Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is a RERA-registered real-estate project in Gonda (RERA ID UPRERAPRJ375818). Its RERA-registered completion deadline (30 Sept 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ375818 |
| Applicant type | Competent authority |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Apr 2019 |
| Project duration | 90 |
| Address | Gonda, Gonda |
| RERA registered | 27 Feb 2019 |
| Promised completion | 31 Mar 2023 |
| Revised completion | 30 Sept 2023 |
| Completion certificate filed | — not on record |
| Registration fee | ₹30,500 |
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 240 | 23 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 418/AP-3/PMAY | 20 Aug 2018 | 19 Aug 2023 | 31 Mar 2023 |
| 418/AP-3/PMAY | 20 Aug 2018 | 19 Aug 2023 | 30 Sept 2023 |
| Khasra | Area | Type |
|---|---|---|
| 135 | 5503 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
| 2024-Q4 | — | CA · Arch · Eng | view ↗ |
| 2025-Q1 | 92% | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 92% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 100% | CA · Arch · Eng | view ↗ |
| 2025-Q4 | 100% | CA · Arch · Eng | view ↗ |
| 2026-Q1 | 100% | CA · Arch · Eng | view ↗ |
Other projects registered in Gonda.
Yes. Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is registered with UPRERA under registration number UPRERAPRJ375818, registered on 27 Feb 2019. Estanzo reproduces that filing; it does not verify the work behind it.
Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is 34 months past the completion date filed with UPRERA (30 Sept 2023), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda is registered in Gonda, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗