Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in GondaUPRERADelayed 34 mo
Home › Projects › Gonda › Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda

Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda

UPRERADelayed 34 moRegisteredConstruction 100% · 2026 Q1updated 4 Aug 2026

Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is a RERA-registered real-estate project in Gonda (RERA ID UPRERAPRJ375818). Its RERA-registered completion deadline (30 Sept 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
34 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹7
Land area
not reported
Units (from plan)
240
Density (derived)
not reported
Towers
not reported
Config
1 BHK
Carpet
23–23
Registered
27 Feb 2019

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2026 Q1
—Q2'24
—Q3'24
—Q4'24
92%Q1'25
92%Q2'25
100%Q3'25
100%Q4'25
100%Q1'26

Basic details

RERA IDUPRERAPRJ375818
Applicant typeCompetent authority
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start1 Apr 2019
Project duration90
AddressGonda, Gonda

Registration & timeline

RERA registered27 Feb 2019
Promised completion31 Mar 2023
Revised completion30 Sept 2023
Completion certificate filed— not on record
Registration fee₹30,500

Inventory

derived from unit plan
Total units · towers · floors240 · 1 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK24023
Towers as filedB5,B6,B9,B10,B11
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

2 permits
Permit no.DateValid uptoRevised end
418/AP-3/PMAY20 Aug 201819 Aug 202331 Mar 2023
418/AP-3/PMAY20 Aug 201819 Aug 202330 Sept 2023

Land & documents

1 filing
KhasraAreaType
1355503Khasra

Quarterly progress reports

25 filed reports
QuarterConstructionCertificatesSource
2020-Q1—CA · Arch · Engview ↗
2020-Q2—CA · Arch · Engview ↗
2020-Q3—CA · Arch · Engview ↗
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q192%CA · Arch · Engview ↗
2025-Q292%CA · Arch · Engview ↗
2025-Q3100%CA · Arch · Engview ↗
2025-Q4100%CA · Arch · Engview ↗
2026-Q1100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1.

Nearby projects

Gonda

Other projects registered in Gonda.

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.
UPRERA ▲ 20 mo
GONARD CITY
UPRERA no delay on record
Plotted development work at Gonda-Faizabaad Marg Bhoomi Vikas Evam Grihstan Yojna Gonda.
UPRERA ▲ 32 mo
Plotted development work of 150 nos plots in second phase at Gonda-Faizabaad Marg Yojna in Distt Gonda
UPRERA ▲ 20 mo

Common questions about Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda

Is Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda RERA registered?

Yes. Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is registered with UPRERA under registration number UPRERAPRJ375818, registered on 27 Feb 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Is Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda delayed?

Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is 34 months past the completion date filed with UPRERA (30 Sept 2023), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda located?

Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is registered in Gonda, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 34 mo
QPR filingNo default reported
DistrictGonda
Last updated4 Aug 2026

Location

AddressGonda
View on map ↗

RERA buyer helpline

Coordinator8795810346
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=tfcmQ358RnQ=&hfFlag=wCMeRpsrl0s=&NPJ6RAme=a89NPbir64thsZSAfZ5px9PAFhyubbsIcWw08wbhga8qqhkrVLWQZ+ykMHzJr0epe034ujdQ68NEmzPq3CC9XVSPcgc37Qf2n5SYXy4doj5RBrL0IG+INQ==&PaURJEMAN4=ZL9MNERkNdbYvhy2l3QD2g==&IRSAHEB=D6PY3lyims8=)