Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY

UPRERARegistered

Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY is a RERA-registered residential project by HAPUR PILKHUWA DEVELOPMENT AUTHORITY in Hapur (RERA ID UPRERAPRJ17948). Registered with a completion deadline of 12 Feb 2022.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ17948
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryHapur Pilkhuwa Development Authority
Proposed start15 Sept 2018
Project duration41 months
AddressHapur, Hapur
TehsilHapur
Applicant typeCompetent authority
Applicant addressPREET VIHAR DELHI ROAD HAPUR UP 245101 INDIA
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Self Approved

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  8. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Nov 2018
Original completion14 Sept 2020
Revised completion12 Feb 2022
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary22 Jun 2022
Registration fee₹56,000
Sanctioning authorityHapur Pilkhuwa Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors408 · 1 · 1 (units from plan)
ConfigurationUnitsCarpet area
1 BHK40823
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A,B,C,D,E,F,G,H,I, · 1 BHK140823
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Probhat Kumar Paul -ATP HPDA
License XXXXXX
HPDA Hapur
Engineer
Prof. M.Z. Khan
I.E.T. Sitapur Road Lucknow.
Contractor
Visa Engineers and Promoter PVT. Ltd. Pundrikaksh Developer PVT. Ltd.
Sector-9 Rohini Delhi, New Ghandi Nagar Ghaziabad
Sr.Development work declared to RERA
1Demarcation of Plots
Well demarcated plots of Anand Vihar Yojna Hapur
2Boundary Wall
No Boundary wall will be made.
3Road Work
External roads are well constructed while internal roads will be with bituminous/CC.
4Footpaths
Not Proposed
5Water Supply Including Drinking Water Facilities
water supply will be provide through ground water storage in under ground/over head reservoir.
6Sewer System
RCC hume pipes will be lay as a sewer line and connect into trunk sewer line of Anand Vihar Yojna
7Drain
Drains are made of RCC and brick work.
8Parks
parks boundary will covered with brick work.
9Tree Planting
Decorative planes are planned along boundary wall.
10Design For Electric Supply Including Street Lighting
each flats have independent electric connection with LED Street lighting are proposed.
11Community Buildings
Beneficiaries may be used Anand Vihar Yojna"s existing Community Building.
12Solid Waste Management And Disposal System
Solid waste will be collect door to door by service facilitater and finally disposed through municipal garrabge Van
13Water Conservation System
roof top water harvesting system will be deployed If necessary.
14Energy Management System Including Use of Renewable Energy
according to requirement.
15Fire Protection And Fire Safety System
Not Applicable
16Social Infrastructure And Other Public Amenities Including Public Health Services
social infrastructure is available with in peripheral of 2 km. .
17Emergency Evacuation Services
Emergency Evacuation services are available near the project.
18Other Miscellaneous Work
as per requirement of project.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 19 Apr 2023.

Sanctioned by Hapur Pilkhuwa Development Authority · 10,200 sqm of land · an approved plan of 1 block and 408 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Self Approved20 Apr 201819 Apr 202319 Apr 202514 Sept 2020
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 12 Feb 2022.

#Granted fromExtended uptoNote
114 Sept 202013 Mar 2021Six months extension in view of force majeure caused by covid-19 pandemic
213 Mar 202112 Feb 2022—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
499, 509,510,51110200Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · XXXXXXXXX
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 Oct 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Oct 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Oct 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New31 Oct 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 Oct 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New31 Oct 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New31 Oct 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New31 Oct 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Oct 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Oct 2018 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗
2020-Q2—CA ↗
2020-Q3—CA ↗
2020-Q4—CA ↗
2021-Q1—CA ↗
2021-Q3—CA ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameHAPUR PILKHUWA DEVELOPMENT AUTHORITY
RolePromoter · current
RERA IDUPRERAPRM12131
PANAAALH0051L
CIN / TANMRTH00293G
Registered addressPREET VIHAR DELHI ROAD HAPUR UP 245101 INDIA
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Hapur

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Vice Chairman HPDA Hapur.BankSyndicate BankBranchHPDA Preet Vihar HapurA/C no.IFSCSYNB0008628
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY

Is Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY RERA registered?

Yes. Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY is registered with UPRERA under registration number UPRERAPRJ17948, registered on 3 Nov 2018. Estanzo reproduces that filing; it does not verify the work behind it.

Has Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY been completed?

UPRERA still lists Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY as Registered, so it is not shown as completed here. A completion certificate dated 22 Jun 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY?

HAPUR PILKHUWA DEVELOPMENT AUTHORITY is the promoter entity that filed Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY with UPRERA (promoter RERA ID UPRERAPRM12131). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY more time to complete?

UPRERA's record carries 2 completion extensions for Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY, the latest running to 12 Feb 2022. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY located?

Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY is registered in Hapur, as filed with UPRERA.

What configurations are available in Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY?

The unit plan filed with UPRERA lists 1 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY?

The approved unit plan describes 1 block and 408 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Construction of 408 EWS Houses in Anand Vihar Housing Scheme Hapur Under PMAY?

About 162 units per acre: 408 planned units across 2.52 acres (10,200 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗