Estanzo

Timeline Bar

Registered31 Jul 2017
Completed14 May 2019
Promised15 Feb 2020

Timeline

Promised completion15 Feb 2020
Revised completion15 Feb 2020
Actual completion14 May 2019
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹43,000
Project cost (in ₹ Lakhs)₹3,623 Lakhs
Project duration103 months
Project categoryResidential
Locality
Original start date1 Aug 2011
Proposed start date1 Aug 2011

Inventory

Total units148
Unit TypeUnitsCarpet Area (sqm)
2 BHK4879.77
3 BHK96106.88–107.89
OTHER48.18–8.46

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9670222298
Emailecl@eldecohousing.co.in
Coordinator9670222298
Address2nd Floor, Eldeco Corporate Chamber- I, Vibhuti Khand, (Opp. Mandi Parishad) Gomti Nagar, Lucknow 22

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
3266117 Feb 201216 Feb 201715 Feb 202015 Feb 2020

Land Parcels

Khasra No.AreaPlot Type
4093050
4102740
4371960
4333520
4361560
4381570
4391570
4093050Khasra
4102740Khasra
4371960Khasra
4333520Khasra
4361560Khasra
4381570Khasra
4391570Khasra

Approved Unit Plan

Unit plan rows on file102
Total flats (sum of rows)148
BlocksBreeze Shopping, Breeze-TA, Breeze-TB, Breeze-TC
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
0211 Jul 2014
90715 Feb 2007
82811 Oct 2007
31476 Jun 2008
128315 Feb 2010

Frequently Asked Questions

What is the RERA registration number of Eldeco City Breeze?

The RERA registration number of Eldeco City Breeze is UPRERAPRJ6147, as recorded on the UP-RERA portal.

What is the RERA status of Eldeco City Breeze?

As reported by UP-RERA, the status of Eldeco City Breeze is "Registered".

Where is Eldeco City Breeze located?

As reported to UP-RERA, Eldeco City Breeze is located at Bakshi Ka Talab**, Lucknow, Uttar Pradesh.

Is Eldeco City Breeze completed?

As reported to UP-RERA, Eldeco City Breeze was completed on 14 May 2019.

Is Eldeco City Breeze delayed?

Measured against the latest completion date reported to UP-RERA, Eldeco City Breeze is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026