Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) MoradabadUPRERADelayed 5 mo
Home › Projects › Moradabad › Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad

Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad

UPRERADelayed 5 moRegisteredConstruction 100% · 2025 Q3updated 4 Aug 2026

Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad is a RERA-registered real-estate project in Moradabad (RERA ID UPRERAPRJ601076). Its RERA-registered completion deadline (26 Feb 2026) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
5 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹22
Land area
not reported
Units (from plan)
432
Density (derived)
not reported
Towers
not reported
Config
1 BHK
Carpet
23–23
Registered
25 Apr 2023

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2025 Q3
—Q4'23
—Q1'24
—Q2'24
—Q3'24
—Q4'24
—Q1'25
100%Q2'25
100%Q3'25

Basic details

RERA IDUPRERAPRJ601076
Applicant typeCompetent authority
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start26 Feb 2023
Project duration37
AddressMoradabad, Moradabad

Registration & timeline

RERA registered25 Apr 2023
Promised completion26 Feb 2026
Revised completion— none granted
Completion certificate filed25 Feb 2026
Registration fee₹27,000

Inventory

derived from unit plan
Total units · towers · floors432 · 1 · 4 (units from plan)
ConfigurationUnitsCarpet area
1 BHK43223
Towers as filed9
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
07602421 Nov 202226 Feb 202626 Feb 2026

Land & documents

1 filing
KhasraAreaType
804, 805, 30858750Khasra

Quarterly progress reports

12 filed reports
QuarterConstructionCertificatesSource
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q2100%CA · Arch · Engview ↗
2025-Q3100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3.

Nearby projects

Moradabad

Other projects registered in Moradabad.

112 EWS HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 103 mo
137 NO SFS HOUSE IN SECT 14 OF MAJHOLA YOJ. NO 04 VISTAAR MORADABAD
UPRERA no delay on record
176 LIG HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 98 mo
2BHK (S+4) TYPE FLAT SECTOR-9A, MAJHOLA YOJNA-4, P
UPRERA ▲ 95 mo
32 MMIG HOUSES AT SECTOR-15A NEW MORADABAD
UPRERA ▲ 98 mo
48 MIG HOUSES AT GATA NO 387 HARTHALA (RAMGANGA VIHAR)
UPRERA ▲ 95 mo

Common questions about Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad

Is Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad RERA registered?

Yes. Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad is registered with UPRERA under registration number UPRERAPRJ601076, registered on 25 Apr 2023. Estanzo reproduces that filing; it does not verify the work behind it.

Has Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad been completed?

UPRERA still lists Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad as Registered, so it is not shown as completed here. A completion certificate dated 25 Feb 2026 is on the record — RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Where is Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad located?

Construction of 432 No Flat (G+3) under PMAY at Sector-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad is registered in Moradabad, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 5 mo
QPR filingNo default reported
DistrictMoradabad
Last updated4 Aug 2026

Location

AddressMoradabad
View on map ↗

RERA buyer helpline

Coordinator8795810195
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=e7mN+Dnoefc=&hfFlag=1E4qQMUGS4qnuSnOY2gD/g==&NPJ6RAme=a89NPbir64thsZSAfZ5px4dG/s3GRSpkHfc1wzrCwZyMFT+kFmFilSuJN46bkp1p5LM2G2YAZm7qaNHZm2KDiirLd53yI7UFSzuA8Zt3dW1dmxjSLQhQXUZlf8Hlbk6gf7rKtFBlHGw=&PaURJEMAN4=ZL9MNERkNdbb+yyVsLRwfw==&IRSAHEB=D6PY3lyims8=)