | 264 |
| 6 · VILLA | 4 | 1 | 126 |
| 7 · VILLA | 4 | 1 | 126 |
| 8 · VILLA | 4 | 1 | 126 |
| 9 · VILLA | 4 | 1 | 126 |
| 10 · VILLA | 4 | 1 | 126 |
| 11 · VILLA | 4 | 1 | 126 |
| 12 · VILLA | 4 | 1 | 126 |
| 14 · VILLA | 4 | 1 | 126 |
| 15 · VILLA | 4 | 1 | 126 |
| 16 · VILLA | 4 | 1 | 126 |
| 17 · VILLA | 4 | 1 | 126 |
| 18 · VILLA | 4 | 1 | 126 |
| 19 · VILLA | 4 | 1 | 126 |
| 20 · VILLA | 4 | 1 | 126 |
| 21 · VILLA | 4 | 1 | 126 |
| 22 · VILLA | 4 | 1 | 126 |
| 23 · VILLA | 4 | 1 | 126 |
| 24 · VILLA | 4 | 1 | 126 |
| 25 · VILLA | 4 | 1 | 126 |
| 26 · VILLA | 4 | 1 | 126 |
| 27 · VILLA | 4 | 1 | 126 |
| 28 · VILLA | 4 | 1 | 126 |
| 29 · VILLA | 4 | 1 | 126 |
| 30 · VILLA | 4 | 1 | 126 |
| 31 · VILLA | 4 | 1 | 126 |
| 32 · VILLA | 4 | 1 | 126 |
| 33 · VILLA | 4 | 1 | 126 |
| 34 · VILLA | 4 | 1 | 126 |
| 35 · VILLA | 4 | 1 | 126 |
| 36 · VILLA | 4 | 1 | 126 |
| 37 · VILLA | 4 | 1 | 126 |
| 64 · VILLA | 4 | 1 | 126 |
| 65 · VILLA | 4 | 1 | 126 |
| 66 · VILLA | 4 | 1 | 126 |
| 67 · VILLA | 4 | 1 | 126 |
| 68 · VILLA | 4 | 1 | 126 |
| 69 · VILLA | 4 | 1 | 126 |
| 70 · VILLA | 4 | 1 | 126 |
| 71 · VILLA | 4 | 1 | 126 |
| 72 · VILLA | 4 | 1 | 126 |
| 73 · VILLA | 4 | 1 | 151 |
| 74 · VILLA | 4 | 1 | 151 |
| 75 · VILLA | 4 | 1 | 151 |
| 76 · VILLA | 4 | 1 | 151 |
| 77 · VILLA | 4 | 1 | 151 |
| 78 · VILLA | 4 | 1 | 151 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots This is single plot polygon shaped , having total 1 no. of entry gate/ exit gate from the 30m wide front road. Site is surrounded by other plots of developers from one side from two sided with 45 mtr & 30 mtr roads respectively and one side by others plot. |
| 2 | Boundary Wall 1.8 - 2.1m high and 200 mm thick Boundary wall designed . Brick Work of 9inches and rcc work in column and beam may be used as per design. Entrance and exit gates are developed with boundary. |
| 3 | Road Work Trimix finish/ bitumen will be used as per design suggested by the Architect for internal road. |
| 4 | Footpaths All internal roads will have narrow footpath with matt finish tiles pavers or equivalent finishes. |
| 5 | Water Supply Including Drinking Water Facilities Ground water may also be used, Als users can used their individual RO system as per their requirement. Overhead tanks shall be provided on building terrace for distribution through gravity. |
| 6 | Sewer System Centralized Sewerage system shall be Provided. All Sewerage water shall go to the central STP for treatment. After treatment ,water shall be recycled and it will be used in gardening, flush tanks.Oveflow from the central STP shall be connected with the Municipal sewerage system. |
| 7 | Drain Storm water system shall be Provided. Storm water from Roads and other landscape area shall be connected to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connected with Municiple drain line. |
| 8 | Parks There are many green/ landscape area in front/ beside of Villas including green parks, play areas for children and different recreational activities. |
| 9 | Tree Planting There are different type of tree plantation is proposed at site in order to maintatin greenary and natural view. |
| 10 | Design For Electric Supply Including Street Lighting We have designed the system as per local electricity board and considered centralized Transformer,HT panel,LT Panel,Feeder Pillar and DG back for common service like External lighting, STP, Pump room etc. |
| 11 | Community Buildings NA (Community building already exist in township.) |
| 12 | Treatment and Disposal System of Sewage and Sullage water Centralized Sewerage system shall be Provided. All Sewerage water shall go to the central STP for treatement, after treatement ,water shall be recycled and it will be used in gardening, flush tanks. Oveflow from the STP shall be connected with the Municiple sewarage system. |
| 13 | Solid Waste Management And Disposal System There are proper garbage collection area provided for the solid waste management. |
| 14 | Water Conservation System A well designed rain water harvesting system shall be provided for the whole building/villa complex to conserve water. |
| 15 | Energy Management System Including Use of Renewable Energy We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor. |
| 16 | Fire Protection And Fire Safety System All the fire norms shall be followed as NBC and approval of fire department |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Green/ landscape area in front/ beside of Villas including green parks, play areas for children and different recreational activities. |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work Lush green shrubs at every vacant space on ground. |
Registered agents
25 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | Abhishek Kumar | UPRERAAGT17780 |
| 3 | Adish Jain | UPRERAAGT21672 |
| 4 | Anoop Shukla | UPRERAAGT20695 |
| 5 | ARVIND KUMAR | UPRERAAGT15927 |
| 6 | ASA FINCAP ADVISORS LLP | UPRERAAGT10926 |
| 7 | Asit Gupta C/O Dwelling Homes | UPRERAAGT20902 |
| 8 | BAJRANG MISHRA C/O BASE INFRA SOLUTION | UPRERAAGT13635 |
| 9 | BASECAMP INFRA CONSULTANTS (OPC) PRIVATE LIMITED | UPRERAAGT14759 |
| 10 | GOLDEN ESTATE | UPRERAAGT10397 |
| 11 | GOLDEN STAR REAL ESTATES | UPRERAAGT10303 |
| 12 | Karshni Buildwell Pvt Ltd | UPRERAAGT11401 |
| 13 | MOHAMMAD RASHID | UPRERAAGT15251 |
| 14 | Mukesh kumar Sharma | UPRERAAGT11494 |
| 15 | REALTYSTRUCTURE INFRATECH PRIVATE LIMITED | UPRERAAGT10144 |
| 16 | Rohit Chandani | UPRERAAGT11546 |
| 17 | SANJEEV KUMAR BANKA | UPRERAAGT10894 |
| 18 | Saurabh Gupta | UPRERAAGT14655 |
| 19 | Shashank Shukla | UPRERAAGT17091 |
| 20 | SINAN REALTY LLP | UPRERAAGT11785 |
| 21 | Smart InfraReality Private Limited | UPRERAAGT10057 |
| 22 | VINAY KUMAR SINGH | UPRERAAGT11226 |
| 23 | VISHESH SRIVASTAVA | UPRERAAGT11416 |
| 24 | VIVEK VERMA | UPRERAAGT18719 |
| 25 | Vivekanand Shukla | UPRERAAGT21638 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 16 Jun 2027.
Sanctioned by Lucknow Development Authority · 44,812 sqm of land · an approved plan of 51 blocks and 51 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| Group Housing/05115/LDA/BP/21-22/1761/20052022 | 17 Jun 2022 | 16 Jun 2027 | 16 Jun 2030 | 20 Oct 2026 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 20 Feb 2027.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 20 Oct 2026 | 20 Feb 2027 | — |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 134, 135, 138 Ka, 138Kha, 138 Ga, 140, 143 Ka, 143 Kha, 144, 145, 146, 147, 148, 149, 150 Ka, 150 Kha, 150 Ga, 150 Da, 150 Gha, 151, 152, 153, 154, 155, 156Ka, 156 Kha, 157, 158, 159, 160, 161, 162, 163 Part, 164, 165, 166, 167, 168, 169, 170, 171, 172, 173, 174, 175, 177, 180, 181, 182, 183, 184, 244, 245, 246, 248, 249, 250, 251 | 44812 | Khasra |
| Registry document · 4251 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 4798 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 5396 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Lease deed · 9652 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Khatauni extract · Khatauni extracts An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Khatauni extracts for Khasra 147, 149, 251 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Sale deed · 8785 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8785 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8785 The registered deed by which the promoter bought the land. | PDF ↗ |
| Registry document · 2587 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Sale deed · 9011 The registered deed by which the promoter bought the land. | PDF ↗ |
| Khatauni extract · Land Acquisition Letter u/s 4 for Khasra 147, 149, 251 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Sale deed · 9010 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 17453 The registered deed by which the promoter bought the land. | PDF ↗ |
| Khatauni extract · Land Area Chart An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Electricity Plan_Valencia County East GH-18 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Water Supply and Waste Disposal Plan_Valencia County East GH-18 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Reply to query letter no. 13460/UPRERA/Tech Cell/2022-23 dated 18.11.2022 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Reply to query letter no. 13742/UPRERA/Project Reg/2022-23 dated 29.11.2022 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Revised Affidavit submission against query letter no. 13742/UPRERA/Project Reg/2022-23 dated 29.11. An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 21 Jul 2022 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 21 Jul 2022 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 22 Nov 2022 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 22 Nov 2022 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 2 Nov 2022 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 2 Nov 2022 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 2 Nov 2022 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 2 Nov 2022 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 21 Jul 2022 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 2 Nov 2022 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 28 Oct 2022 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 28 Oct 2022 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 21 Jul 2022 ↗ |
Quarterly progress reports
15 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
15 quarterly progress reports are on file with UPRERA, covering 2022-Q3 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 60% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 60% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 77.66% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 77.66% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | M/s Shalimar Lakecity Private Limited (Formerly M/s ANS Developers Private Limited) |
| Role | Promoter · current |
| RERA ID | UPRERAPRM10813 |
| PAN | AAFCA9848N |
| CIN / TAN | U70109DL2006PTC389838 |
| Name of chairman | Mr. Anwar Rizvi |
| Registered address | 11th floor, Shalimar Titanium Vibhuti Khand Gomti Nagar Lucknow-226010 UP India |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | M/S ANS DPL COL AC VALENCIA COUNTY EAST GH-18BankHDFC BankBranchVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch addressVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCHDFC0004805 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | M/S ANS DPL SEP AC VALENCIA COUNTY EAST GH-18BankHDFC BankBranchVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch addressVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCHDFC0004805 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | M/S ANS DPL TRANS AC VALENCIA COUNTY EAST GH-18BankHDFC BankBranchVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch addressVIBHUTI KHAND, GOMTI NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCHDFC0004805 |
What has changed on this record
3 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 33 (Under Registration - 1 ) → 33 (Under Registration - 0 ) changed in Estanzo’s record | 18 Oct 2026 |
| Revised completion date on file | 2026-10-20 → 2027-02-20 changed in Estanzo’s record | 7 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 32 (Under Registration - 0 ) → 33 (Under Registration - 1 ) changed in Estanzo’s record | 11 Sept 2026 |
| Revised completion date on file | changed in Estanzo’s record · 7 Oct 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 18 Oct 2026 · 2 movements on record |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Valencia County East GH-18
Is Valencia County East GH-18 RERA registered?
Yes. Valencia County East GH-18 is registered with UPRERA under registration number UPRERAPRJ707640, registered on 3 Dec 2022. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Valencia County East GH-18?
The completion date filed with UPRERA is 20 Feb 2027. No completion certificate is on record yet.
Who is the builder of Valencia County East GH-18?
M/s Shalimar Lakecity Private Limited (Formerly M/s ANS Developers Private Limited) is the promoter entity that filed Valencia County East GH-18 with UPRERA (promoter RERA ID UPRERAPRM10813). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted Valencia County East GH-18 more time to complete?
UPRERA's record carries 1 completion extension for Valencia County East GH-18, the latest running to 20 Feb 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does Valencia County East GH-18 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Valencia County East GH-18 located?
Valencia County East GH-18 is registered in Lucknow, as filed with UPRERA.
What configurations are available in Valencia County East GH-18?
The unit plan filed with UPRERA lists VILLA. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Valencia County East GH-18?
The approved unit plan filed with UPRERA runs from 126 to 264 m² of carpet area (about 1,358 to 2,839 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Valencia County East GH-18?
The approved unit plan describes 51 blocks and 51 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Valencia County East GH-18?
About 5 units per acre: 51 planned units across 11.07 acres (44,812 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗