Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.

UPRERARegistered

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is a RERA-registered residential project by U.P. Awas Evam Vikas Parishad in Gonda (RERA ID UPRERAPRJ814610). Registered with a completion deadline of 30 May 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
84%Q3'25
100%Q4'25
100%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ814610
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryU.P. Awas Evam Vikas Parishad
Proposed start1 Dec 2020
Project duration66 months
AddressGonda, Gonda
TehsilGonda
Applicant typeCompetent authority
Applicant address104 Mahatma Gandhi Marg, Lucknow
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    418/AP-3/PMAY

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered29 Jul 2020
Original completion30 Nov 2024
Revised completion30 May 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary29 May 2026
Registration fee₹50,500
Sanctioning authorityU.P. Awas Evam Vikas Parishad

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors396 · 9 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK39623
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
B1 · 1 BHK44823
B11 · 1 BHK44823
B2 · 1 BHK44823
B3 · 1 BHK44823
B4 · 1 BHK44823
B5 · 1 BHK41223
B6 · 1 BHK44823
B7 · 1 BHK44823
B8 · 1 BHK44823
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Arvind Dev
License CA/97/22345
Unit-03,Neelgiri Complex,Indira Nagar Lucknow
Engineer
Sanjay Jaiswal
Ms Perceptions,11/165,Vasundhara,Gaziabad
Contractor
Name of Contractor will be final after Tender process.
Name of Contractor will be final after Tender process.
Sr.Development work declared to RERA
1Demarcation of Plots
As per Layout Plan by UPAVP.
2Boundary Wall
Not Applicable
3Road Work
Yet to be started as per Layout plan.Internal Road work will be done by UPAVP and External Road work will be done by UPPWD as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018. Bituminous road is proposed with Base of WMM/WBM and including GSB.
4Footpaths
Yet to be started as per Layout plan.Internal Footpath work will be done by UPAVP and External Footpath work will be done by UPPWD as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018. Footpath prosed as per UPAVP guidelines by Interlocking tiles or SOB Brick soling.
5Water Supply Including Drinking Water Facilities
Yet to be started as per Layout plan.Internal Water Supply Including Drinking Water Facilities work will be done by UPAVP and External Water Supply Including Drinking Water Facilities work will be done by UP JAL NIGAM as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018. Water supply proposed as per UPAVP guidelines with rising main.
6Sewer System
Yet to be started as per Layout plan.Internal Sewer System work will be done by UPAVP and External Sewer System work will be done by UP JAL NIGAM as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018. Septic tamk and soak pit proposed as per site requirement for sewage disposal.
7Drain
Yet to be started as per Layout plan.Internal DRAIN System work will be done by UPAVP and External DRAIN System work will be done by UP LOCAL BODIES as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018. Brick work in 1 ratio 6 proposed for drain with pointing.
8Parks
Yet to be started as per Layout plan by UPAVP.
9Tree Planting
Yet to be started as per Layout plan by UPAVP.
10Design For Electric Supply Including Street Lighting
Yet to be started as per Layout plan.Internal ELECTRIC SUPPLY System work will be done by UPAVP and External ELECTRIC SUPPLY System work will be done by UP PCL as per GO No. 1878/Aath-1-16-80/Miscellaneous/2010 Date-17.10.2018
11Community Buildings
Not applicable.
12Treatment and Disposal System of Sewage and Sullage water
After completion of project will be handed over to local authority.Sewarage and sullage waste Point is situated in Proposede scheme.
13Solid Waste Management And Disposal System
After completion of project will be handed over to local authority.Sewarage and sullage waste Point is situated in Proposede scheme.
14Water Conservation System
Not applicable.
15Energy Management System Including Use of Renewable Energy
Not applicable.
16Fire Protection And Fire Safety System
As per Layout Plan
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not applicable.
18Emergency Evacuation Services
Not applicable.
19Other Miscellaneous Work
As per Layout Plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 26 Aug 2023. 1 of them carries a revalidation, valid to 19 Aug 2026.

Sanctioned by U.P. Awas Evam Vikas Parishad · 9,098 sqm of land · an approved plan of 9 blocks and 396 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
418/AP-3/PMAY27 Aug 201826 Aug 202326 Aug 202530 Nov 2024—
418/AP-3/PMAY27 Aug 201826 Aug 202310 Aug 202630 Nov 202427 Aug 2018
valid to 19 Aug 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 May 2026.

#Granted fromExtended uptoNote
130 Nov 202430 May 2026—

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1359098Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 101/NAJOOL VIBHAG/BHU. HASTA./2018
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Jun 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New11 Jun 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 Jun 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New11 Jun 2020 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New11 Jun 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New8 Jul 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New11 Jun 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New11 Jun 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New11 Jun 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Jun 2020 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New8 Jul 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New25 Jun 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 Jun 2020 ↗

Quarterly progress reports

23 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

23 quarterly progress reports are on file with UPRERA, covering 2020-Q3 to 2026-Q1.

QuarterConstructionCertificates
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q284%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameU.P. Awas Evam Vikas Parishad
RolePromoter · current
RERA IDUPRERAPRM4243
PANAAAJU0103A
CIN / TANLKNU05017F
Registered address104 Mahatma Gandhi Marg, Lucknow
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Executive Engineer Construction Division Two UPAVPBankHDFC BankBranchGondaA/C no.IFSCHDFC0001901
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

20 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)761 (Under Registration - 10 ) → 762 (Under Registration - 11 )
changed in Estanzo’s record
19 Oct 2026
Promoter’s complaints tally (all their projects)760 (Under Registration - 9 ) → 761 (Under Registration - 10 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)759 (Under Registration - 8 ) → 760 (Under Registration - 9 )
changed in Estanzo’s record
15 Oct 2026
Promoter’s complaints tally (all their projects)758 (Under Registration - 7 ) → 759 (Under Registration - 8 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)757 (Under Registration - 6 ) → 758 (Under Registration - 7 )
changed in Estanzo’s record
9 Oct 2026
Promoter’s complaints tally (all their projects)755 (Under Registration - 4 ) → 757 (Under Registration - 6 )
changed in Estanzo’s record
7 Oct 2026
Promoter’s complaints tally (all their projects)753 (Under Registration - 2 ) → 755 (Under Registration - 4 )
changed in Estanzo’s record
5 Oct 2026
Promoter’s complaints tally (all their projects)753 (Under Registration - 6 ) → 753 (Under Registration - 2 )
changed in Estanzo’s record
1 Oct 2026
Promoter’s complaints tally (all their projects)752 (Under Registration - 5 ) → 753 (Under Registration - 6 )
changed in Estanzo’s record
29 Sept 2026
Promoter’s complaints tally (all their projects)751 (Under Registration - 4 ) → 752 (Under Registration - 5 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)750 (Under Registration - 3 ) → 751 (Under Registration - 4 )
changed in Estanzo’s record
17 Sept 2026
Filed document
viewprojects · 18
ENGINEERS CERTIFICATE
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 17
ARCHITECT CERTIFICATE
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 16
CA CERTIFICATE
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 15
Affidavit (Form-B)
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 14
Development Work Plan
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 13
Electricity Supply Plan
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 12
Water Supply Plan
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 11
Waste Disposal Plan
newly filed with RERA
3 Sept 2026
Filed document
viewprojects · 10
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
3 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 19 Oct 2026 · 14 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.

Is Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. RERA registered?

Yes. Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is registered with UPRERA under registration number UPRERAPRJ814610, registered on 29 Jul 2020. Estanzo reproduces that filing; it does not verify the work behind it.

Has Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. been completed?

UPRERA still lists Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. as Registered, so it is not shown as completed here. A completion certificate dated 29 May 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.?

U.P. Awas Evam Vikas Parishad is the promoter entity that filed Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. with UPRERA (promoter RERA ID UPRERAPRM4243). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. more time to complete?

UPRERA's record carries 1 completion extension for Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda., the latest running to 30 May 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. located?

Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda. is registered in Gonda, as filed with UPRERA.

What configurations are available in Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.?

The approved unit plan describes 9 blocks and 396 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Construction of 396 Nos houses under PMAY (U) in second Phase at Gonda.?

About 176 units per acre: 396 planned units across 2.25 acres (9,098 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗