Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.UPRERADelayed 20 mo
Home › Projects › Gonda › Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.

UPRERADelayed 20 moRegisteredConstruction 100% · 2026 Q1updated 4 Aug 2026

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is a RERA-registered real-estate project in Gonda (RERA ID UPRERAPRJ814610). Its RERA-registered completion deadline (30 Nov 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
20 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹25
Land area
not reported
Units (from plan)
396
Density (derived)
not reported
Towers
not reported
Config
1 BHK
Carpet
23–23
Registered
29 Jul 2020

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2026 Q1
—Q2'24
—Q3'24
—Q4'24
—Q1'25
84%Q2'25
100%Q3'25
100%Q4'25
100%Q1'26

Basic details

RERA IDUPRERAPRJ814610
Applicant typeCompetent authority
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start1 Dec 2020
Project duration66
AddressGonda, Gonda

Registration & timeline

RERA registered29 Jul 2020
Promised completion30 Nov 2024
Revised completion— none granted
Completion certificate filed29 May 2026
Registration fee₹50,500

Inventory

derived from unit plan
Total units · towers · floors396 · 9 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK39623
Towers as filedB1 · B11 · B2 · B3 · B4 · B5 · B6 · B7 · B8
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

2 permits
Permit no.DateValid uptoRevised end
418/AP-3/PMAY27 Aug 201826 Aug 202330 Nov 2024
418/AP-3/PMAY27 Aug 201826 Aug 202330 Nov 2024

Land & documents

1 filing
KhasraAreaType
1359098Khasra

Quarterly progress reports

23 filed reports
QuarterConstructionCertificatesSource
2020-Q3—CA · Arch · Engview ↗
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q284%CA · Arch · Engview ↗
2025-Q3100%CA · Arch · Engview ↗
2025-Q4100%CA · Arch · Engview ↗
2026-Q1100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1.

Nearby projects

Gonda

Other projects registered in Gonda.

Construction of 132 Nos. PMAY (URBAN) Block B6, B9 & B10 at First Phase in Gonda
UPRERA ▲ 34 mo
GONARD CITY
UPRERA no delay on record
Plotted development work at Gonda-Faizabaad Marg Bhoomi Vikas Evam Grihstan Yojna Gonda.
UPRERA ▲ 32 mo
Plotted development work of 150 nos plots in second phase at Gonda-Faizabaad Marg Yojna in Distt Gonda
UPRERA ▲ 20 mo

Common questions about Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.

Is Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. RERA registered?

Yes. Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is registered with UPRERA under registration number UPRERAPRJ814610, registered on 29 Jul 2020. Estanzo reproduces that filing; it does not verify the work behind it.

Has Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. been completed?

UPRERA still lists Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. as Registered, so it is not shown as completed here. A completion certificate dated 29 May 2026 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Where is Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. located?

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is registered in Gonda, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 20 mo
QPR filingNo default reported
DistrictGonda
Last updated4 Aug 2026

Location

AddressGonda
View on map ↗

RERA buyer helpline

Coordinator8795810032
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=N086z6yH/lI=&hfFlag=wCMeRpsrl0s=&NPJ6RAme=a89NPbir64thsZSAfZ5px7wuGqPHsrFgpvr0HpdRh8BM4on8wZPtYzKowr2N/XWuLsLoBKd9BUUfLvnIZi6H45mXSZzKOHxc&PaURJEMAN4=ZL9MNERkNdZ8/hAaX1KCXg==&IRSAHEB=D6PY3lyims8=)